In brief

The question

1. Whether the petitioner's bid could be excluded from technical evaluation for failure to separately digitally sign each uploaded document, where the documents were uploaded within time in a composite PDF in the alternative field, and whether that deviation was material under the Assam Public Procurement Rules, 2020.

The court held

The exclusion of the petitioner, recorded without examining whether the placement of documents was a material deviation, could not be sustained, and the post-bid division of the composite package into two separate allotments violated Section 8(3) of the Assam Public Procurement Act read with Rule 8(8) of the 2020 Rules.

It also directed

The writ petition was partly allowed. The exclusion decision was set aside to that extent and the matter was remitted to the bid evaluation committee to decide the petitioner's preliminary responsiveness within six weeks, strictly on the original electronic bid and under Rule 23(10), (13), (14) and (15).

The separate allotments to respondent Nos. 5 and 6 were set aside, and no work order may issue on them. If the petitioner's bid is found responsive, its financial bid is to be treated under the original NIT. The identical L1 situation must be resolved under the bidding documents and applicable law, with no separate allotment of the two works.

The respondents may initiate fresh tender process if justified. Parties bear their own costs.

01Facts

The Public Works Roads Department, Government of Assam, floated NIT No. ASOM-MALA-3.0-25-26-52 under Asom Mala 3.0 on 20.01.2026 for the improvement of two roads in Bongaigaon district, (I) Shahid Bedi to North Salmara Junction Road and (II) Talaguri Basugaon Road, with a combined estimated value of Rs. 8841.28 lakhs.

¶ 3-4

Three bidders participated: the petitioner, respondent No. 5 (M/s Macrocosm Builders), and respondent No. 6 (Srimanta Sankardeva Infracon Pvt. Ltd.).

¶ 5

The petitioner submitted its bid on 02.02.2026 at 11.08 AM, and the e-procurement portal generated bid ID 296141.

¶ 6

The technical evaluation sheet recorded that the petitioner's bid was not evaluated because it had not digitally signed and uploaded the bid documents. Respondent Nos. 5 and 6 were found technically qualified and quoted identical prices equal to the full estimate, so they were shown as joint L1.

¶ 7

The department explained that the petitioner uploaded Part-I (Tech1.pdf) in the "bid documents" field and Part-II (Tech2.pdf) in the "technical qualifications" field, without separately digitally signed copies of each document.

¶ 11

The Chief Engineer's instruction dated 18.11.2026 stated that the two roads had separate estimates and bills of quantities with a combined abstract. The tender committee allotted one road to each joint L1 bidder, with their consent, to avoid cancellation and delay, and the decision was said to have government approval.

¶ 12

The printed bid documents produced before the court show each page physically signed and sealed, with scanned copies uploaded in a composite PDF.

¶ 23, 29

02Issues

i.1. Whether the petitioner's bid could be excluded from technical evaluation for failure to separately digitally sign each uploaded document, where the documents were uploaded within time in a composite PDF in the alternative field, and whether that deviation was material under the Assam Public Procurement Rules, 2020.

¶ 16-25, 31-32

ii.2. Whether the department could divide the composite two-road package and allot one road each to the two joint L1 bidders after the financial bids were opened.

¶ 34-42

03Law Applied

The court applied the judicial review principles in Tata Cellular v. Union of India, Jagdish Mandal v. State of Orissa and Afcons Infrastructure v. Nagpur Metro Rail Corporation, under which interference is warranted only where a decision is mala fide, favours someone, or is so arbitrary or irrational that no reasonable authority could take it.

¶ 14-15

The court relied on clauses 12.1, 18.1-18.2, 19.1, 19.4 and 26 of the bidding documents, and on the e-procurement portal instructions (Nos. 9, 14, 18-20), which permit clubbing of documents and treat digital authentication at freezing as the operative act.

¶ 17, 19, 22

Rule 23 of the Assam Public Procurement Rules, 2020, in particular Rule 23(10), (11), (13), (14) and (15), governs preliminary responsiveness, the definition of material deviation, and the bar on post-deadline changes to a bid; immaterial non-conformities may be waived or rectified.

¶ 18, 24-25

Section 8(3) of the Assam Public Procurement Act permits division of procurement only before bids are invited, with reasons recorded, and Rule 8(8) of the 2020 Rules bars any division after bids are invited "under any circumstances".

¶ 38-39

Article 14 of the Constitution applies where post-bid division prejudices prospective tenderers who were deterred by the high value of the composite package.

¶ 40

Provisions in the judgment · 2 · Linked ones open on LawLens

Commercial Documents Evidence Act, 1939 Section 26

ASSAM PUBLIC PROCUREMENT ACT, 2017 Section 8

04Reasoning

The absence of a separate digital signature on each scanned document is not shown by any tender condition, portal instruction or statute, and so cannot be equated with the absence of digital authentication of the bid itself.

¶ 22

The petitioner's bid was submitted in time and its documents were available in the electronic bid.

¶ 23

Placement in the wrong field did not dispense with the procedural requirement, but the department had not shown how the misplacement affected the authenticity or substance of the offer or prejudiced other bidders.

¶ 22, 28

The evaluation sheet's ground was inconsistent with the department's later admission that the bid was uploaded with a digital signature.

¶ 26-27

Because exclusion was made without applying the Rule 23 materiality test, the decision did not reflect the statutory test of responsiveness.

¶ 25, 31

The court did not declare the bid responsive, since that is for the committee, and it barred any fresh documents or improvement of the bid.

¶ 30, 33

Separate estimates did not show that the NIT contemplated separate awards. The package was notified as one procurement and evaluated as a whole, and the division came only after the financial result emerged.

¶ 41

Consent of the bidders and government approval cannot validate a step the statute prohibits.

¶ 42

Concerns about delay under public-interest arguments do not justify departing from the prescribed procedure.

¶ 43

05Holding

The exclusion of the petitioner, recorded without examining whether the placement of documents was a material deviation, could not be sustained, and the post-bid division of the composite package into two separate allotments violated Section 8(3) of the Assam Public Procurement Act read with Rule 8(8) of the 2020 Rules.

¶ 32, 44

The writ petition was partly allowed. The exclusion decision was set aside to that extent and the matter was remitted to the bid evaluation committee to decide the petitioner's preliminary responsiveness within six weeks, strictly on the original electronic bid and under Rule 23(10), (13), (14) and (15).

¶ 45-47, 50

The separate allotments to respondent Nos. 5 and 6 were set aside, and no work order may issue on them. If the petitioner's bid is found responsive, its financial bid is to be treated under the original NIT. The identical L1 situation must be resolved under the bidding documents and applicable law, with no separate allotment of the two works.

¶ 48-49

The respondents may initiate fresh tender process if justified. Parties bear their own costs.

¶ 50-51
Gauhati High Court

Original Court PDF

Purbanchal Buildtech Pvt. Ltd And AnrvsThe State Of Assam And Ors

Gauhati High Court · November 25, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment