01Facts
The petitioner was admitted as a partner in the respondent firm (Ghori Developers) by a Deed of Reconstitution dated 16 January 2019, holding 80% share, to fund a stalled redevelopment of Fatehpur House, Kanheri, Borivali.
¶ 5The petitioner claims to have invested Rs. 1.68 crore.
¶ 2On 23 July 2022 two documents were signed: a Cancellation/Surrender of the 31 December 2018 MoU, which records an agreed total payment of Rs. 2 crore (Rs. 50 lakh by RTGS; three post-dated cheques of Rs. 50 lakh each) and conditions cancellation on clearance of those cheques.
¶ 10–13On 23 July 2022 a Deed of Retirement was also signed, under which the petitioner retired "with effect from the date of execution," without any condition tied to payment.
¶ 14–16The respondent states that the Rs. 50 lakh was paid, the cheques were issued, the firm was reconstituted on 27 July 2022 with Rathi Lifespaces Realtors Pvt. Ltd. as a new partner, and over Rs. 3.96 crore has been invested with 16 tenants and third-party purchasers involved.
¶ 3, 27The petitioner alleges non-payment of the balance but has produced no bank records.
¶ 17Neither side has proved whether the cheques were honoured.
¶ 18An ad-interim injunction under prayer clause A was granted ex parte on 15 October 2026.
¶ 35The respondent later appeared, contested the petition, and raised objections regarding limitation, the arbitration notice of 20 June 2025, the firm's name, the death/retirement of named partners, and the joinder of Rathi Lifespaces.
¶ 20–2502Issues
i.1. Whether the petitioner has shown a prima facie right in the partnership property, including whether she continued as a partner after the Retirement Deed dated 23 July 2022.
¶ 4, 9, 16, 29ii.2. Whether there is a real possibility that the respondent will take steps that defeat or affect her right, such that interim protection is needed to safeguard the arbitral proceedings.
¶ 4, 28, 30iii.3. Whether an arbitration agreement exists between the parties despite the wrong clause references and the respondent's objections.
¶ 21–22iv.4. Whether the balance of convenience and the need to protect the redevelopment project and third parties justify continuing the injunction and the status quo order.
¶ 34, 38v.5. Whether appointment of a Court Receiver is necessary.
¶ 3303Law Applied
Section 9 of the Arbitration and Conciliation Act, 1996 governs interim protection in aid of arbitration.
¶ 1Section 9 is intended to protect the subject matter of arbitration so that a future award is not rendered ineffective, and it is not meant to halt an ongoing business merely because a money dispute exists.
¶ 30Interim relief requires a prima facie right, a real risk that the right will be defeated, and a favourable balance of convenience.
¶ 4, 34, 38A Court Receiver is appointed only where property requires protection from misuse, waste, or damage and ordinary protection is insufficient.
¶ 33An ad-interim order may be re-examined once the other side appears.
¶ 35Contract interpretation applies: clauses of the partnership deed are read together, with Clause 13 (restrictions on partners) read alongside Clause 9 (right to sell saleable area) and Clause 18.
¶ 5–8A cheque given is not the same as the amount received until it is presented and paid.
¶ 17Arbitration agreements in the earlier MoU (2018) and Deed of Reconstitution (Clause 17) may extend to later disputes connected with the same arrangement.
¶ 21The judgment cites no case law.
Provisions in the judgment · 1 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 9
04Reasoning
Clause 13 cannot be read to bar all ordinary sales in the redevelopment, since Clause 9 permits partners to sell their saleable areas without consent.
¶ 8The petitioner's reliance on Clause 13 fails because the Retirement Deed, which has no payment condition, ended her partnership from 23 July 2022.
¶ 16, 26, 29The Cancellation Deed ties the cancellation of the MoU to clearance of the cheques, so the petitioner retains a contractual claim for any unpaid balance, which is distinct from her partnership status.
¶ 13, 16, 29Neither party proved payment of the Rs. 1.50 crore: the respondent produced no evidence of honouring the cheques, and the petitioner produced no bank records. The court therefore left this factual question to the tribunal.
¶ 17–19The petitioner showed no specific transaction, third party, or document that threatened to defeat an award.
¶ 28, 31The prayer was overbroad: it would freeze the entire project, affect 16 tenants and purchasers who are not parties, and go beyond protecting a money claim.
¶ 30, 37–38Given the absence of a specific threat, the balance of convenience did not favour continuing the injunction.
¶ 34, 38The Court Receiver was refused because there was no evidence of waste or diversion, and appointment would interfere with an advanced project.
¶ 33An arbitration agreement exists in the 2018 MoU and the 2019 Deed of Reconstitution, and wrong clause numbers do not defeat it.
¶ 21–22Limitation, the adequacy of service of the notice, and the firm's name were not decided and were left to the tribunal.
¶ 20, 23–24The ex parte order was granted without the complete facts, including the firm's present constitution.
¶ 3605Holding
The petitioner did not establish a continuing partnership right after 23 July 2022 or a real risk of dissipation that justified interim protection.
¶ 39The Arbitration Petition is dismissed insofar as it seeks interim reliefs under prayer clauses A, B, D, E, and F. The ad-interim injunction of 15 October 2026 stands vacated, the respondent's application for vacation is allowed to that extent, and the prayer for a Court Receiver is rejected.
¶ 41(i)–(iv)The claim for the unpaid Rs. 1.50 crore under the Cancellation/Surrender Deed, along with the limitation and service issues, is left open for the arbitral tribunal, and the findings are confined to the interim application.
¶ 40, 41(v)–(vi)No order as to costs.
¶ 41(vii)Original Court PDF
Mrs Snehlata Anurag Singh Through Poa Holder Mr Niraj Shivkumar VermavsM S Ghori Enterprises Running Its Business Through Its Partners Mr Abdul Hafeez Aziz Ghori
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
