01Facts
The appellant entered into a Bulk Power Transmission Agreement (BPTA) with the transmission utility for long-term access (LTA) to evacuate power from its generating station.
pp. 5–7Under Clause 6.0 of the BPTA, it furnished construction bank guarantees (BGs) securing completion of the generating station and dedicated transmission system; Clause 2.0 separately required an LC/BG to secure payment of transmission charges.
pp. 5–7, 13–19After the generating units and dedicated transmission line were commissioned, the appellant sought return of the construction BGs.
pp. 3–4, 8The Central Electricity Regulatory Commission (CERC) held that the BGs could not be withheld for failure to open an LC, but made their return subject to PGCIL’s satisfaction with the LC.
pp. 3–4, 8The appellant appealed that condition and also sought reimbursement of costs incurred in extending the BGs.
pp. 7–8, 23–2402Issues
i.1. Whether return of the Clause 6.0 construction BGs could be made conditional on the appellant opening an LC/BG under Clause 2.0 of the BPTA.
pp. 11, 20–22ii.2. Whether the appellant was entitled to reimbursement of the costs incurred in extending the construction BGs.
pp. 23–2403Law Applied
Clauses 2.0 and 6.0 of the BPTA provide distinct security mechanisms for different purposes: Clause 6.0 secures construction-related obligations and permits encashment in specified circumstances involving failure to construct, exit or abandonment, while Clause 2.0 secures payment of transmission charges.
pp. 13–19The BG must be applied in accordance with the terms and purpose for which it was furnished; it cannot be used for an unrelated obligation.
pp. 19–22The Tribunal also referred to Section 126 of the Indian Contract Act, 1872, describing a contract of guarantee as an undertaking to discharge a third party’s liability in the event of default.
p. 22Provisions in the judgment · 1 · Linked ones open on LawLens
Indian Contract Act, 1872 Section 126
04Reasoning
The Tribunal found that the generating station and dedicated transmission system had been commissioned, fulfilling the obligations secured by the Clause 6.0 BGs.
pp. 19–22The BPTA did not make those BGs interchangeable with, or conditional upon, the LC/BG required under Clause 2.0; nor did relinquishment of part of the LTA amount to abandonment of the project within Clause 6.0.
pp. 19–22Accordingly, the Commission’s condition linking release of the construction BGs to satisfaction regarding the LC was inconsistent with the BPTA.
pp. 19–22However, the appellant had continued extending the BGs without seeking interim relief until 2025, so the Tribunal considered reimbursement of the extension costs unjustified.
pp. 23–2405Holding
The appeal was partly allowed.
pp. 22–24The direction making return of the Clause 6.0 construction BGs conditional on PGCIL’s satisfaction regarding the Clause 2.0 LC/BG was set aside.
pp. 22–24CTUIL was directed to return the construction BGs forthwith and no later than two weeks from the judgment.
pp. 22–24The claim for reimbursement of ₹5,74,25,547.50 in BG-extension costs was rejected.
pp. 22–24Original Court PDF
GMR Kamalanga Energy Limited VSRSUS Central Electricity Regulatory Commission & Ors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in