01Facts
Jayamal Energy LLP entered into a PPA with BESCOM on 2 July 2015 for a 2 MW solar project.
pp. 2–3The PPA was approved by KERC on 25 August 2015.
pp. 2–3The project was commissioned on 31 August 2017, after BESCOM had granted extensions of time, ultimately up to 1 October 2017.
pp. 2–3, 18–19KERC rejected the developer’s petition seeking approval of the extension and the PPA tariff of ₹8.40/kWh; it instead applied the tariff of ₹4.36/kWh and held the developer liable for damages under the PPA.
pp. 3–6The developer appealed.
pp. 3–602Issues
i.1. Whether the PPA’s effective date—and therefore the project’s Scheduled Commercial Operation Date (SCOD)—was the date of execution or the date KERC approved the PPA.
pp. 6–8, 17ii.2. Whether the extensions granted by BESCOM could be upheld beyond the period permitted by the PPA, and whether the developer could claim force majeure relief without giving the required notice.
pp. 18–25, 30–31iii.3. Whether the developer was entitled to the PPA tariff of ₹8.40/kWh or the tariff applicable on the project’s actual commissioning date, having regard to when its capital cost crystallised.
pp. 25–3003Law Applied
Under Section 86(1)(b) of the Electricity Act, 2003, a distribution licensee’s power procurement and the price payable under a PPA are subject to regulatory oversight and approval.
The Tribunal relied on Tata Power Company Ltd. v. Reliance Energy Ltd., (2009) 16 SCC 659, and its decisions in Rithwik Energy Generation Pvt. Ltd. v. Karnataka Power Transmission Corp. Ltd., 2011 ELR (APTEL) 1651, and Eswari Green Energy LLP v. KERC, Appeal No. 180 of 2018 and batch, for the principle that a PPA requiring regulatory approval becomes operative upon approval.
Under PPA Articles 2.5.1–2.5.4, extensions are limited to the specified periods; Article 5.1 provides for the lower applicable tariff where commissioning is delayed beyond the permissible extension and the tariff has varied.
Article 8.3(b)(i) requires written notice of a force majeure event as soon as practicable.
The Tribunal applied Chamundeshwari Electricity Supply Co. Ltd. v. Saisudhir Energy (Chitradurga) Pvt. Ltd., Civil Appeal No. 6888 of 2018 (25 August 2025), for the rule that such notice is a condition precedent to invoking force majeure.
It also applied Smt. Sharada Doddi v. Gulbarga Electricity Supply Co. Ltd., Appeal No. 418 of 2023 (4 December 2025), under which the PPA tariff may be protected if the project’s capital cost crystallised before the SCOD.
Provisions in the judgment · 4 · Linked ones open on LawLens
Electricity Act, 2003 Section 86Section 185
KARNATAKA ELECTRICITY REFORM ACT, 1999 Section 25Section 17
04Reasoning
The Tribunal held that the PPA became effective when KERC approved it on 25 August 2015, making 25 February 2017 the SCOD.
pp. 17–18Although BESCOM had extended the commissioning date, the Tribunal found that, because the claimed delay related to force majeure events affecting the developer, Article 2.5.4 allowed an extension of no more than three months.
pp. 23–25The SCOD therefore extended only to 25 May 2017; the project’s commissioning on 31 August 2017 was beyond that period.
pp. 23–25The developer could not obtain force majeure relief because it had not provided the notice required by Article 8.3(b)(i), and the Tribunal therefore upheld the damages liability.
pp. 30–31On tariff, the Tribunal found the record insufficient to determine whether the project’s capital cost had crystallised before the SCOD.
pp. 28–30Following Sharada Doddi, it remitted that question to KERC: if the capital cost had crystallised before 25 February 2017, the PPA tariff would apply; otherwise, the tariff applicable on the actual commissioning date would apply.
pp. 28–3005Holding
The appeal was partly allowed.
pp. 31–32The Tribunal held that the effective date was 25 August 2015 and that the permissible extension ended on 25 May 2017; it affirmed the developer’s liability for damages under PPA Articles 2.2 and 2.5.7.
pp. 31–32It remitted the tariff issue to KERC to determine whether the capital cost had crystallised before the SCOD, directing KERC to complete the inquiry within one month.
pp. 31–32If so, the tariff would be ₹8.40/kWh from the actual commissioning date, with applicable carrying cost; otherwise, the tariff applicable on the actual commissioning date would govern.
pp. 31–32Original Court PDF
Jayamal Energy LLPvsBangalore Electricity Supply Company Limited & Anr
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
