Madras High CourtAdministrative and Public LawProperty and Real Estate Law

Authorities must remove encroachments from government poromboke land through statutory procedure within twelve weeks.

Kamal Mills Residents Welfare Association Peelamedv.The District collector

Authorities must remove encroachments from government poromboke land through statutory procedure within twelve weeks.. Kamal Mills Residents Welfare Association Peelamed vs The District collector. Madras High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the court should direct removal of the alleged encroachment and restoration of the public wall on the disputed land, given the authorities' stated identification of the land as Government poromboke.

The court held

The court did not answer the framed questions on the merits. It held that, in view of the Corporation's submission regarding identified encroachments on Government poromboke, the official respondents must continue enforcement and remove encroachments from that land by following the procedure under the relevant statutes and rules.

It also directed

The entire exercise is to be completed within twelve weeks from receipt of a copy of the order. The writ petition is disposed of with no costs, and connected miscellaneous petitions, if any, are closed. The prayers for restoration of the wall and for penal and recovery proceedings against Respondent 8 were not expressly granted.

01Facts

The petitioner, the Secretary of a residents' welfare association in Kamala Colony, Peelamedu, Coimbatore, sought a writ of mandamus under Article 226 directing Respondents 1 to 7 to remove an alleged encroachment by Respondent 8 over a corporation road in S.F. No. 53, Block No. 17, Ward AF(32), to restore a public wall originally erected when the layout was formed, and to replace old fencing unlawfully demolished.

p. 2 · p. 3

The petitioner also sought a direction to the 2nd Respondent (Corporation Commissioner) to initiate penal and recovery proceedings against Respondent 8, relying on the 4th Respondent's proceedings dated 31.03.2022 and an RTI reply dated 06.04.2022.

p. 2 · p. 3

The Standing Counsel for the Corporation submitted that authorities had conducted a survey, identified encroachments, and classified the subject property as Government poromboke, and that enforcement action would be initiated.

p. 3 · ¶ 2

02Issues

i.1. Whether the court should direct removal of the alleged encroachment and restoration of the public wall on the disputed land, given the authorities' stated identification of the land as Government poromboke.

p. 3 · ¶ 2

ii.2. Whether the court should direct the Corporation to initiate penal and recovery proceedings against Respondent 8 based on the 4th Respondent's proceedings and RTI material.

p. 3 · ¶ 1

03Law Applied

The court's order rests principally on the Corporation's undertaking that encroachments on Government poromboke land would be removed through enforcement action.

p. 3 · ¶ 2

The court directs that removal be carried out "by following the procedure as contemplated under the relevant statutes and rules in force."

p. 4 · ¶ 3

The petition invokes Article 226 of the Constitution of India as the basis for mandamus.

p. 2

The court does not identify any specific statutory provision, rule, or precedent, does not discuss the legal content of "poromboke" land, the scope of municipal powers over encroachments, or the availability of penal or recovery action under any statute.

04Reasoning

The court did not adjudicate the merits of the petitioner's claim that Respondent 8 encroached on the road, that the wall was unlawfully demolished, or that the 4th Respondent's 2022 proceedings established liability.

Instead, the court accepted the Corporation's statement that a survey had identified encroachments on Government poromboke land and that enforcement would follow, and on that basis directed the official respondents to continue enforcement and remove encroachments from the poromboke land under the applicable statutory procedure.

p. 3 · ¶ 2 · pp. 3–4 · ¶ 3

The direction is limited to removal of encroachments from poromboke land. It does not expressly order restoration of the demolished wall or fencing, nor does it direct penal or recovery proceedings against Respondent 8, which were the petitioner's specific prayers.

pp. 2–3

The court thus resolved the writ by way of a time-bound supervisory direction, not a determination of the disputed reliefs.

05Holding

The court did not answer the framed questions on the merits. It held that, in view of the Corporation's submission regarding identified encroachments on Government poromboke, the official respondents must continue enforcement and remove encroachments from that land by following the procedure under the relevant statutes and rules.

pp. 3–4 · ¶ 3

The entire exercise is to be completed within twelve weeks from receipt of a copy of the order. The writ petition is disposed of with no costs, and connected miscellaneous petitions, if any, are closed. The prayers for restoration of the wall and for penal and recovery proceedings against Respondent 8 were not expressly granted.

p. 4 · ¶ 3 · p. 4 · ¶ 4 · pp. 2–4
Madras High Court

Original Court PDF

Kamal Mills Residents Welfare Association PeelamedvsThe District collector

Madras High Court · November 19, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment