01Facts
The contractor (Marino Dredgeco) performed dredging of the approach channel and basin for a shore-based pilot station at Sagar Island under a contract with the Port Trust.
The original contract value was Rs. 2,86,56,200, of which Rs. 2,79,32,865 was admittedly paid.
¶ 6 · ¶ 7The Port Trust's letter dated 19.07.2000 entrusted additional work, which the contractor attributed to force majeure weather conditions, 100% siltation, and a mismatch between the soil data supplied by the Port Trust and actual soil conditions, along with the Port Trust's failure to construct protective walls.
¶ 3 · ¶ 6 · ¶ 7The channel was inaugurated on 17.04.2001.
¶ 3 · ¶ 6The Port Trust contends that no completion certificate was issued, that no additional work was entrusted, and that the contract was terminated.
¶ 5The Arbitrator passed an award dated 03.11.2003, which the Single Judge upheld under Section 34.
¶ 6On appeal under Section 37, the Division Bench modified the award by reducing the amount payable to 50% of the sum quantified and reducing interest to 6% on the principal from 08.02.2002. It did so on the ground that the claim for additional work exceeded 70% of the original contract value, which it held shocked the judicial conscience, though it recorded that the award was not perverse, patently illegal, or based on no evidence.
¶ 2 · ¶ 8The Division Bench also found that the completion certificate was not issued by the Port Trust and that the award rested on joint measurements and pre- and post-work levels.
¶ 802Issues
i.1. Whether the Division Bench, exercising jurisdiction under Section 37, was justified in modifying the arbitral award on the sole ground that the additional-work claim exceeded 70% of the original contract value and shocked the judicial conscience.
¶ 2 · ¶ 8 · ¶ 10ii.2. Whether the entire award should be set aside, or alternatively, whether it may be partially set aside, on the ground that it is against public interest.
¶ 4 · ¶ 11 · ¶ 12iii.3. Whether the absence of a completion certificate under the GCC disentitles the contractor to payment for work actually executed and billed.
¶ 5 · ¶ 8iv.4. Whether the awarder's status as a Government entity justifies reducing the quantum of an award that is otherwise valid.
¶ 1303Law Applied
The Court applied Sections 34 and 37 of the Arbitration and Conciliation Act, 1996, which confine courts to the grounds for setting aside awards and bar merits review.
¶ 12Ssangyong Engineering & Construction Co. Ltd. v. NHAI (2019) 15 SCC 131: after the 2015 Amendment, the "most basic notions of morality or justice" ground (shocking the conscience) requires a substantive reason that blatantly and patently conflicts with those notions, and is not satisfied by lip service.
¶ 9Somdatt Builders–NCC–NEC (JV) v. NHAI (2025) 6 SCC 757: the High Court under Section 37 cannot set aside an award by invoking phrases such as "public policy," "patent illegality," or "shocking the conscience" without substantive reasons.
¶ 10Gayatri Balasamy v. M/s ISG Novasoft Technologies Ltd. (2025 INSC 605): partial setting aside is permitted only where the valid and invalid portions are legally and practically severable and not intertwined.
¶ 11Pam Developments Pvt. Ltd. v. State of West Bengal (2019) 8 SCC 112: Government and private parties must be treated equally in arbitral matters.
¶ 13Batliboi Environmental Engineers Ltd. v. HPCL (2024) 2 SCC 375 was held inapplicable because it concerned damages, not invoices for additional work.
¶ 5Provisions in the judgment · 2 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 34Section 37
04Reasoning
The Division Bench's modification rested solely on the ratio of the additional-work claim to the original contract, without examining the nature of the additional work or the measurements and invoices underlying the quantification.
¶ 8 · ¶ 10Because the Division Bench itself found the award based on adequate evidence and not perverse or patently illegal, the shock-the-conscience ground was not substantively established under Ssangyong and Somdatt.
¶ 8 · ¶ 9 · ¶ 10The Port Trust's argument that the claim was against public interest did not satisfy the statutory grounds, and the Court rejected the plea to set aside the award entirely.
¶ 4 · ¶ 12Partial setting aside under Gayatri Balasamy was unavailable because the quantification rested on a single character of re-dredging work and was not divisible into "valid" and "invalid" parts.
¶ 11 · ¶ 12The absence of a completion certificate did not defeat payment, since the Division Bench had found that the contractor's documentary proof of work carried out was valid.
¶ 8The awarder's Government status could not justify reducing the award, as this would breach the equality principle in Pam Developments.
¶ 13The Division Bench had effectively adjudicated the merits by reviewing the quantum, which Sections 34 and 37 do not permit, and the nature of the work (re-dredging to keep the channel operational) was consistent with the original dredging contract.
¶ 12 · ¶ 1405Holding
The Division Bench's modification of the award on the "shock the conscience" ground, based only on the 70% ratio and the awarder's Government status, was outside the jurisdiction conferred by Section 37 and not in consonance with the grounds under the Act.
¶ 8 · ¶ 13 · ¶ 14The impugned judgment of the Division Bench is set aside, the contractor's appeal (C.A. No. 14303 of 2026) is allowed, and the arbitral award dated 03.11.2003 is restored in full.
¶ 15The Port Trust's appeal (C.A. No. 14304 of 2026) is disposed of accordingly, as the impugned order was already set aside.
¶ 16Pending applications, if any, stand disposed of.
¶ 17Original Court PDF
M/S Marino Dredgeco LimitedvsThe Board Of Trustees Of The Port Of Kolkata
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in