Facts
On 11 January 1991, NBCC subcontracted flooring and cladding work at Vashi Railway Station-cum-Commercial Complex to Sharma Enterprises. Delays in the underlying civil works restricted the appellant’s work, and NBCC terminated the contract on 22 September 1992.
Source reference: paras. 3.1–3.2After protracted proceedings, the arbitrator found the termination wrongful, allowed several monetary claims, and awarded interest at 10% per annum from 22 September 1992, including pre-reference, pendente lite and post-award interest.
Source reference: paras. 3.3–3.4The High Court, acting under Sections 34 and 37 of the Arbitration and Conciliation Act, 1996, set aside the pre-reference and pendente lite interest, but left the substantive claims and post-award interest undisturbed.
Source reference: paras. 3.6–3.7Sharma Enterprises appealed to the Supreme Court.
Source reference: para. 3.8Issues
1. Whether Clause 26 of the Special Conditions of Contract barred the arbitral tribunal from awarding pre-reference and pendente lite interest under Section 31(7)(a) of the 1996 Act
Source reference: para. 62. Whether the contractual bar also excluded post-award interest under Section 31(7)(b)
Source reference: para. 17Law Applied
Section 31(7)(a) of the 1996 Act makes an arbitral tribunal’s power to award pre-award interest subject to the parties’ agreement; read with Section 28(3), the tribunal must give effect to the contract.
Source reference: paras. 8–10A contractual prohibition on interest may exclude pre-award interest where its language does so expressly or by necessary implication.
Source reference: paras. 12–14The ejusdem generis rule applies only where general words follow specific words forming a distinct genus; disjunctively joined expressions may require independent interpretation.
Source reference: paras. 12–14The Court relied on Sayeed Ahmed and Company v. State of Uttar Pradesh, Union of India v. Manraj Enterprises, and Union of India v. Larsen & Toubro Limited on contractual restrictions on pre-award interest.
Source reference: paras. 10, 12, 15–16Section 31(7)(b), by contrast, provides for post-award interest unless the award directs otherwise; the parties cannot contract out of entitlement to that interest.
Source reference: para. 17Reasoning
Clause 26 provided that no claim for interest would be entertained for balances or deposits held up because of a dispute, delays in monthly or final payments, “or otherwise”.
Source reference: para. 7The Court held that “or otherwise” was a broad residuary expression, not confined by ejusdem generis to delayed contractual payments, and covered other circumstances in which interest might be claimed against NBCC.
Source reference: paras. 12–14The clause was therefore materially similar to the broad prohibition considered in Sayeed Ahmed and Jaiprakash Associates Limited v. THDC, and barred pre-reference and pendente lite interest.
Source reference: paras. 15–16That bar did not extend to post-award interest, which is governed by Section 31(7)(b).
Source reference: para. 17Holding
The Supreme Court held that Clause 26 barred pre-reference and pendente lite interest under Section 31(7)(a), but did not disturb the award of post-award interest under Section 31(7)(b).
Finding no error in the High Court’s decision to set aside the award only to the extent of pre-reference and pendente lite interest, the Court dismissed the appeal.
Source reference: paras. 18–19Acts & Sections Cited
5 provisions across 2 statutes referred to in this judgment. Each provision opens on LawLens.
Arbitration and Conciliation Act, 19964
Interest Act, 19781