Punjab and Haryana High CourtProperty and Real Estate LawConsumer Protection

Allottee cannot be penalised with non-construction charges where the authority failed to deliver possession of the plot.

Greater Mohali Area Development Authority (Gmada),v.The National Consumer Disputes Redressal Commission,

Allottee cannot be penalised with non-construction charges where the authority failed to deliver possession of the plot.. Greater Mohali Area Development Authority (Gmada), vs The National Consumer Disputes Redressal Commission,. Punjab and Haryana High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether GMADA can levy non-construction charges on an allottee for failing to raise construction within the stipulated period when GMADA itself failed to deliver physical possession of the plot within that period.

The court held

The obligation to construct is dependent on delivery of possession, and a deemed possession clause cannot be invoked where the authority did not in fact make a demarcated plot available.

It also directed

The non-construction demand of Rs. 4,16,726 raised before possession on 02.04.2013 was unjustified.

The writ petition is dismissed. The directions of the District Forum, as upheld by the State and National Commissions, remain operative and enforceable according to their terms.

Pending applications, if any, stand disposed of.

The judgment does not specify the individual directions in the decision itself.

01Facts

Respondent No. 2, Harwinder Kaur Gill, applied for a 400 sq. yd. freehold plot and was successful in the draw of lots held on 30.03.2001. The tentative price was Rs. 15,00,000, and she paid the 15% deposit on 24.05.2001.

¶ 2

Fresh allotment proceedings were held on 16.05.2008, and Plot No. 1086 (Corner), Sector 77, Mohali, was allotted by letter dated 25.09.2008.

¶ 3

The tentative price was revised to Rs. 18,45,937 on 02.02.2009 due to an additional area.

¶ 3

Clause 11 required the allottee to take possession within 60 days, and GMADA relied on this as a deemed possession clause.

¶ 4

The land in Sectors 76 to 80 was subject to litigation and a stay order of this Court, and development work was incomplete. GMADA's own reports referred to feasibility, sewerage, drainage and the stay order.

¶ 7

Respondent No. 2 sought physical possession by letter dated 17.02.2009.

¶ 6

There is no record of any communication fixing a date for possession.

¶ 6, 18

GMADA demanded and received Rs. 2,67,775 on 30.04.2012 with no non-construction charges shown.

¶ 8

Subsequent demands for non-construction charges were raised on 21.09.2012, 06.11.2012 and 14.03.2013 (Rs. 4,16,726). The allottee's representation of 20.11.2012 was not accepted, and the No Dues Certificate was refused.

¶ 9

Physical possession was delivered only on 02.04.2013, more than four years after the request.

¶ 10–11, 15

The District Consumer Disputes Redressal Forum, Mohali, allowed the complaint on 01.08.2014. The State Commission dismissed GMADA's appeal on 22.09.2016, and the National Commission dismissed its revision on 26.03.2024.

¶ 1

GMADA then filed this writ petition under Article 226.

¶ 1

02Issues

i.1. Whether GMADA can levy non-construction charges on an allottee for failing to raise construction within the stipulated period when GMADA itself failed to deliver physical possession of the plot within that period.

¶ 14

ii.2. Whether the deemed possession clause in the allotment letter (Clause 11, 60 days) can be invoked to treat possession as having been delivered, so as to fix the allottee with default.

¶ 4–5, 18

03Law Applied

The Court relied on Clause 11 (possession within 60 days) and Clause 13 (construction within three years) of the allotment letter.

¶ 4, 12, 15

A deemed possession clause cannot be read in isolation. It presupposes that the authority can deliver an identifiable, demarcated and legally available plot, and it cannot be used to create a fiction contrary to the actual state of affairs, particularly where litigation prevented delivery.

¶ 5

The obligation to raise construction cannot be considered independently of delivery of possession. An allottee is responsible for non-construction only if the plot was made available and she failed to build despite a reasonable opportunity. Mere expiry of the construction period does not establish default where possession was not delivered.

¶ 20

The authority bears the burden of showing that possession was offered, since a stipulation alone does not prove an offer.

¶ 18

The judgment does not cite any statutory provision or precedent.

04Reasoning

The Court read Clause 11 together with GMADA's own stand. GMADA relied on the litigation stay and incomplete development to show the area was not ready, yet it also charged the allottee for failing to build.

¶ 16–17

The Court held that if the plot could not be handed over, the allottee could not reasonably be expected to construct on it.

¶ 17

Respondent No. 2's written request of 17.02.2009 was unanswered by any communication fixing a date for possession. The physical handover occurred only on 02.04.2013.

¶ 6, 18

Meanwhile GMADA continued to collect instalments and raised non-construction demands. The Court therefore held that the deemed possession clause could not establish that the plot was available.

¶ 18

The Court found that the Rs. 4,16,726 demand, raised on 14.03.2013 before physical possession, could not be justified on failure to construct, because GMADA cannot attribute to the allottee a default that resulted from circumstances preventing construction.

¶ 21

The Court also noted that the State and National Commissions had concurrently recorded findings on feasibility, litigation and the absence of any offer of possession, and the National Commission found no ground for interference.

¶ 19

05Holding

The obligation to construct is dependent on delivery of possession, and a deemed possession clause cannot be invoked where the authority did not in fact make a demarcated plot available.

¶ 5, 20

The non-construction demand of Rs. 4,16,726 raised before possession on 02.04.2013 was unjustified.

¶ 21

The writ petition is dismissed. The directions of the District Forum, as upheld by the State and National Commissions, remain operative and enforceable according to their terms.

¶ 22

Pending applications, if any, stand disposed of.

¶ 23

The judgment does not specify the individual directions in the decision itself.

Punjab and Haryana High Court

Original Court PDF

Greater Mohali Area Development Authority (Gmada),vsThe National Consumer Disputes Redressal Commission,

Punjab and Haryana High Court · November 18, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment