01Facts
The Union of India accepted Sanmati Builders’ bid for railway-platform works through a communication dated 27 January 2017.
¶ 5–11A detailed acceptance letter dated 1 February 2017 contained two additional conditions concerning rates and quantities.
¶ 5–11Sanmati objected to those conditions and did not furnish the Performance Bank Guarantee (PBG).
¶ 5–11The Union terminated the contract on 6 April 2017 under Clause 16(4)(a) of GCC-2014 and forfeited the EMD.
¶ 5–11The sole arbitrator found the termination premature and awarded the EMD, part of the claim for allegedly irrecoverable advances, and costs; it rejected the Union’s counterclaim.
¶ 15–16The Commercial Court set aside the award under Section 34 of the Arbitration and Conciliation Act, 1996.
¶ 17–18Sanmati appealed under Section 37.
¶ 17–1802Issues
i.1. Whether the Commercial Court was justified under Section 34 in setting aside the arbitrator’s finding that termination and forfeiture of the EMD were unsustainable, given the disputed effect of the additional conditions in the detailed acceptance letter.
¶ 23–30ii.2. Whether the award of Rs.12,09,000 for alleged irrecoverable advances was liable to be set aside for want of evidence or because no work had commenced.
¶ 31–37iii.3. Whether the contractual provisions barred pre-award or post-award interest, and whether Clause 64(6) barred the award of costs.
¶ 38–45iv.4. Whether the Commercial Court had an adequate basis under Section 34 to set aside the rejection of the Union’s counterclaim.
¶ 46–4803Law Applied
Under Sections 34 and 37 of the Arbitration and Conciliation Act, 1996, an appellate court reviewing an order setting aside an award must remain within Section 34’s limited grounds and cannot substitute its own interpretation or reappreciate evidence merely because another view is possible; a plausible arbitral interpretation is ordinarily not displaced (*MMTC Ltd. v. Vedanta Ltd.*).
¶ 21An acceptance that materially varies an offer may constitute a counter-proposal requiring assent (*Padia Timber Company (P) Ltd. v. Board of Trustees of Visakhapatnam Port Trust*).
¶ 25An express contractual bar on pre-award interest must be given effect (*Union of India v. Manraj Enterprises*); post-award interest is separately considered under Section 31(7)(b), subject to applicable contractual terms.
¶ 39–42Section 31A governs costs, and a pre-dispute agreement allocating costs cannot, by itself, override the statutory costs regime; Clause 64(6) was not an absolute bar (*Union of India v. Om Vajrakaya Construction Company*).
¶ 44–45Provisions in the judgment · 5 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 11Section 28Section 31Section 34Section 37
04Reasoning
The Commercial Court treated the 27 January acceptance as conclusive without adequately addressing whether the later letter introduced unaccepted material conditions.
¶ 24–30The High Court held that the arbitrator’s view on the correspondence was plausible and that the Commercial Court had not demonstrated a Section 34 ground for substituting its own conclusion; the consequential setting aside of the EMD refund therefore could not stand.
¶ 24–30On Claim No. 4, the award recorded documentary material, including bank statements, vouchers and financial records, contrary to the Commercial Court’s premise that no evidence had been produced.
¶ 32–37The Court held that the claim for preparatory expenditure could not be rejected solely because work had not commenced, and that reassessing the evidence was impermissible absent a recognised ground for interference.
¶ 32–37Clause 64(5) barred pre-award interest, but the post-award interest direction required separate consideration under Section 31(7)(b).
¶ 39–42Clause 64(6) did not, by itself, prohibit the arbitrator from awarding costs under Section 31A, and the Commercial Court had not adequately justified setting aside the rejection of the counterclaim.
¶ 43–4805Holding
The appeal was allowed in part.
¶ 49–50The Commercial Court’s judgment was set aside insofar as it set aside the award concerning termination, refund of the EMD, Claim No. 4, costs and rejection of the Union’s counterclaim; those determinations were restored.
¶ 49–50The pre-award interest direction was modified to the extent inconsistent with Clause 64(5), while post-award interest was left to the applicable contractual terms and Section 31(7)(b).
¶ 50–52The parties were directed to bear their own costs of the appeal.