01Facts
The appellant, Power Grid Corporation of India Ltd. (PGCIL), is the Central Transmission Utility. It created two Line-In/Line-Out (LILO) connections on the two circuits of the Tuticorin JV–Madurai 400kV D/C (Quad) line at the Tuticorin Pooling Station. The first LILO was commissioned on 04.01.2015 and the second on 08.01.2015.
¶ 1The generating company, Moxie Power Generation Ltd. (formerly Coastal Energen Pvt. Ltd.), began generation on 23.12.2014 and evacuated power through the Tuticorin JV–Madurai line under STOA/MTOA arrangements.
¶ 7 · ¶ 17The generating company's Dedicated Transmission Line (DTL) to the Tuticorin Pooling Station was commissioned only on 27.10.2016, and the upstream Tuticorin–Salem line was commissioned on 13.11.2016.
¶ 7PGCIL claimed transmission charges (non-PoC) of Rs. 15,43,26,909 for the LILOs for the period 04.01.2015 to 27.10.2016.
¶ 14The CERC, by order dated 29.07.2016, accepted the COD of the LILOs and, by paras 73–77, placed liability for transmission charges on the generating company until its DTL was commissioned.
¶ 41 · ¶ 48TANGEDCO contended the LILOs were never used, relying on para. 72 of the CERC order.
¶ 1 · ¶ 9APTEL set aside the CERC order, holding the LILOs were not put to beneficial use and that the COD required review.
¶ 14On PGCIL's review, APTEL remanded the COD question to the CERC. Both sets of appeals arise from these orders.
¶ 1402Issues
i.1. Whether PGCIL is entitled to transmission tariff, including the element of the two LILOs, for the period 04.01.2015/08.01.2015 to 27.10.2016, given that the LILOs formed part of the statutory planning under Section 29(4) of the Electricity Act, 2003 and the BPTA.
¶ 20(I)ii.2. Whether APTEL was right in law in interpreting Regulation 4(3)(ii) of the Tariff Regulations, 2014 by directing the CERC to reconsider the COD of the LILOs already approved by the CERC.
¶ 20(II)iii.3. Whether the delay in construction of the DTL by the generating company enables liability for transmission charges for the period 04.01.2015/08.01.2015 to 27.10.2016 to be imposed on the generating company.
¶ 20(III)03Law Applied
Sections 2(16), 2(32), 2(72), 10, 29(4), 61 and 62 of the Electricity Act, 2003, under which a generator must establish DTLs, transmission lines include "other works," and Standing Committee decisions bind the parties.
¶ 22–26Regulation 3(53) and Regulation 4 of the CERC Tariff Regulations, 2014, under which "Regular Service" means putting a transmission element into use after successful trial operation certified by the RLDC, and Regulation 4(3)(ii) applies where delay in one part of the system prevents regular service of another, with liability falling on the defaulting party.
¶ 38–40The Bulk Power Transmission Agreement (BPTA) and the Standing Committee minutes, which made the LILOs a permanent part of the transmission plan.
¶ 30–32PTC India Ltd. v. CERC (2010) 4 SCC 603 and Energy Watchdog v. CERC (2017) 14 SCC 80, which hold that the CERC may impose liability under Section 79(1) in the absence of a regulation, provided it is reasonable and imposed on the defaulting party.
¶ 43–45PGCIL v. MPPTCL (2025) 8 SCC 705, in which a CTU's COD under Regulation 4(3)(ii) and transmission charges were upheld against a delaying party.
¶ 42Provisions in the judgment · 24 · Linked ones open on LawLens
04Reasoning
The Court held that APTEL's "beneficial use" test was misplaced because the Regulations define COD by "Regular Service" and not by commercial viability, and the generation, transmission and consumption were admitted.
¶ 17 · ¶ 40The LILOs were an intervening, permanent element of the Standing Committee-approved plan, through which power was diverted to the Tuticorin Pooling Station and returned to the Tuticorin JV–Madurai line.
¶ 16 · ¶ 35–37Since evacuation continued seamlessly from 23.12.2014 and the generating company never objected in the Standing Committee meetings, the delay in the upstream line did not prevent regular service.
¶ 36 · ¶ 46–47Paragraph 72 of the CERC order recorded TANGEDCO's contention and could not be read in isolation from paras. 73–77, which imposed liability on the generator.
¶ 48The liability for the period between the LILO COD and DTL commissioning fell on the generator under Regulation 4(3)(ii) because it caused the DTL delay, and the CERC's power under Section 79(1) supported this imposition.
¶ 39 · ¶ 44–4505Holding
Issue 1 is answered in the affirmative: the LILOs are includable in the transmission tariff as non-PoC from 04.01.2015 until DTL commissioning on 27.10.2016.
¶ 49Issue 2 is answered in the negative, holding that APTEL's interpretation of the COD was erroneous.
¶ 49Issue 3 is answered in the affirmative: liability for the interim period lies on the generating company for its DTL delay.
¶ 49The impugned APTEL orders in both appeals are set aside, the CERC order dated 29.07.2016 is restored, the appeals are allowed, and pending applications are disposed of.
¶ 50–52Original Court PDF
Power Grid Corporation Of India LimitedvsTangedco
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
