01Facts
The petitioner, a developer, constructed the "SMR Vinay Estella" residential project.
Respondent No. 2 bought Flat No. 412, E2 Block, under an agreement of sale dated 10.05.2017, with possession due within 24 months plus a 6-month grace period.
¶ 2The petitioner asserts the project was completed in time and that other flat owners in the block took possession from 11.09.2019, whereas Respondent No. 2 delayed taking possession until the sale deed of 26.06.2020.
¶ 2Respondent No. 2 filed a complaint before the Regulatory Authority on 21.03.2022 seeking compensation for delay.
¶ 2The matter was posted for objections on 25.07.2023. No hearing took place that day, and the matter was posted for orders 2½ months later.
¶ 3On 07.10.2023 the Authority directed the petitioner to pay ₹15,68,344 as delayed-period interest, with MCLR-based interest at 2% from 12.05.2019 to 21.03.2022.
¶ 3The petitioner challenged this order and the undated Guidelines (Annexure-M) under Articles 226 and 227.
¶ 1, 3The petitioner also challenged an e-mail notice dated 13.12.2023.
¶ 1, 302Issues
i.1. Whether the writ petition is maintainable despite the statutory appeal under Section 44 of the RERA Act, where the Authority lacked jurisdiction and natural justice was violated.
¶ 4(i), 19ii.2. Whether the impugned order was passed in violation of the principles of natural justice.
¶ 18–19iii.3. Whether the undated Guidelines (Annexure-M), insofar as they divest the Adjudicating Officer of jurisdiction over Section 18(1) proviso claims, are ultra vires the RERA Act and the Karnataka RERA Rules, 2017.
¶ 20–21iv.4. Whether the Regulatory Authority had jurisdiction to adjudicate a complaint seeking delayed-period interest and compensation, as opposed to refund.
¶ 22–28v.5. Whether the bench constitution under the Notification dated 10.03.2022, which named a specific Member to head a bench but was heard by a different Member, vitiated the order by invalid delegation.
¶ 29–31, 34vi.6. Whether the Authority followed the enquiry procedure prescribed under Rule 29(2) of the Karnataka RERA Rules, 2017.
¶ 32–3303Law Applied
Section 18(1) of the RERA Act provides for refund with interest and for interest for delayed possession, and Section 18(3) provides for compensation for other breaches.
¶ 22Section 71 provides for an Adjudicating Officer, a judicial officer, to adjudicate compensation under Sections 12, 14, 18 and 19, and Section 31(2), as amended, permits the Authority to prescribe complaint procedures.
¶ 21, 23In M/s. New Tech Promoters & Developers Pvt. Ltd. v. State of U.P. (2021) 18 SCC 1, para. 85, refund, interest on refund, and delayed-possession interest fall within the Regulatory Authority's domain, while compensation and interest thereon under Sections 12, 14, 18 and 19 fall exclusively within the Adjudicating Officer's domain.
¶ 23–24Under Section 81, delegation of non-legislative powers is permissible, save for compensation adjudication.
¶ 6, 40Regulations 11(4) and 12 of the Karnataka RERA (General) Regulations, 2022 authorise constitution of benches and assignment of matters to single members.
¶ 34Rule 29(2) of the Karnataka RERA Rules, 2017 prescribes a summary enquiry procedure with sub-rules (a) to (j).
¶ 32The court considered Marvel Landmarks Pvt. Ltd. v. State of Maharashtra (2026 SCC OnLine Bom 2462), paras. 35, 40–42, and distinguished it.
¶ 27–28The petitioner's reliance on State of M.P. v. B.R. Thakare (2002) 10 SCC 338 and Ballabhdas Agarwala v. J.C. Chakravarty (1960 SC) was noted in the arguments, but the court did not expressly rely on either.
¶ 9, 15Provisions in the judgment · 9 · Linked ones open on LawLens
Real Estate (Regulation and Development) Act, 2016. 9 provisions
Section 12Section 14Section 18Section 19Section 31Section 44Section 71Section 72Section 8104Reasoning
The natural justice violation was established on the face of the order sheets. The Authority accepted the complainant's memo of calculation on 25.07.2023 and reserved orders without giving the respondent-promoter an opportunity to present its case.
¶ 19This justified entertaining the writ despite the alternative appeal remedy under Section 44.
¶ 19On jurisdiction, the court applied New Tech and found that the complaint sought delayed-period interest, which is within the Regulatory Authority's competence. The prayer's label in the online portal (Sections 12 and 18) did not control, because the portal's bottom-line relief read "compensation for delay" and the order itself granted interest.
¶ 25–26The Bombay High Court's Marvel Landmarks decision was distinguished because it concerned delegation of a refund power to the Adjudicating Officer, not the reverse.
¶ 28The challenge to the bench composition was treated as hyper-technical, since named incumbents change over time and the Notification concerned bench numbers. The court nonetheless advised amendment of the Notification to avoid such challenges.
¶ 30–31The guidelines were upheld because they regulate complaint procedure and fall within Section 31(2), and they do not conflict with New Tech.
¶ 20–21The court found that none of the orders, including the impugned order, showed compliance with the Rule 29(2) summary enquiry procedure, and it issued directions to correct this across pending matters.
¶ 32–3305Holding
The Regulatory Authority had jurisdiction over the delayed-period interest claim, but the order dated 07.10.2023 is quashed because of the natural justice violation and non-compliance with Rule 29.
¶ 19, 25, 33, 36(ii)The challenge to the Annexure-M Guidelines as ultra vires was rejected.
¶ 20–21The court did not separately address the prayer to quash the e-mail notice dated 13.12.2023 (Annexure-P).
The writ petition is allowed. The matter is remitted for fresh consideration under Section 18 read with Rule 29(2) of the Karnataka RERA Rules, 2017.
¶ 36(i) · ¶ 36(iii)The Authority must issue a corrigendum or amended Notification identifying bench members by office rather than name, and must issue guidelines directing strict adherence to Rules 29 and 30.
¶ 31, 36(iv), 36(v)Original Court PDF