Gauhati High CourtAdministrative and Public LawEmployment and Labour Law

Section 12 contract labour licence does not satisfy a tender's Section 7 labour registration requirement.

Sri Subhashis Chakrabortyv.The State Of Assam

Section 12 contract labour licence does not satisfy a tender's Section 7 labour registration requirement.. Sri Subhashis Chakraborty vs The State Of Assam. Gauhati High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether a licence issued under Section 12(1) CLRA satisfies the "labour registration" requirement of Clause 10 of the NIT, or whether that requirement refers to registration under Section 7 CLRA.

The court held

A Section 12 licence under the CLRA cannot be treated as the "labour registration" required under Clause 10 of the NIT, and the Tender Committee's interpretation was plausible and not arbitrary or irrational.

It also directed

No interference under Article 226 was warranted.

The Court expressed no opinion on comparative technical or financial capability, and the successful bidder remains obliged to obtain and maintain the Section 12 licence before executing the contract work.

The writ petition was dismissed with no order as to costs, and the interim order dated 23.10.2026 was vacated.

01Facts

The petitioner, an existing contractor for transportation of food grains under the National Food Security Act (NFSA) in Bongaigaon district since 2022, challenged the Tender Committee's decision dated 14.10.2026 rejecting his technical bid under a Notice Inviting Tender dated 27.08.2026.

¶ 1, 2, 18

Five bidders participated. The Committee, on 13.10.2026, found the petitioner and three others had not furnished the requisite Labour Registration Certificate. Only Respondent No. 5 was found compliant and recommended for opening of its financial bid.

¶ 3

Clause 10 of the NIT required up-to-date labour registration, ESIC and EPF.

¶ 4

The petitioner submitted a labour licence dated 31.07.2026 issued under Section 12(1) of the Contract Labour (Regulation and Abolition) Act, 1970 (CLRA) by the Assistant Labour Commissioner, Nagaon, valid for Nagaon district, though he claimed it was valid across Assam.

¶ 14, 15

Respondent No. 5 furnished a certificate of registration dated 31.07.2026 under Section 7(2) CLRA, issued by the same authority.

¶ 16

The cause title names Respondent No. 5 "Vivek Transport Agency," while para. 16 refers to "Bibek Transport Agency."

¶ 16

The petitioner alleged the process was hurried and favoured Respondent No. 5.

¶ 24

The Court had passed an interim order dated 23.10.2026.

¶ 28

02Issues

i.1. Whether a licence issued under Section 12(1) CLRA satisfies the "labour registration" requirement of Clause 10 of the NIT, or whether that requirement refers to registration under Section 7 CLRA.

¶ 7, 13, 14

ii.2. Whether the Tender Committee's interpretation and rejection of the petitioner's technical bid were arbitrary or irrational, warranting interference under Article 226 of the Constitution.

¶ 20, 21, 22

iii.3. Whether the petitioner's prior satisfactory experience as a food grain transporter can substitute for compliance with the independent eligibility condition in Clause 10.

¶ 18

iv.4. Whether the decision to proceed with the sole technically qualified bidder was contrary to Rule 23(16)(v) of the Assam Public Procurement Rules, 2020 (APPR).

¶ 25

03Law Applied

Section 7 CLRA requires registration of an establishment by its principal employer, and a certificate under Section 7(2) is issued in Form II under Rule 18 of the Assam Contract Labour (Regulation and Abolition) Rules, 1971.

¶ 8, 9

Section 12 requires a contractor to hold a licence before executing work through contract labour, and this licence is distinct from establishment registration; the two documents are not interchangeable.

¶ 10, 11

A Section 12 licence is not an eligibility requirement at the bid stage but must be obtained before work begins.

¶ 12

Tender authorities may interpret their conditions, and judicial review is limited to arbitrariness, mala fides, irrationality, or material departure from tender conditions; a plausible, rational interpretation cannot be substituted by the Court.

¶ 20, 21

Experience and eligibility conditions operate independently.

¶ 18

Rule 23(16)(v) APPR 2020 permits continuation where fewer than three bidders qualify, but does not dispense with satisfying eligibility conditions.

¶ 25

Provisions in the judgment · 3

National Food Security Act, 2012 Section 2Section 7Section 12

04Reasoning

Clause 10 uses the term "labour registration" and not "labour licence," so the expression must be read in light of the CLRA's structure.

¶ 13

The petitioner's Section 12(1) licence, even if valid across Assam, remained a licence and did not become a Section 7(2) registration certificate merely because of its territorial scope.

¶ 15

Respondent No. 5's certificate, by contrast, expressly recorded issuance under Section 7(2).

¶ 16

The fact that the certificate was issued at Nagaon did not render it unacceptable, as the NIT did not prescribe the issuing office or limit registration to the tendered work.

¶ 17

The petitioner's experience under the NFSA was a separate criterion and could not compensate for the missing Clause 10 document.

¶ 18

The Committee's reading of "registration" as distinct from "licence" was held to be rational and not an unreasonable construction of the NIT.

¶ 19, 22

The Court found no evidence that the Committee applied a different standard to Respondent No. 5 or relaxed the condition in his favour, and noted that the Labour Officer's clarification dated 29.09.2026 supported the distinction.

¶ 23

The speed of the process was not shown to involve a departure from the prescribed timeline or discriminatory treatment, and the urgency of NFSA food distribution was a relevant consideration.

¶ 24

Rule 23(16)(v) APPR did not authorise waiver of eligibility conditions.

¶ 25

05Holding

A Section 12 licence under the CLRA cannot be treated as the "labour registration" required under Clause 10 of the NIT, and the Tender Committee's interpretation was plausible and not arbitrary or irrational.

¶ 13, 22, 26

No interference under Article 226 was warranted.

¶ 26

The Court expressed no opinion on comparative technical or financial capability, and the successful bidder remains obliged to obtain and maintain the Section 12 licence before executing the contract work.

¶ 27

The writ petition was dismissed with no order as to costs, and the interim order dated 23.10.2026 was vacated.

¶ 28
Gauhati High Court

Original Court PDF

Sri Subhashis ChakrabortyvsThe State Of Assam