Madhya Pradesh High CourtArbitration and MediationContract Law

Arbitral award granting interest above the agreed contractual rate contravenes Section 31(7)(a) and public policy, and is modified.

Wagad Infraprojects Pvt Ltdv.M/S Aryavart Projects Developers Pvt Ltd

Arbitral award granting interest above the agreed contractual rate contravenes Section 31(7)(a) and public policy, and is modified.. Wagad Infraprojects Pvt Ltd vs M/S Aryavart Projects  Developers Pvt Ltd. Madhya Pradesh High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the Tribunal's appropriation of the Rs. 4.41 crore performance security/retention money, for defect liability and defective construction, was without evidence or contrary to the contract and public policy.

The court held

The Tribunal's findings on the performance security, punch-list items, retention money for defective construction, and the Rs. 7.09 crore excess payment are upheld as supported by evidence and not contrary to public policy.

It also directed

The 18% interest on the Rs. 7.09 crore excess-payment component is reduced to 14% p.a., in accordance with the contractual rate and Section 31(7)(a).

The appeal is partly allowed. The remainder of the award is affirmed, and the Commercial Court's order is confirmed as modified.

01Facts

The appellant-claimant was a sub-contractor under a sub-contract dated 01.01.2013 with the respondent, an EPC contractor, for the Guna–Ashoknagar–Isagarh road.

¶ 25

The lump-sum bid was Rs. 96.71 crore, with commencement on 01.05.2013 and completion due by 31.01.2015.

¶ 25

The appellant stopped work in March 2016 and claimed Rs. 106.85 crore; the respondent counter-claimed Rs. 115.54 crore.

¶ 3

The Arbitral Tribunal, by a 2:1 majority, allowed Rs. 1.83 crore to the claimant and Rs. 18.42 crore (including Rs. 50 lakh costs) to the respondent, with interest.

¶ 3, 13, 26

The Commercial Court set aside the award on 16.06.2022 (MJC AV No. 30/2021).

¶ 4

This Court, in Arbitration Appeal No. 62/2022 (decided 10.07.2023), set aside that order as non-speaking and remanded.

¶ 4, 25

On remand, the Commercial Court dismissed the Section 34 application on 06.01.2025 (MJC AV No. 23/2021).

¶ 1

The appellant then filed the present Section 37 appeal.

The defect liability period ran to 22.03.2019.

¶ 27

Clause 5.1.8 of the contract fixed interest at 14% p.a. on amounts paid under Clause 5.1.6.

¶ 35

02Issues

i.1. Whether the Tribunal's appropriation of the Rs. 4.41 crore performance security/retention money, for defect liability and defective construction, was without evidence or contrary to the contract and public policy.

¶ 14–17, 26–31

ii.2. Whether the Rs. 2.01 crore award on punch-list items, and the burden of proof applied to it, is sustainable.

¶ 30

iii.3. Whether the Rs. 7.09 crore excess-payment award is based on no evidence or is perverse.

¶ 32

iv.4. Whether the 18% interest awarded on the Rs. 7.09 crore excess payment is contrary to Section 31(7)(a) and the contractual 14% rate.

¶ 33–39

v.5. Whether the Tribunal's failure to record oral evidence vitiates the award.

¶ 44

vi.6. Whether the scope of Section 37 permits this Court to reappraise the merits of the award and whether any Section 34 ground is made out.

¶ 22, 40–43

03Law Applied

The court applied Section 34 of the Arbitration and Conciliation Act, 1996, as narrowed by the proviso to Section 34(2A), which bars setting aside an award merely for erroneous application of law or reappreciation of evidence.

¶ 43

Patent illegality and perversity arise only where a finding is based on no evidence, irrelevant material, or ignores vital evidence, and the Section 37 court cannot act as an ordinary appellate court, citing Punjab State Civil Supplies Corp. v. Sanman Rice Mills (2024) and Rajasthan Rajya Vidyut Utpadan Nigam v. Parsa Kente Collieries (2026).

¶ 42–43

The court applied Delhi Metro Rail Corp. v. Delhi Airport Metro Express (2024) 6 SCC 357 as the touchstone for interference.

¶ 41

Under Section 31(7)(a), the tribunal may award interest at a reasonable rate only "unless otherwise agreed by the parties".

¶ 33–34

Following Associate Developers v. DDA (2015) 3 SCC 49, departure from a mandatory statutory provision is contrary to public policy.

¶ 38

Gayatri Balasamy v. ISG Novasoft Technologies (2025) 7 SCC 1 permits the court to modify an award in part.

¶ 46

Provisions in the judgment · 3 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 31Section 34Section 37

04Reasoning

The appropriation of the Rs. 4.41 crore security was supported by material: the claimant admittedly performed no work or maintenance after March 2016, and it had admitted completing only about 90% of the work.

¶ 27–28

Because no defect-liability work was done, the appropriation could not be said to conflict with public policy.

¶ 29

The punch-list award rested on the respondent's letter of 11.01.2016 and the claimant's reply, which did not deny non-execution, so the finding was documented.

¶ 30

The retention forfeiture for defective construction was supported by IE reports (R-34 to R-38), the Engineer-in-Chief's inspection note of 22.07.2016 (Annexure-63), and the unrectified defects.

¶ 31

The excess-payment finding relied on the IE certification (R-12) and the claimant's failure to rebut it with evidence; the court found it neither without evidence nor perverse.

¶ 32

The court accepted that the tribunal's 18% rate contravened the binding 14% contractual rate under Clause 5.1.8, which the court treated as "otherwise agreed" under Section 31(7)(a).

¶ 35–36

This departure from a statutory provision was held to be contrary to public policy and was corrected.

¶ 37–39

The absence of oral evidence was not a defect because both parties had agreed on record that the dispute could be decided on documents.

¶ 44

Otherwise, the court found no fundamental breach of natural justice, perversity, or patent illegality.

¶ 40

05Holding

The Tribunal's findings on the performance security, punch-list items, retention money for defective construction, and the Rs. 7.09 crore excess payment are upheld as supported by evidence and not contrary to public policy.

¶ 29–32, 40–41

The 18% interest on the Rs. 7.09 crore excess-payment component is reduced to 14% p.a., in accordance with the contractual rate and Section 31(7)(a).

¶ 39, 45

The appeal is partly allowed. The remainder of the award is affirmed, and the Commercial Court's order is confirmed as modified.

¶ 45–47
Madhya Pradesh High Court

Original Court PDF

Wagad Infraprojects Pvt LtdvsM/S Aryavart Projects Developers Pvt Ltd

Madhya Pradesh High Court · November 25, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment