Madras High CourtAdministrative and Public LawContract Law

Madras HC Orders 3.3-MW Windmill Name Transfer, Energisation Approval And Wheeling Agreement Within 3 Weeks Of Buyer’s Consolidated Filing

M/s.Blue Breeze Enterprisesv.THE TAMIL NADU POWER DISTRIBUTION CORPORATION LIMT

Madras HC Orders 3.3-MW Windmill Name Transfer, Energisation Approval And Wheeling Agreement Within 3 Weeks Of Buyer’s Consolidated Filing. M/s.Blue Breeze Enterprises vs THE TAMIL NADU POWER DISTRIBUTION CORPORATION LIMT. Madras High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the respondents should be directed to process the petitioner’s request for name transfer, “Noted-for-Record” approval, and an Energy Wheeling Agreement.

The court held

The Court disposed of the writ petition, directing the petitioner to submit a consolidated application forthwith and the fourth respondent, in consultation with the third respondent, to complete the three specified steps within three weeks of receipt.

It also directed

No costs were ordered, and the connected miscellaneous petition was closed.

01Facts

The petitioner sought transfer into its name of a 3.3 MW wind mill registered to its developer, together with “Noted-for-Record” approval for energising the wind mill and execution of an Energy Wheeling Agreement.

It had applied for the name transfer and paid the required charges, but the application remained pending after a 27 May 2026 circular-memo directing that approvals relating to wind and solar connectivity not be granted.

pp. 3–4

The petitioner also relied on a site inspection confirming that the wind mill was fit for commissioning.

p. 4

In response to the petition, the respondents’ counsel stated that the three requested steps would be considered on receipt of a consolidated application.

p. 5

02Issues

i.1. Whether the respondents should be directed to process the petitioner’s request for name transfer, “Noted-for-Record” approval, and an Energy Wheeling Agreement.

p. 2, 5

ii.2. Whether the respondents should complete those steps within a specified time after receiving a consolidated application.

p. 5

03Law Applied

The petition invoked the High Court’s jurisdiction under Article 226 of the Constitution to seek mandamus.

p. 2

The Court did not cite or elaborate on any statutory provision, precedent, or substantive legal test.

Its direction was based on the respondents’ submission that the three requested steps would be considered upon receipt of a consolidated application.

p. 5

04Reasoning

The Court recorded the respondents’ submission that a consolidated application covering the name transfer, “Noted-for-Record” approval, and Energy Wheeling Agreement would be considered.

p. 5

In light of that submission, it directed the petitioner to submit the consolidated application and required the fourth respondent, in consultation with the third respondent, to complete all three steps within three weeks of receiving it.

p. 5

05Holding

The Court disposed of the writ petition, directing the petitioner to submit a consolidated application forthwith and the fourth respondent, in consultation with the third respondent, to complete the three specified steps within three weeks of receipt.

pp. 5–6

No costs were ordered, and the connected miscellaneous petition was closed.

p. 6
Madras High Court

Original Court PDF

M/s.Blue Breeze EnterprisesvsTHE TAMIL NADU POWER DISTRIBUTION CORPORATION LIMT

Madras High Court · November 10, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment