Madras High CourtAdministrative and Public LawProperty and Real Estate Law

Allottee cannot be penalised for non-construction during the period of delayed possession and pending litigation.

State Industries Promotion Corporation of Tamil Nav.HMTD Engineering Private Ltd

Allottee cannot be penalised for non-construction during the period of delayed possession and pending litigation.. State Industries Promotion Corporation of Tamil Na vs HMTD Engineering Private Ltd. Madras High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the cancellation of the allotment dated 11.03.2021 for non-compliance with construction and commercial-production timelines was sustainable, given that the respondent's possession was delivered on 18.05.2006 and the matter remained pending before the authority from 05.07.2019 to 11.03.2021.

The court held

The Single Judge committed no error warranting interference, and the cancellation dated 11.03.2021 could not be sustained because the allottee's inability to construct during the pending proceedings was not a default under the allotment order or lease deed.

It also directed

The writ appeal was dismissed with no order as to costs, and CMP Nos. 11155 of 2025 and 30204 of 2026 were closed.

The respondent may proceed with construction and commercial use in accordance with the allotment terms, and the conditions will operate prospectively from the date of judgment, with SIPCOT free to act on any fresh violations calculated from that date.

01Facts

SIPCOT allotted Plot No. 4/D4 (2 acres) in its IT Park, Siruseri, to the respondent by proceedings dated 10.01.2002.

¶ 5

A lease deed was executed on 11.01.2002 and registered at Thiruporur.

¶ 5

Possession was handed over only on 18.05.2006.

¶ 5

On 18.07.2006, within two months of possession, SIPCOT cancelled the allotment for alleged violation of clauses 3(vii) and 3(viii) of the allotment order and clause 18 of the lease deed (non-construction and non-use).

¶ 6

In W.P. No. 33785 of 2007, the learned Single Judge set aside that cancellation on 05.07.2019 and remitted the matter for fresh consideration.

¶ 7–8

The quoted operative paragraphs refer to the cancellation as dated 20.07.2007, although the impugned order is elsewhere dated 18.07.2006.

¶ 7

SIPCOT then passed a second cancellation order dated 07.03.2021, communicated/dated 11.03.2021, again citing clauses 3(vii)–(ix) of the allotment order and clauses 18–19 of the lease deed (construction to commence within six months, complete within 24 months, and commercial production within 30 months).

¶ 8

In W.P. No. 10921 of 2021, the learned Single Judge set aside the second cancellation on 30.10.2023, holding that the delay from 05.07.2019 to 11.03.2021 could not be attributed to the respondent and leaving SIPCOT free to fix fresh timelines.

¶ 9

SIPCOT appealed.

¶ 9

02Issues

i.1. Whether the cancellation of the allotment dated 11.03.2021 for non-compliance with construction and commercial-production timelines was sustainable, given that the respondent's possession was delivered on 18.05.2006 and the matter remained pending before the authority from 05.07.2019 to 11.03.2021.

¶ 2, 8, 9

ii.2. Whether the period during which the allottee was prevented from constructing by the pending cancellation proceedings and interim orders could be counted as the allottee's default under the allotment order and lease deed.

¶ 8, 9, 10

03Law Applied

The terms of the allotment order dated 10.01.2002 (clauses 3(vii)–(ix)) and the lease deed dated 11.01.2002 (clauses 18–19), which require commencement of construction within six months, completion within 24 months, and commercial production within 30 months, and which the appellant invoked as a power of cancellation and resumption.

¶ 2, 8

The directions of the Single Judge in W.P. No. 33785 of 2007 (order dated 05.07.2019), which set aside the first cancellation and remitted the matter for fresh consideration, thereby making the authority's pending decision the operative constraint on construction.

¶ 7–8

The principle that an allottee cannot be held in default for a period in which the allotting authority's own pending proceedings and interim orders restrained construction.

¶ 8–10

Provisions in the judgment · 3

allotment order (alias, unresolved) Section 3

lease deed (alias, unresolved) Section 18Section 19

04Reasoning

The Court found that possession was handed over only on 18.05.2006, and the first cancellation followed within two months, which the Court regarded as untenable because the allottee could not realistically build an industrial unit in that period.

¶ 6, 7

After the 2019 remand, the authority took nearly two years (05.07.2019 to 11.03.2021) to pass a fresh order, and the Court held that this delay could not be attributed to the respondent, since the remand required the authority to decide the issues afresh.

¶ 9

The Court further reasoned that interim stays in the writ proceedings, combined with the pendency of the cancellation, meant the respondent could not be expected to commit investment that might be lost if the writ failed.

¶ 10

On that basis, the Court held that the second cancellation was not founded on any default attributable to the allottee and that the Single Judge's interference was justified.

¶ 9–11

The Court declined to accept SIPCOT's contention that the period from 05.07.2019 to 11.03.2021 by itself established non-compliance.

¶ 2, 9

05Holding

The Single Judge committed no error warranting interference, and the cancellation dated 11.03.2021 could not be sustained because the allottee's inability to construct during the pending proceedings was not a default under the allotment order or lease deed.

¶ 9–11

The writ appeal was dismissed with no order as to costs, and CMP Nos. 11155 of 2025 and 30204 of 2026 were closed.

¶ 13

The respondent may proceed with construction and commercial use in accordance with the allotment terms, and the conditions will operate prospectively from the date of judgment, with SIPCOT free to act on any fresh violations calculated from that date.

¶ 11–12
Madras High Court

Original Court PDF

State Industries Promotion Corporation of Tamil NavsHMTD Engineering Private Ltd

Madras High Court · November 17, 2026