Supreme CourtAdministrative and Public LawCommercial and Corporate Law

Power Generator Must Bear Transmission Charges Until Its Dedicated Line Was Built, Supreme Court Holds

Power Grid Corporation Of India Limitedv.Tangedco

Power Generator Must Bear Transmission Charges Until Its Dedicated Line Was Built, Supreme Court Holds. Power Grid Corporation Of India Limited vs Tangedco. Supreme Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether PGCIL is entitled to transmission tariff, including the element of the two LILOs, for the period 04.01.2015/08.01.2015 to 27.10.2016, given that the LILOs formed part of the statutory planning under Section 29(4) of the Electricity Act, 2003 and the BPTA.

The court held

Issue 1 is answered in the affirmative: the LILOs are includable in the transmission tariff as non-PoC from 04.01.2015 until DTL commissioning on 27.10.2016.

It also directed

Issue 2 is answered in the negative, holding that APTEL's interpretation of the COD was erroneous.

Issue 3 is answered in the affirmative: liability for the interim period lies on the generating company for its DTL delay.

The impugned APTEL orders in both appeals are set aside, the CERC order dated 29.07.2016 is restored, the appeals are allowed, and pending applications are disposed of.

01Facts

The appellant, Power Grid Corporation of India Ltd. (PGCIL), is the Central Transmission Utility. It created two Line-In/Line-Out (LILO) connections on the two circuits of the Tuticorin JV–Madurai 400kV D/C (Quad) line at the Tuticorin Pooling Station. The first LILO was commissioned on 04.01.2015 and the second on 08.01.2015.

¶ 1

The generating company, Moxie Power Generation Ltd. (formerly Coastal Energen Pvt. Ltd.), began generation on 23.12.2014 and evacuated power through the Tuticorin JV–Madurai line under STOA/MTOA arrangements.

¶ 7 · ¶ 17

The generating company's Dedicated Transmission Line (DTL) to the Tuticorin Pooling Station was commissioned only on 27.10.2016, and the upstream Tuticorin–Salem line was commissioned on 13.11.2016.

¶ 7

PGCIL claimed transmission charges (non-PoC) of Rs. 15,43,26,909 for the LILOs for the period 04.01.2015 to 27.10.2016.

¶ 14

The CERC, by order dated 29.07.2016, accepted the COD of the LILOs and, by paras 73–77, placed liability for transmission charges on the generating company until its DTL was commissioned.

¶ 41 · ¶ 48

TANGEDCO contended the LILOs were never used, relying on para. 72 of the CERC order.

¶ 1 · ¶ 9

APTEL set aside the CERC order, holding the LILOs were not put to beneficial use and that the COD required review.

¶ 14

On PGCIL's review, APTEL remanded the COD question to the CERC. Both sets of appeals arise from these orders.

¶ 14

02Issues

i.1. Whether PGCIL is entitled to transmission tariff, including the element of the two LILOs, for the period 04.01.2015/08.01.2015 to 27.10.2016, given that the LILOs formed part of the statutory planning under Section 29(4) of the Electricity Act, 2003 and the BPTA.

¶ 20(I)

ii.2. Whether APTEL was right in law in interpreting Regulation 4(3)(ii) of the Tariff Regulations, 2014 by directing the CERC to reconsider the COD of the LILOs already approved by the CERC.

¶ 20(II)

iii.3. Whether the delay in construction of the DTL by the generating company enables liability for transmission charges for the period 04.01.2015/08.01.2015 to 27.10.2016 to be imposed on the generating company.

¶ 20(III)

03Law Applied

Sections 2(16), 2(32), 2(72), 10, 29(4), 61 and 62 of the Electricity Act, 2003, under which a generator must establish DTLs, transmission lines include "other works," and Standing Committee decisions bind the parties.

¶ 22–26

Regulation 3(53) and Regulation 4 of the CERC Tariff Regulations, 2014, under which "Regular Service" means putting a transmission element into use after successful trial operation certified by the RLDC, and Regulation 4(3)(ii) applies where delay in one part of the system prevents regular service of another, with liability falling on the defaulting party.

¶ 38–40

The Bulk Power Transmission Agreement (BPTA) and the Standing Committee minutes, which made the LILOs a permanent part of the transmission plan.

¶ 30–32

PTC India Ltd. v. CERC (2010) 4 SCC 603 and Energy Watchdog v. CERC (2017) 14 SCC 80, which hold that the CERC may impose liability under Section 79(1) in the absence of a regulation, provided it is reasonable and imposed on the defaulting party.

¶ 43–45

PGCIL v. MPPTCL (2025) 8 SCC 705, in which a CTU's COD under Regulation 4(3)(ii) and transmission charges were upheld against a delaying party.

¶ 42

04Reasoning

The Court held that APTEL's "beneficial use" test was misplaced because the Regulations define COD by "Regular Service" and not by commercial viability, and the generation, transmission and consumption were admitted.

¶ 17 · ¶ 40

The LILOs were an intervening, permanent element of the Standing Committee-approved plan, through which power was diverted to the Tuticorin Pooling Station and returned to the Tuticorin JV–Madurai line.

¶ 16 · ¶ 35–37

Since evacuation continued seamlessly from 23.12.2014 and the generating company never objected in the Standing Committee meetings, the delay in the upstream line did not prevent regular service.

¶ 36 · ¶ 46–47

Paragraph 72 of the CERC order recorded TANGEDCO's contention and could not be read in isolation from paras. 73–77, which imposed liability on the generator.

¶ 48

The liability for the period between the LILO COD and DTL commissioning fell on the generator under Regulation 4(3)(ii) because it caused the DTL delay, and the CERC's power under Section 79(1) supported this imposition.

¶ 39 · ¶ 44–45

05Holding

Issue 1 is answered in the affirmative: the LILOs are includable in the transmission tariff as non-PoC from 04.01.2015 until DTL commissioning on 27.10.2016.

¶ 49

Issue 2 is answered in the negative, holding that APTEL's interpretation of the COD was erroneous.

¶ 49

Issue 3 is answered in the affirmative: liability for the interim period lies on the generating company for its DTL delay.

¶ 49

The impugned APTEL orders in both appeals are set aside, the CERC order dated 29.07.2016 is restored, the appeals are allowed, and pending applications are disposed of.

¶ 50–52
Supreme Court

Original Court PDF

Power Grid Corporation Of India LimitedvsTangedco