Delhi High CourtArbitration and MediationCivil Procedure and Evidence

Delhi HC Sends Back Challenge to 2018 Arbitral Award, Says Commercial Court Must Decide Limitation First

M/S Telecommunication Consultants India Limitedv.M/S Rajput Construction

Delhi HC Sends Back Challenge to 2018 Arbitral Award, Says Commercial Court Must Decide Limitation First. M/S Telecommunication Consultants India Limited vs M/S Rajput Construction. Delhi High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the objections under s. 34 were filed within the period prescribed by s. 34(3), including the condonable 30-day extension, such that the Commercial Court could entertain them.

The court held

The appeal is allowed. The Commercial Court erred in entertaining and allowing the s. 34 objections without first deciding whether they were filed within the period under s. 34(3).

It also directed

The impugned judgment dated 13.04.2023 is set aside, and the objections are remitted to the Commercial Court for fresh decision. The parties or their representatives are to appear before the Commercial Court on 14.12.2026, and the Commercial Court is directed to decide the objections as expeditiously as possible, given that the award dates from 2018.

01Facts

The appellant was the successful bidder in a tender of the Madhya Pradesh Rural Road Development Authority. The parties signed an MOU dated 18.10.2007, under which the work would go to the respondent upon acceptance of the bid, and the work was awarded to the respondent on a back-to-back basis on 07.12.2007.

¶ 2

The appellant invoked arbitration on 07.04.2014, a sole arbitrator was appointed, and an ex parte award was passed on 15.05.2018.

¶ 2.1

The respondent filed objections under s. 34 of the Arbitration and Conciliation Act, 1996 on 27.05.2019. It claimed that it first received a copy of the award on 01.03.2019 under the RTI Act, 2005, and it challenged the unilateral appointment of the arbitrator.

¶ 2.2

The appellant raised limitation as a preliminary objection.

¶ 2.2

The Commercial Court allowed the objections on the ground that the award was made by a unilaterally appointed arbitrator, without deciding limitation.

¶ 2.3

That judgment, dated 13.04.2023, is challenged in this appeal.

¶ 1

02Issues

i.1. Whether the objections under s. 34 were filed within the period prescribed by s. 34(3), including the condonable 30-day extension, such that the Commercial Court could entertain them.

¶ 3, 6, 8

ii.2. Whether the Commercial Court was required to decide the question of limitation before adjudicating the challenge based on s. 12(5) (unilateral appointment of the arbitrator).

¶ 3, 8

03Law Applied

The court relied on s. 34(3) of the Arbitration Act, which fixes a three-month limitation period from receipt of the award, with a proviso allowing a further 30 days on sufficient cause and no further extension.

¶ 5, 6

Because s. 34(3) falls within s. 29(2) of the Limitation Act, 1963, s. 5 of that Act is excluded, and the court may condone delay only up to 30 days.

¶ 6

This position rests on Consolidated Engineering Enterprises v. Principal Secretary, Irrigation Department (2008) 7 SCC 169, Singh Enterprises v. CCE (2008) 3 SCC 70, Commissioner of Customs & Central Excise v. Hongo India (P) Ltd. (2009) 5 SCC 791, and Chhattisgarh State Electricity Board v. CERC (2010) 5 SCC 23, which hold that where a special statute prescribes a limitation period with a capped extension, the general power under s. 5 stands excluded.

¶ 7.1, 7.2, 7.3, 7.4

The respondent relied on s. 12(5) of the Act and Bhadra International (India) Pvt. Ltd. v. Airports Authority of India, 2026 INSC 6, for the proposition that an award by an ineligible arbitrator is a nullity. The judgment does not analyse this authority.

¶ 4

Provisions in the judgment · 8 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 34Section 12Section 33

Limitation Act, 1963 Section 29Section 5

Central Excise Act, 1944 Section 35

Electricity Act, 2003 Section 125Section 111

04Reasoning

The court held that limitation under s. 34(3) is a threshold question that must be decided before the merits of any ground, including s. 12(5), can be considered.

¶ 8

The Commercial Court set aside the award without first determining whether the 27.05.2019 filing was within time, which was a contested issue on the respondent's claimed date of receipt, 01.03.2019.

¶ 2.2, 8

Because the Commercial Court did not record a finding on limitation, the court did not reach the merits of the s. 12(5) challenge or the respondent's nullity argument.

¶ 8

The court therefore set aside the impugned judgment and remitted the matter for fresh consideration in accordance with law.

¶ 9

05Holding

The appeal is allowed. The Commercial Court erred in entertaining and allowing the s. 34 objections without first deciding whether they were filed within the period under s. 34(3).

¶ 8

The impugned judgment dated 13.04.2023 is set aside, and the objections are remitted to the Commercial Court for fresh decision. The parties or their representatives are to appear before the Commercial Court on 14.12.2026, and the Commercial Court is directed to decide the objections as expeditiously as possible, given that the award dates from 2018.

¶ 9, 10, 11
Delhi High Court

Original Court PDF

M/S Telecommunication Consultants India LimitedvsM/S Rajput Construction

Delhi High Court · November 17, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment