In brief

The question

1. Whether, in the face of conflicting reports and counter affidavits denying encroachment, the petitioner is entitled to a mandamus directing removal of the alleged encroachment on the Panchayat Road.

The court held

The Court did not grant the mandamus sought at this stage. It held that a survey conducted without notice to the petitioner and without his presence cannot be accepted as conclusive on encroachment.

It also directed

The Court directed respondents 4 to 6 to conduct a fresh survey of the road with a qualified surveyor, after notice to all concerned parties, in their presence, with full videography, and to file a detailed report with the video record. The writ petition was disposed of on these terms with no order as to costs. The matter is listed on 02.12.2026 for reporting compliance.

The Court did not separately address the petitioner's prayer for action against respondents 2 and 5 against the seventh respondent, which is effectively left to await the survey outcome.

01Facts

The petitioner sought a writ of mandamus under Article 226 directing respondents 1, 3, 4 and 6 to remove alleged encroachments on a 12-feet East-West Panchayat Road south of the seventh respondent's (A. Subramaniyan's) house at Sembiyan Mahadevipattinam Village, Peravurani Taluk, and to restore the road.

p. 2

The petitioner also sought action against respondents 2 and 5 for the alleged demolition of the road.

p. 2

Both the seventh respondent and the fourth respondent (BDO) filed counter affidavits denying any encroachment.

The Tahsildar had written to the BDO stating there was no encroachment.

p. 3 · ¶ 2

The petitioner contended that the seventh respondent had encroached and that the fourth respondent was colluding with him and merely echoing his stand.

p. 3 · ¶ 3

The Court noted that the sixth respondent (Tahsildar) had reported no encroachment, but no records showed that notice of the survey was given to the petitioner or that the survey was conducted in his presence.

p. 4 · ¶ 5

02Issues

i.1. Whether, in the face of conflicting reports and counter affidavits denying encroachment, the petitioner is entitled to a mandamus directing removal of the alleged encroachment on the Panchayat Road.

p. 3 · ¶ 2–3 · p. 4 · ¶ 5

ii.2. Whether a survey relied upon to reject the encroachment complaint is legally sustainable where no notice was given to the petitioner and he was not present during the survey.

p. 4 · ¶ 5

iii.3. What directions are appropriate to determine the factual question of encroachment fairly, given the alleged collusion between the BDO and the seventh respondent.

p. 3 · ¶ 3 · p. 4 · ¶ 5–6

03Law Applied

The writ jurisdiction invoked is Article 226 of the Constitution, which forms the basis of the prayer.

p. 2

A person whose rights are affected by a factual determination, here a survey of the disputed road, must receive notice and an opportunity to be present, and the determination must be transparent.

p. 4 · ¶ 5

The Court may direct a fresh, supervised factual inquiry by a qualified surveyor, with videographic recording and a reporting obligation, where the existing material is insufficient to resolve the dispute.

p. 4 · ¶ 6 · p. 5

04Reasoning

The Court did not decide whether encroachment existed. It found that the Tahsildar's report, which was the principal basis for rejecting the complaint, could not be relied upon in its current form because the record disclosed no notice to the petitioner and no presence of the petitioner during the survey.

p. 4 · ¶ 5

Given the conflicting stands of the petitioner and the BDO/seventh respondent, and the petitioner's allegation of collusion, the Court held that the factual dispute could not be resolved on affidavits alone. It ordered a fresh survey that cured the procedural defect, requiring notice to the petitioner, the seventh respondent and other claimants, prior intimation of date and time, conduct in the presence of the parties, and videography of the entire proceedings. These safeguards addressed both the procedural irregularity and the collusion concern without the Court making findings on the merits.

p. 4 · ¶ 5–6 · p. 5

05Holding

The Court did not grant the mandamus sought at this stage. It held that a survey conducted without notice to the petitioner and without his presence cannot be accepted as conclusive on encroachment.

p. 4 · ¶ 5

The Court directed respondents 4 to 6 to conduct a fresh survey of the road with a qualified surveyor, after notice to all concerned parties, in their presence, with full videography, and to file a detailed report with the video record. The writ petition was disposed of on these terms with no order as to costs. The matter is listed on 02.12.2026 for reporting compliance.

p. 4 · ¶ 6 · p. 5 · ¶ 6, 7, 9

The Court did not separately address the petitioner's prayer for action against respondents 2 and 5 against the seventh respondent, which is effectively left to await the survey outcome.

Madras High Court

Original Court PDF

Kumaravel. GvsThe District Collector/Chairperson

Madras High Court · November 17, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment