01Facts
The petitioner, a housekeeping-services company, held a three-year contract with the East Central Railway to provide onboard housekeeping services at RNCC Depot.
¶ 2–5After the Central Government’s notification dated 19 January 2017 increased minimum wages, the petitioner sought reimbursement of the resulting additional labour costs.
¶ 2–5The Railway refused, relying on the contract’s Price Variation Clause (PVC).
¶ 2–5The contract was extended until 7 April 2019, and the petitioner contended that it remained legally obliged to pay the revised minimum wages but was not adequately compensated under the PVC.
¶ 2–5The petitioner relied on Union of India v. M/s A2Z Infra Services Ltd.; the respondents opposed the petition but filed no counter affidavit.
¶ 6–702Issues
i.Whether the petitioner was entitled to reimbursement of additional labour costs resulting from the minimum-wage revision under the notification dated 19 January 2017
¶ 903Law Applied
The Court proceeded on the basis that the petitioner was statutorily required to pay workers the revised minimum wages and that the contractual PVC should be interpreted to give effect to its purpose of neutralising labour-cost variations.
¶ 10It held that reimbursement could not be denied merely because the PVC was linked to the Consumer Price Index, particularly where the contract also required compliance with statutory labour laws.
¶ 10The Court relied on the Bombay High Court’s decision in A2Z Infraservices Ltd. v. Union of India & Ors., stating that the Railways must neutralise increased labour costs caused by a revision in minimum wages during the subsistence of the contract, and noted that the view had been upheld by the Supreme Court.
¶ 11The judgment does not identify the specific statute governing minimum wages or provide full citations for the A2Z decisions.
04Reasoning
The petitioner’s statutory obligation to pay the revised minimum wages generated additional labour costs while the contract remained in force.
¶ 10The Court considered that the PVC’s purpose was to neutralise labour-cost variations and rejected the Railway’s reliance on its Consumer Price Index linkage as a sufficient reason to deny reimbursement, given the contract’s requirement to comply with labour laws.
¶ 10Applying the A2Z decisions, the Court concluded that the Railway was liable for the increased costs attributable to the revised minimum wages during the contractual period.
¶ 11–1205Holding
The Court held that the petitioner was entitled to reimbursement of the difference in minimum wages arising from the notification dated 19 January 2017, for the period during which the contract remained in force, and allowed the writ petition to that extent.
¶ 12Interlocutory applications, if any, were disposed of.
¶ 13Original Court PDF
M/s Aroom Aviation Services Pvt. Ltd.vsUnion of India
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in