Madras High CourtArbitration and MediationContract Law

Section 37 appellate court cannot reappraise arbitral findings absent perversity or Section 34 grounds

NADIPPISAI PULAVAR K.P.RAMASAMYv.THIRUMAGAL ENTERPRISE LIMITED

Section 37 appellate court cannot reappraise arbitral findings absent perversity or Section 34 grounds. NADIPPISAI PULAVAR K.P.RAMASAMY vs THIRUMAGAL ENTERPRISE LIMITED. Madras High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the appellant has made out any ground under s.34 of the Arbitration and Conciliation Act, 1996 warranting interference with the arbitral award and the Single Judge's order.

The court held

No ground under s.34 warranting interference was made out, the s.37 court cannot re-appreciate evidence or interfere with concurrent findings absent perversity, and the Arbitrator's findings must stand.

It also directed

The appeal is dismissed with no order as to costs, and the connected C.M.P. No. 8181 of 2021 is closed. The arbitral award allowing the claim (Rs. 2,61,09,476.81 with interest) and the Single Judge's dismissal of the s.34 petition are thereby upheld.

01Facts

The respondent (claimant) was the successful tenderer for supply of machinery and commissioning for expanding the appellant sugar mill's capacity.

The parties agreed that the "Supply and Commissioning" contract and the erection contract were separate, with separate rates for erection.

p. 2

The Letter of Intent (LoI) price was Rs. 2,119.69 lakhs against a tender price of Rs. 1,745 lakhs; the difference was attributed to an additional 3HW Turbo Set order and excise duty.

p. 2

The base date for escalation on MS, SS and brass items was 10.05.1991, and commissioning was due within 18 months of the agreement.

pp. 2–3

The claimant sought Rs. 6,09,47,540.64, with interest at 22% p.a., alleging non-settlement despite supply and erection.

p. 3

The sole Arbitrator allowed Rs. 2,61,09,476.81 with 12% interest on Rs. 84,84,271.60 from the date of award, rejected Rs. 70 lakhs, held that Ex.C5 was a supply and commissioning (not turnkey) agreement superseding the LoI, allowed the counter-claim only to Rs. 52,667, and imposed costs of Rs. 35,60,345 on the respondent.

pp. 3–4

The learned Single Judge dismissed the s.34 petition, holding that no ground was made out and relying on Fiza Developers.

p. 4

The appellant, in s.37 appeal, contended that a claim of Rs. 3,22,890 was neither within the original contract nor in the s.21 notice, rendering the award unsustainable.

p. 5

02Issues

i.1. Whether the appellant has made out any ground under s.34 of the Arbitration and Conciliation Act, 1996 warranting interference with the arbitral award and the Single Judge's order.

p. 5 / p.6

ii.2. Whether the award of Rs. 3,22,890, allegedly outside the contract and the s.21 notice, renders the award unsustainable.

p. 5

03Law Applied

Section 37 of the Arbitration and Conciliation Act, 1996, under which appellate review is confined to the s.34 grounds and cannot travel beyond them.

pp. 5–6

Sepco Electric Power Construction Corp. v. GMR Kamalanga Energy Ltd., which holds that s.37 courts do not independently evaluate the merits and should exercise caution in disturbing concurrent findings.

pp. 5–7

Konkan Railway Corp. v. Chenab Bridge Project Undertaking, holding that s.34 interference is limited to perversity or manifest arbitrariness, and that a Division Bench cannot reinterpret contractual terms under s.37.

pp. 5–6

C&C Constructions Ltd. v. Ircon International Ltd., (2025) 4 SCC 234, which restates Larsen Air Conditioning and Associate Builders on patent illegality and the deference owed to a reasonable construction of the contract.

pp. 7–8

Fiza Developers & Inter-Trade Pvt. Ltd. v. AMCI (India) Pvt. Ltd., (2009) 17 SCC 796, for the principle that a s.34 court is not an appellate forum.

p. 4

Provisions in the judgment · 3 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 37Section 34Section 21

04Reasoning

The Court first noted that the appellant's challenge was directed at factual findings of the Arbitrator.

p. 4

The Court held that the appellant could not point to any perversity in the findings and that the Arbitrator had considered the factual matrix and documents in full.

¶ 10 (p.7)

Applying the Sepco and Konkan Railway principles, the Court declined to re-appreciate evidence or reinterpret the contract, since the Arbitrator's view was a plausible, reasoned one.

p. 8

On the Rs. 3,22,890 contention, the judgment records the submission but does not separately analyse whether the amount fell outside the contract or the s.21 notice. The point is effectively subsumed in the general finding that no perversity or s.34 ground was established.

p. 5 · p. 7

The Court's reasoning rests on the absence of perversity and the bar on re-appreciation, not on a specific finding on that claim.

p. 7

05Holding

No ground under s.34 warranting interference was made out, the s.37 court cannot re-appreciate evidence or interfere with concurrent findings absent perversity, and the Arbitrator's findings must stand.

p. 8

The appeal is dismissed with no order as to costs, and the connected C.M.P. No. 8181 of 2021 is closed. The arbitral award allowing the claim (Rs. 2,61,09,476.81 with interest) and the Single Judge's dismissal of the s.34 petition are thereby upheld.

p. 9
Madras High Court

Original Court PDF

NADIPPISAI PULAVAR K.P.RAMASAMYvsTHIRUMAGAL ENTERPRISE LIMITED

Madras High Court · November 16, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment