01Facts
The petitioner, an EPC contractor, was awarded the improvement and widening of the Fultali–Jurichhara Section of NH-208 (Package-II), Tripura, under a Letter of Acceptance dated 24.11.2020
¶ 12 · p. 2The project was completed on 02.02.2023, and the respondent (NHIDCL) issued a completion certificate. The project remained under the Defect Liability and Maintenance Period.
¶ 13 · pp. 2–3The respondent identified defects and issued a cure notice giving sixty days for rectification.
¶ 13 · pp. 2–3By order dated 25.09.2026, the respondent temporarily suspended the petitioner from participating in ongoing and future bidding of NHIDCL/MoRTH, citing failure to complete rectification within time and failure to commence maintenance and repairs.
¶ 10–11 · p. 2 · ¶ 14 · p. 3The order was passed under MoRTH circular dated 06.10.2021.
¶ 10–11 · p. 2 · ¶ 14 · p. 3The petitioner filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996 and an application under Section 151 CPC seeking ad-interim ex parte stay of the suspension order.
¶ 5, 10 · pp. 1–2The petitioner's counsel contended that Clause 5 of the circular requires 15 days' notice, a written reply, and a personal hearing before a bar is imposed, and that the suspension was imposed for one month without any such notice.
¶ 15–16 · p. 3The respondent's counsel sought instructions.
¶ 17 · p. 4The court issued notice, directed a reply within four weeks, and listed the matter for 28.01.2027.
¶ 6–9 · p. 2 · ¶ 21 · p. 402Issues
i.1. Whether the suspension order dated 25.09.2026 could validly be passed without the 15-day notice and personal hearing required under Clause 5 of the MoRTH circular dated 06.10.2021.
¶ 15–16 · p. 3 · ¶ 18–19 · pp. 3–4ii.2. Whether the petitioner was entitled to an interim stay of the suspension order pending final disposal of the Section 9 petition.
¶ 10 · p. 2 · ¶ 20 · p. 403Law Applied
Section 9 of the Arbitration and Conciliation Act, 1996, which empowers the court to grant interim measures of protection.
¶ 5, 10 · pp. 1–2Section 151 CPC, which preserves the court's inherent power to make orders necessary for justice.
¶ 5, 10 · pp. 1–2MoRTH circular dated 06.10.2021, under which, before a contractor is barred from bidding for other construction, the authority must issue a notice allowing 15 days for a written reply and a personal hearing before the Competent Authority.
¶ 15 · p. 3 · ¶ 18–19 · pp. 3–4The order cites no judicial precedent.
The interim-relief principles of prima facie case, balance of convenience and irreparable harm are not expressly discussed in the order.
Provisions in the judgment · 2 · Linked ones open on LawLens
Code of Civil Procedure, 1908 Section 151
Arbitration and Conciliation Act, 1996 Section 9
04Reasoning
The court examined the circular directly and accepted the petitioner's submission that Clause 5 mandates a 15-day notice before suspension from bidding. The impugned order of 25.09.2026 was passed without any such notice, and the petitioner had been barred from ongoing and future bids for one month.
¶ 18–19 · pp. 3–4 · ¶ 16 · p. 3Because the procedural precondition in the circular was apparently not satisfied, the court found a prima facie basis for interim relief and treated the non-compliance as sufficient to stay the order at this stage. The order does not analyse the merits of the defect dispute or the petitioner's contractual obligations. Those issues were left open for the reply and rejoinder. The stay is therefore grounded in procedural non-compliance with the circular, not in any finding on the substance of the defects.
¶ 19 · p. 4 · ¶ 20 · p. 4 · ¶ 8 · p. 205Holding
The suspension order dated 25.09.2026 was passed without the 15-day notice and personal hearing mandated by Clause 5 of the MoRTH circular dated 06.10.2021, and the court so agreed.
¶ 18–19 · pp. 3–4The court accordingly granted interim relief and stayed the operation of the impugned order dated 25.09.2026 until further orders.
¶ 20 · p. 4The application under Section 151 CPC seeking exemption and the lengthy synopsis and list of dates were allowed or disposed of.
¶ 1–4 · p. 1The respondent is to file its reply within four weeks, with a rejoinder within two weeks thereafter, and the matter is listed for 28.01.2027.
¶ 8 · p. 2 · ¶ 21 · p. 4Original Court PDF
Ms Narendra Builders In JvvsNational Highways And Infrastructure Development Corporation Limited
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in