Supreme Court
Arbitration and MediationContract Law

A broadly worded “or otherwise” clause bars pre-award interest under Section 31(7)(a).

Ms Sharma Enterprises vs National Building Construction Corporation

Supreme CourtJUDGMENT: October 15, 20262 MIN READSOURCE JUDGMENT
A broadly worded “or otherwise” clause bars pre-award interest under Section 31(7)(a).. Ms Sharma Enterprises vs National Building Construction Corporation. Supreme Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

On 11 January 1991, NBCC subcontracted flooring and cladding work at Vashi Railway Station-cum-Commercial Complex to Sharma Enterprises. Delays in the underlying civil works restricted the appellant’s work, and NBCC terminated the contract on 22 September 1992.

Source reference: paras. 3.1–3.2

After protracted proceedings, the arbitrator found the termination wrongful, allowed several monetary claims, and awarded interest at 10% per annum from 22 September 1992, including pre-reference, pendente lite and post-award interest.

Source reference: paras. 3.3–3.4

The High Court, acting under Sections 34 and 37 of the Arbitration and Conciliation Act, 1996, set aside the pre-reference and pendente lite interest, but left the substantive claims and post-award interest undisturbed.

Source reference: paras. 3.6–3.7

Sharma Enterprises appealed to the Supreme Court.

Source reference: para. 3.8
02

Issues

1. Whether Clause 26 of the Special Conditions of Contract barred the arbitral tribunal from awarding pre-reference and pendente lite interest under Section 31(7)(a) of the 1996 Act

Source reference: para. 6

2. Whether the contractual bar also excluded post-award interest under Section 31(7)(b)

Source reference: para. 17
03

Law Applied

Section 31(7)(a) of the 1996 Act makes an arbitral tribunal’s power to award pre-award interest subject to the parties’ agreement; read with Section 28(3), the tribunal must give effect to the contract.

Source reference: paras. 8–10

A contractual prohibition on interest may exclude pre-award interest where its language does so expressly or by necessary implication.

Source reference: paras. 12–14

The ejusdem generis rule applies only where general words follow specific words forming a distinct genus; disjunctively joined expressions may require independent interpretation.

Source reference: paras. 12–14

The Court relied on Sayeed Ahmed and Company v. State of Uttar Pradesh, Union of India v. Manraj Enterprises, and Union of India v. Larsen & Toubro Limited on contractual restrictions on pre-award interest.

Source reference: paras. 10, 12, 15–16

Section 31(7)(b), by contrast, provides for post-award interest unless the award directs otherwise; the parties cannot contract out of entitlement to that interest.

Source reference: para. 17
04

Reasoning

Clause 26 provided that no claim for interest would be entertained for balances or deposits held up because of a dispute, delays in monthly or final payments, “or otherwise”.

Source reference: para. 7

The Court held that “or otherwise” was a broad residuary expression, not confined by ejusdem generis to delayed contractual payments, and covered other circumstances in which interest might be claimed against NBCC.

Source reference: paras. 12–14

The clause was therefore materially similar to the broad prohibition considered in Sayeed Ahmed and Jaiprakash Associates Limited v. THDC, and barred pre-reference and pendente lite interest.

Source reference: paras. 15–16

That bar did not extend to post-award interest, which is governed by Section 31(7)(b).

Source reference: para. 17
05

Holding

The Supreme Court held that Clause 26 barred pre-reference and pendente lite interest under Section 31(7)(a), but did not disturb the award of post-award interest under Section 31(7)(b).

Finding no error in the High Court’s decision to set aside the award only to the extent of pre-reference and pendente lite interest, the Court dismissed the appeal.

Source reference: paras. 18–19
06

Acts & Sections Cited

5 provisions across 2 statutes referred to in this judgment. Each provision opens on LawLens.

Arbitration and Conciliation Act, 19964

Interest Act, 19781

Supreme Court

Original Court PDF

Ms Sharma EnterprisesvsNational Building Construction Corporation

Supreme Court · October 15, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment