01Facts
The petitioner sought transfer into its name of a 3.3 MW wind mill and consequential approval to energise it through the 110/33 KV Renfra Malaikovilur Pooling Sub-Station.
The developer had registered the wind mill and, after purchasing the land and wind mill, the petitioner applied for name transfer on 26 March 2026 and paid the required charges. The application remained pending following a 27 May 2026 circular directing field officers not to grant solar and wind connectivity approvals; the petitioner also relied on a site inspection confirming the wind mill was fit for commissioning.
pp. 3–4The respondents submitted that a consolidated application covering name transfer, Noted-for-Record approval, and execution of an Energy Wheeling Agreement would be considered.
p. 502Issues
i.1. Whether the respondents should be directed to process the petitioner’s request for name transfer and Noted-for-Record approval for energising the wind mill.
p. 2 · p. 5ii.2. Whether the petitioner was required to submit a consolidated application covering those requests and the Energy Wheeling Agreement.
p. 503Law Applied
The petition invoked the High Court’s jurisdiction under Article 226 of the Constitution of India.
p. 2Its directions were based on the respondents’ submission that the consolidated application would be considered and on the Court’s consequent direction that the three identified stages be completed within the stipulated period.
p. 504Reasoning
The Court did not determine the substantive merits of the petitioner’s entitlement to the approvals or address the validity or effect of the 27 May 2026 circular.
p. 5Instead, it relied on the respondents’ submission that they would consider a consolidated application covering name transfer, Noted-for-Record approval, and the Energy Wheeling Agreement. The Court directed the petitioner to submit that application and imposed a three-week deadline for completion of all three stages.
p. 505Holding
The Court disposed of the writ petition, directing the petitioner to submit a consolidated application forthwith and the fourth respondent, in consultation with the third respondent, to complete the three stages within three weeks of receiving it.
p. 6No costs were ordered, and the connected miscellaneous petition was closed.
p. 6Original Court PDF
M/S. ARUN INDIAN MOTORS,vsTHE TAMIL NADU POWER DISTRIBUTION CORPORATION LIMT
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in