Karnataka High CourtArbitration and MediationCivil Procedure and Evidence

Pendency of a review petition, without any interim order, is not sufficient cause to condone delay in commercial appeals.

M.B. PATIL CONSTRUCTIONS LIMITEDv.THE EXECUTIVE ENGINEER

Pendency of a review petition, without any interim order, is not sufficient cause to condone delay in commercial appeals.. M.B. PATIL CONSTRUCTIONS LIMITED vs THE EXECUTIVE ENGINEER. Karnataka High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the delay of 240 days in preferring COMAP No. 200010/2026 (Department) can be condoned under Section 5 of the Limitation Act, 1963, as applied to Section 37 of the Arbitration and Conciliation Act, 1996 read with Section 13(1-A) of the Commercial Courts Act, 2015.

The court held

Neither the Department nor the Contractor established sufficient cause for condoning the delays of 240 days and 422 days, respectively. The pendency of a review petition, without any interim order, and filed by the other party, does not justify delay in filing a statutory appeal.

It also directed

The applications for condonation of delay in I.A. No. 3/2026 (COMAP No. 200010/2026) and I.A. No. 1/2026 (COMAP No. 200024/2026) are rejected. Consequently, both commercial appeals are dismissed.

The judgment of the Principal District Judge, Kalaburagi, dated 02.05.2025 in Commercial Arbitration Suit No. 5/2019 therefore stands.

01Facts

The Executive Engineer, PWP and IWTD Division, Kalaburagi (the Department) and M.B. Patil Constructions Ltd. (the Contractor) were parties to an arbitration. The sole arbitrator passed an award on 30.10.2018 in CMP No. 200006/2014, rectified on 08.03.2019.

¶ 2

The Department challenged the award in Commercial Arbitration Suit No. 5/2019. The Principal District Judge, Kalaburagi, decided the suit on 02.05.2025.

¶ 1 · p. 5

The Department's first portion of the judgment was favourable, but the second portion was ambiguous, prompting internal consultation before an appeal was decided upon.

¶ 2 · p. 5

The Contractor filed Review Petition No. 1/2025 on 02.06.2025 concerning non-consideration of its liquidated damages claim.

¶ 4 · p. 7

The review was dismissed on 27.01.2026 as not maintainable, with liberty to approach the competent court.

¶ 2, 4 · pp. 5, 7–8

The Department filed W.P. No. 200864/2026, which was disposed of on 23.02.2026. The Contractor filed E.P. No. 6/2026.

¶ 3 · p. 6

The Department filed COMAP No. 200010/2026 with I.A. No. 3/2026 seeking condonation of 240 days' delay. The Contractor filed COMAP No. 200024/2026 with I.A. No. 1/2026 seeking condonation of 422 days' delay.

¶ 2–4 · pp. 5–7

Both parties cited administrative delay, official transfers, and the pendency of the review petition as reasons. The Contractor also pleaded ill health and counsel's inaction.

¶ 4 · pp. 7–8

It is admitted that both appeals were filed beyond limitation, and that no interim order was passed in the review petition. The review was filed by the Contractor, not the Department.

¶ 8, 12 · p. 10, 18

02Issues

i.1. Whether the delay of 240 days in preferring COMAP No. 200010/2026 (Department) can be condoned under Section 5 of the Limitation Act, 1963, as applied to Section 37 of the Arbitration and Conciliation Act, 1996 read with Section 13(1-A) of the Commercial Courts Act, 2015.

¶ 8 · p. 10 · ¶ 11 · p. 17

ii.2. Whether the delay of 422 days in preferring COMAP No. 200024/2026 (Contractor) can be condoned on the ground of the pendency of a review petition, ill health, and counsel's delay.

¶ 4 · p. 7 · ¶ 8 · p. 10 · ¶ 12 · p. 18

iii.3. Whether the pendency of a review petition constitutes "sufficient cause" for condoning delay in filing a statutory appeal, in the absence of any stay or interim order.

