Punjab and Haryana High CourtArbitration and MediationContract Law

Contractor’s ₹3.6-Crore Escalation Claim Fails Despite Delay Attributed to Corporation; P&H HC Upholds Rejection Under Fixed-Rate Contract

M/S Brij Gopal Construction Co. Pvt. Ltd.v.Haryana State Industrial Andinfrastructure Development Corporation Ltd.

Contractor’s ₹3.6-Crore Escalation Claim Fails Despite Delay Attributed to Corporation; P&H HC Upholds Rejection Under Fixed-Rate Contract. M/S Brij Gopal Construction Co. Pvt. Ltd. vs Haryana State Industrial Andinfrastructure Development Corporation Ltd.. Punjab and Haryana High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

Whether the arbitrator’s rejection of the claim for price escalation during the extended contract period warranted interference under Section 34 of the Arbitration and Conciliation Act, 1996.

The court held

The High Court held that neither the rejection of the escalation claim nor the rejection of the loss-of-profits and overheads claim disclosed a basis to interfere with the arbitral award under Section 34.

It also directed

The appeal was dismissed, with no order as to costs; pending miscellaneous applications, if any, were disposed of.

01Facts

The Corporation engaged the appellant to construct residential and dormitory blocks in IMT Manesar under a fixed-rate contract executed on 29 January 2007.

pp. 2–3

Although the stipulated completion period was 15 months, the work was completed on 30 July 2009 after extensions; the Corporation did not levy liquidated damages.

pp. 2–3

The appellant attributed the delay to matters including non-availability of a clear site and delayed drawings, and claimed additional costs.

pp. 2–3

The arbitrator awarded amounts under certain claims, including for increased minimum wages and additional insurance charges, but rejected claims for price escalation and loss of profits and overheads.

pp. 2–3

The appellant’s objections under Section 34 of the Arbitration and Conciliation Act, 1996 were dismissed by the Commercial Court.

pp. 2–3

It appealed under Section 13 of the Commercial Courts Act, 2015, challenging the rejection of its escalation and loss-of-profits claims.

pp. 2–3

02Issues

i.Whether the arbitrator’s rejection of the claim for price escalation during the extended contract period warranted interference under Section 34 of the Arbitration and Conciliation Act, 1996.

pp. 4–6

ii.Whether the rejection of the claim for loss of profits and overheads warranted interference, including on the ground that the arbitrator had not separately addressed that claim.

pp. 7–8

03Law Applied

Under Sections 34 of the Arbitration and Conciliation Act, 1996 and 13 of the Commercial Courts Act, 2015, appellate review of a decision on an arbitral award is limited; the court does not reassess the contractual dispute merely because another interpretation is possible.

pp. 4–5

Associate Builders v. Delhi Development Authority and Ssangyong Engineering and Construction Co. Ltd. v. National Highways Authority of India support restraint where the arbitrator’s interpretation is reasonable and plausible; patent illegality is not a basis for reappreciating evidence or correcting every alleged error.

pp. 4–5

Sections 54 and 73 of the Indian Contract Act, 1872 were invoked in support of compensation for delay-related losses.

pp. 3, 5–6

K.N. Sathyapalan v. State of Kerala recognises that compensation for additional expenditure may be awarded where a contracting party’s failure affects performance, subject to the contract’s terms.

pp. 3, 5–6

Under M/S Unibros v. All India Radio, a claim for loss of profitability or lost business opportunities requires substantial evidence; a formula-based calculation alone is insufficient.

p. 8

Provisions in the judgment · 4 · Linked ones open on LawLens

Commercial Courts Act, 2015 Section 13

Arbitration and Conciliation Act, 1996 Section 34

Indian Contract Act, 1872 Section 54Section 73

04Reasoning

The contract fixed the appellant’s rates and, under Clauses 5.25 and 5.26, provided for extension of time without escalation, including where delay arose from matters such as delayed instructions.

pp. 5–7

The arbitrator’s interpretation that enhanced rates were unavailable during the extension was a plausible reading of the agreement and could not be displaced merely because the appellant advanced an alternative interpretation under Sections 54 and 73.

pp. 5–7

The arbitrator had separately allowed specified additional expenses, distinguishing those from a general claim for increased contractual rates; K.N. Sathyapalan did not require the escalation claim to be allowed contrary to the contract.

pp. 5–7

As to loss of profits and overheads, the appellant did not establish actual lost opportunities or profits with substantial evidence.

pp. 7–8

Although the arbitrator had not reproduced the claim under a separate heading, the basis for rejecting it was discernible from the award as a whole, and that omission did not establish a ground for interference.

pp. 7–8

05Holding

The High Court held that neither the rejection of the escalation claim nor the rejection of the loss-of-profits and overheads claim disclosed a basis to interfere with the arbitral award under Section 34.

p. 8

The appeal was dismissed, with no order as to costs; pending miscellaneous applications, if any, were disposed of.

p. 8
Punjab and Haryana High Court

Original Court PDF

M/S Brij Gopal Construction Co. Pvt. Ltd.vsHaryana State Industrial Andinfrastructure Development Corporation Ltd.

Punjab and Haryana High Court · November 16, 2026