Madras High CourtCivil Procedure and EvidenceProperty and Real Estate Law

Plausible reasons establish sufficient cause; RERA appeal delay condoned so limitation does not defeat merits adjudication.

ARMY WELFARE HOUSING ORGANISATION (AWHO)v.J.Jayaprakash

Plausible reasons establish sufficient cause; RERA appeal delay condoned so limitation does not defeat merits adjudication.. ARMY WELFARE HOUSING ORGANISATION (AWHO) vs J.Jayaprakash. Madras High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the Tribunal erred in dismissing the application to condone the 326-day delay without appreciating the genuine reasons assigned by the appellant.

The court held

The Court answered the substantial question of law in favour of the appellant: the Tribunal erred in dismissing the condonation application.

It also directed

The Court set aside the Tribunal's order dated 13.09.2024 in M.A. No. 59 of 2024 and condoned the 326-day delay, subject to the appellant paying Rs. 10,000/- as costs to the respondent within two weeks. Upon proof of payment, the Tribunal is directed to number and restore the appeal, hear both parties, and pass a reasoned order on merits as expeditiously as possible. The deposited amount remains subject to the Tribunal's final decision. The CMSA is allowed with costs and the connected CMP is closed.

01Facts

The appellant, AWHO, a "No Profit, No Loss" welfare housing organisation, implemented the "Chinnavedampatti Raman Vihar" project at Coimbatore.

¶ 10

The respondent was allotted a flat for Rs. 19,58,218/-, and paid Rs. 12,97,208/- by December 2014, relying on a promise of handover by December 2014.

¶ 10

The flat was handed over only on 22.10.2018.

¶ 11

The respondent approached the Adjudicating Authority, which on 15.03.2023 awarded interest at 9.30% p.a. on amounts paid, Rs. 50,000/- for mental agony, and Rs. 25,000/- for litigation expenses.

¶ 11

The appellant participated in those proceedings but filed its appeal before the Tamil Nadu Real Estate Appellate Tribunal (Appeal (SR) No. 171 of 2024) 326 days late, with M.A. No. 59 of 2024 and a supporting affidavit.

¶ 12

The affidavit attributed the delay to pending SLP proceedings before the Supreme Court and other forums concerning the same project, and to misplacement of the case papers during the temporary shifting of its office; the papers were reconstructed with difficulty.

¶ 15–17

By order dated 13.09.2024, the Tribunal rejected the reasons as not plausible and dismissed the condonation application.

¶ 13

During the appeal, the Court granted interim orders, and the appellant deposited Rs. 9,24,606/- before the Tribunal.

¶ 2

The respondent contended that the appellant had knowledge of the order and offered no plausible explanation.

¶ 8

02Issues

i.1. Whether the Tribunal erred in dismissing the application to condone the 326-day delay without appreciating the genuine reasons assigned by the appellant.

¶ 3

ii.2. Whether the appellant assigned plausible and valid reasons, showing sufficient cause, for condoning the delay in preferring the appeal.

¶ 14

03Law Applied

The appeal was filed under Section 58 of the Real Estate (Regulation and Development) Act, 2016.

p. 1

The Court applied the principle that "sufficient cause" for condonation of delay should be liberally construed in favour of deciding cases on merits, with "substantial justice" being paramount, as articulated in A.B. Govardhan v. P. Ragothaman (quoting Collector (LA) v. Katiji and Esha Bhattacharjee v. Raghunathpur Nafar Academy).

¶ 18

It relied on N.L. Abhyankar v. Union of India for the test that the question is whether delay reflects negligence sufficient to infer abandonment of the claim, or whether third-party rights have intervened, rather than mere passage of time.

¶ 18

In Inder Singh v. State of Madhya Pradesh (2025 SCC OnLine SC 600), the Supreme Court held that where plausible reasons showing sufficient cause are assigned, courts should condone delay and permit adjudication on merits rather than dismiss on technical grounds.

¶ 18

Under Janardhan Dass v. Kirnesh Jung (SLP (C) No. 23859 of 2025), merely the duration of delay cannot defeat a substantive right, and courts should not adopt a pedantic approach to applications under Section 5 of the Limitation Act, 1963.

¶ 19

Provisions in the judgment · 2 · Linked ones open on LawLens

Real Estate (Regulation and Development) Act, 2016. Section 58

Limitation Act, 1963 Section 5

04Reasoning

The Court found that the appellant's explanation, namely pending SLP and related proceedings on the same project and misplacement of papers during office relocation, was a bona fide reason rather than wilful default.

¶ 15–17

The Tribunal's rejection of these reasons was given without a reasoned assessment of the affidavit.

¶ 13

Applying Inder Singh and Janardhan Dass, the Court held that a substantive dispute over the alleged four-year handover delay and the compensation award merited adjudication on merits, since the appellant should have the opportunity to establish whether any delay actually occurred.

¶ 20–21

The Court noted that the appellant had already deposited the awarded amount, which mitigated any prejudice to the respondent.

¶ 18

It held the appellant's explanation sufficient to warrant condonation, enabling the appellant to contest the appeal on merits.

¶ 22

05Holding

The Court answered the substantial question of law in favour of the appellant: the Tribunal erred in dismissing the condonation application.

¶ 23

The Court set aside the Tribunal's order dated 13.09.2024 in M.A. No. 59 of 2024 and condoned the 326-day delay, subject to the appellant paying Rs. 10,000/- as costs to the respondent within two weeks. Upon proof of payment, the Tribunal is directed to number and restore the appeal, hear both parties, and pass a reasoned order on merits as expeditiously as possible. The deposited amount remains subject to the Tribunal's final decision. The CMSA is allowed with costs and the connected CMP is closed.

¶ 24–25
Madras High Court

Original Court PDF

ARMY WELFARE HOUSING ORGANISATION (AWHO)vsJ.Jayaprakash

Madras High Court · November 18, 2026