¶ 8 · p. 10 · ¶ 12 · p. 18

03Law Applied

Section 13(1-A) of the Commercial Courts Act, 2015 and Section 37 of the Arbitration and Conciliation Act, 1996, read with Articles 116 and 117 of the Limitation Act, govern the appeals.

¶ 11 · p. 17

Condonation of delay is discretionary and requires sufficient cause supported by a satisfactory explanation, with the length of delay being immaterial in itself.

¶ 9 · p. 10, quoting Sheo Raj Singh (D) Tr. LRs v. Union of India, (2023) 10 SCC 531 · ¶ 30–32 · pp. 11–12

An "explanation" must be distinguished from an "excuse".

¶ 9 · pp. 11–12, quoting Sheo Raj Singh · ¶ 31–32

Prejudice to the opposite party is a relevant factor in the sufficiency assessment.

¶ 9 · p. 12, quoting Sheo Raj Singh · ¶ 39 (University of Delhi v. Prateek Sharma, larger bench)

Institutional delay of the State may be considered, but individual defaults should not be nit-picked.

¶ 9 · pp. 12–13, quoting State of Manipur v. Koting Lamkang · ¶ 7–8

Delay beyond 90, 30, or 60 days (as applicable) is condoned only by way of exception, not by rule. "Sufficient cause" under Section 5 is not elastic enough to cover long delays, and negligence, inaction, or lack of bona fides bars condonation. Government bodies are not given a different yardstick.

¶ 10 · pp. 13–17, applying Jharkhand Urja Utpadan Nigam Ltd. v. BHEL, 2025 INSC 533 · ¶ 20–21

Provisions in the judgment · 5 · Linked ones open on LawLens

Commercial Courts Act, 2015 Section 13

Arbitration and Conciliation Act, 1996 Section 37

Limitation Act, 1963 Section 5Section 116Section 117

04Reasoning

Both appeals were admittedly time-barred and the only ground was the pendency of the review petition. Applying the principles of Sheo Raj Singh and Jharkhand Urja, the delay could not be condoned as a matter of course, since the Arbitration Act is designed for speedy disposal.

¶ 8 · p. 10 · ¶ 9 · p. 10

Apart from the pendency of the review petition, neither appellant showed any sufficient cause. The review petition had no interim order, which meant it did not suspend the limitation period for the statutory appeal. The review was filed by the Contractor, not the Department, so it could not justify the Department's delay.

¶ 12 · p. 18

The Department's reasons of administrative exigencies, official transfers, and communication gaps were treated as excuses rather than explanations, and did not account for the 240-day delay.

¶ 3, 6, 11 · p. 6, 10, 17

The Contractor's reasons of ill health and counsel's inaction were treated as negligence, which cannot satisfy the sufficient cause test.

¶ 4 · p. 8 · ¶ 11 · p. 17

Following Jharkhand Urja, merely because the Government is a party, a different standard for condonation cannot apply. Because the statutory timeline under Section 13(1-A) of the Commercial Courts Act is designed to ensure speedy resolution, there is no basis to relax the period.

¶ 10 · p. 16 · ¶ 11 · p. 17

05Holding

Neither the Department nor the Contractor established sufficient cause for condoning the delays of 240 days and 422 days, respectively. The pendency of a review petition, without any interim order, and filed by the other party, does not justify delay in filing a statutory appeal.

¶ 12–13 · p. 18

The applications for condonation of delay in I.A. No. 3/2026 (COMAP No. 200010/2026) and I.A. No. 1/2026 (COMAP No. 200024/2026) are rejected. Consequently, both commercial appeals are dismissed.

¶ 13 · p. 18 · ¶ 14(i)–(ii) · p. 18

The judgment of the Principal District Judge, Kalaburagi, dated 02.05.2025 in Commercial Arbitration Suit No. 5/2019 therefore stands.

¶ 1 · p. 4 · ¶ 14 · p. 18
Karnataka High Court

Original Court PDF

M.B. PATIL CONSTRUCTIONS LIMITEDvsTHE EXECUTIVE ENGINEER

Karnataka High Court · October 27, 2026