After Two Acquisition Rounds Lapsed, J&K HC Orders Fresh Compensation Award for Road Land, Pegging Valuation to 2021

UT OF J AND K TH COMMISSIONER CUM SECRETARY REVENUE DEPARTMENTv.ABDUL GANI AND OTHERS

After Two Acquisition Rounds Lapsed, J&K HC Orders Fresh Compensation Award for Road Land, Pegging Valuation to 2021. UT OF J AND K TH COMMISSIONER CUM SECRETARY REVENUE DEPARTMENT vs ABDUL GANI AND OTHERS. Jammu and Kashmir High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the acquisition proceedings lapsed under Section 11-B despite the invocation of urgency powers under Section 17, where the requirement to tender or pay 80% of estimated compensation under Section 17-A was not met.

The court held

The Court affirmed that the 2017 acquisition proceedings had lapsed but modified the remedy.

It also directed

It set aside the 10 December 2021 award insofar as it concerned the respondents and directed the Collector to make a fresh award for them alone, using 10 December 2021 as the date for determining market value and applying the compensation yardsticks under the 1990 Act.

Statutory benefits, including interest, are to be calculated by reference to 9 January 2014; any compensation already received must be deducted.

The respondents may seek enhancement from the date the fresh award is made and communicated.

The Court awarded them Rs. 3 lakh in costs, shared equally, and disposed of the appeal.

01Facts

The respondents’ land at Tetharka was acquired for a road.

¶ 1–5

After an earlier acquisition initiated in 2014 was quashed for lapse under Section 11-B of the J&K Land Acquisition Act, 1990, the authorities commenced fresh proceedings by notification dated 2 November 2017.

¶ 1–5

A declaration under Sections 6 and 7 followed on 22 February 2018, but the final award was not passed until 10 December 2021—more than two years later.

¶ 1–5

The respondents challenged the proceedings, and the Writ Court held that they had lapsed, directed fresh acquisition under the 2013 Act, and awarded Rs. 6 lakh in costs.

¶ 1–5

The UT appealed.

¶ 1–5

The authorities argued that Section 17 urgency powers applied; the respondents contended that Section 11-B still applied because 80% of the estimated compensation had not been tendered or paid under Section 17-A.

¶ 6–7

02Issues

i.1. Whether the acquisition proceedings lapsed under Section 11-B despite the invocation of urgency powers under Section 17, where the requirement to tender or pay 80% of estimated compensation under Section 17-A was not met.

¶ 8–10

ii.2. Whether, given the land’s public use and the history of the proceedings, the relief should be modified rather than requiring a third acquisition process, and how compensation should be assessed.

¶ 11–16

03Law Applied

Section 11-B of the J&K Land Acquisition Act, 1990 requires an award to be made within two years from the relevant declaration; otherwise, the acquisition proceedings lapse.

¶ 9–10

Sections 17 and 17-A permit possession to be taken urgently before a final award, but Section 17-A requires the Collector to tender and pay 80% of the estimated compensation before taking possession; invocation of Section 17 alone does not displace Section 11-B where that requirement is unmet.

¶ 9–10

The Court also relied on M/s Delhi Airtech Services Pvt. Ltd. v. State of U.P., 2022 INSC 1086, and the decisions in Gulzar Ahmad Akhoon v. UT of J&K and UT of J&K v. Piaray Lal Tickoo in shaping the remedy where land was already in public use.

¶ 11, 15

Provisions in the judgment · 9

Jammu and Kashmir Land Acquisition Act, 1990 (Svt.) 9 provisionsSection 4Section 6Section 7Section 9Section 9ASection 11Section 11BSection 17Section 17A

04Reasoning

The declaration was issued on 22 February 2018 and the final award on 10 December 2021, beyond Section 11-B’s two-year period.

¶ 8–10

Although the authorities had invoked Section 17, they had not tendered or paid 80% of the estimated compensation as required by Section 17-A; the urgency provision therefore did not prevent the proceedings from lapsing.

¶ 8–10

However, because the land was already in public use and two rounds of acquisition had failed, the Court considered a third round contrary to the public interest and likely to delay compensation.

¶ 11–15

It found no documentary evidence that possession had been taken in 2002 or 2003 and treated 9 January 2014—the date of the first Section 4 notification—as the relevant date for calculating statutory benefits, including interest.

¶ 11–15

05Holding

The Court affirmed that the 2017 acquisition proceedings had lapsed but modified the remedy.

¶ 16–17

It set aside the 10 December 2021 award insofar as it concerned the respondents and directed the Collector to make a fresh award for them alone, using 10 December 2021 as the date for determining market value and applying the compensation yardsticks under the 1990 Act.

¶ 16–17

Statutory benefits, including interest, are to be calculated by reference to 9 January 2014; any compensation already received must be deducted.

¶ 16–17

The respondents may seek enhancement from the date the fresh award is made and communicated.

¶ 16–17

The Court awarded them Rs. 3 lakh in costs, shared equally, and disposed of the appeal.

¶ 16–17
Jammu and Kashmir High Court

Original Court PDF

UT OF J AND K TH COMMISSIONER CUM SECRETARY REVENUE DEPARTMENTvsABDUL GANI AND OTHERS

Jammu and Kashmir High Court · October 29, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment