01Facts
The Corporation engaged the appellant to construct residential and dormitory blocks in IMT Manesar under a fixed-rate contract executed on 29 January 2007.
pp. 2–3Although the stipulated completion period was 15 months, the work was completed on 30 July 2009 after extensions; the Corporation did not levy liquidated damages.
pp. 2–3The appellant attributed the delay to matters including non-availability of a clear site and delayed drawings, and claimed additional costs.
pp. 2–3The arbitrator awarded amounts under certain claims, including for increased minimum wages and additional insurance charges, but rejected claims for price escalation and loss of profits and overheads.
pp. 2–3The appellant’s objections under Section 34 of the Arbitration and Conciliation Act, 1996 were dismissed by the Commercial Court.
pp. 2–3It appealed under Section 13 of the Commercial Courts Act, 2015, challenging the rejection of its escalation and loss-of-profits claims.
pp. 2–302Issues
i.Whether the arbitrator’s rejection of the claim for price escalation during the extended contract period warranted interference under Section 34 of the Arbitration and Conciliation Act, 1996.
pp. 4–6ii.Whether the rejection of the claim for loss of profits and overheads warranted interference, including on the ground that the arbitrator had not separately addressed that claim.
pp. 7–803Law Applied
Under Sections 34 of the Arbitration and Conciliation Act, 1996 and 13 of the Commercial Courts Act, 2015, appellate review of a decision on an arbitral award is limited; the court does not reassess the contractual dispute merely because another interpretation is possible.
pp. 4–5Associate Builders v. Delhi Development Authority and Ssangyong Engineering and Construction Co. Ltd. v. National Highways Authority of India support restraint where the arbitrator’s interpretation is reasonable and plausible; patent illegality is not a basis for reappreciating evidence or correcting every alleged error.
pp. 4–5Sections 54 and 73 of the Indian Contract Act, 1872 were invoked in support of compensation for delay-related losses.
pp. 3, 5–6K.N. Sathyapalan v. State of Kerala recognises that compensation for additional expenditure may be awarded where a contracting party’s failure affects performance, subject to the contract’s terms.
pp. 3, 5–6Under M/S Unibros v. All India Radio, a claim for loss of profitability or lost business opportunities requires substantial evidence; a formula-based calculation alone is insufficient.
p. 8Provisions in the judgment · 4 · Linked ones open on LawLens
Commercial Courts Act, 2015 Section 13
Arbitration and Conciliation Act, 1996 Section 34
Indian Contract Act, 1872 Section 54Section 73
04Reasoning
The contract fixed the appellant’s rates and, under Clauses 5.25 and 5.26, provided for extension of time without escalation, including where delay arose from matters such as delayed instructions.
pp. 5–7The arbitrator’s interpretation that enhanced rates were unavailable during the extension was a plausible reading of the agreement and could not be displaced merely because the appellant advanced an alternative interpretation under Sections 54 and 73.
pp. 5–7The arbitrator had separately allowed specified additional expenses, distinguishing those from a general claim for increased contractual rates; K.N. Sathyapalan did not require the escalation claim to be allowed contrary to the contract.
pp. 5–7As to loss of profits and overheads, the appellant did not establish actual lost opportunities or profits with substantial evidence.
pp. 7–8Although the arbitrator had not reproduced the claim under a separate heading, the basis for rejecting it was discernible from the award as a whole, and that omission did not establish a ground for interference.
pp. 7–805Holding
The High Court held that neither the rejection of the escalation claim nor the rejection of the loss-of-profits and overheads claim disclosed a basis to interfere with the arbitral award under Section 34.
p. 8The appeal was dismissed, with no order as to costs; pending miscellaneous applications, if any, were disposed of.
p. 8Original Court PDF