Bombay High CourtArbitration and MediationCommercial and Corporate Law

Unpaid retirement consideration does not justify a blanket Section 9 injunction halting an ongoing redevelopment project.

Mrs Snehlata Anurag Singh Through Poa Holder Mr Niraj Shivkumar Vermav.M S Ghori Enterprises Running Its Business Through Its Partners Mr Abdul Hafeez Aziz Ghori

Unpaid retirement consideration does not justify a blanket Section 9 injunction halting an ongoing redevelopment project.. Mrs Snehlata Anurag Singh Through Poa Holder Mr Niraj Shivkumar Verma vs M S Ghori Enterprises Running Its Business Through Its Partners Mr Abdul Hafeez Aziz Ghori. Bombay High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the petitioner has shown a prima facie right in the partnership property, including whether she continued as a partner after the Retirement Deed dated 23 July 2022.

The court held

The petitioner did not establish a continuing partnership right after 23 July 2022 or a real risk of dissipation that justified interim protection.

It also directed

The Arbitration Petition is dismissed insofar as it seeks interim reliefs under prayer clauses A, B, D, E, and F. The ad-interim injunction of 15 October 2026 stands vacated, the respondent's application for vacation is allowed to that extent, and the prayer for a Court Receiver is rejected.

The claim for the unpaid Rs. 1.50 crore under the Cancellation/Surrender Deed, along with the limitation and service issues, is left open for the arbitral tribunal, and the findings are confined to the interim application.

No order as to costs.

01Facts

The petitioner was admitted as a partner in the respondent firm (Ghori Developers) by a Deed of Reconstitution dated 16 January 2019, holding 80% share, to fund a stalled redevelopment of Fatehpur House, Kanheri, Borivali.

¶ 5

The petitioner claims to have invested Rs. 1.68 crore.

¶ 2

On 23 July 2022 two documents were signed: a Cancellation/Surrender of the 31 December 2018 MoU, which records an agreed total payment of Rs. 2 crore (Rs. 50 lakh by RTGS; three post-dated cheques of Rs. 50 lakh each) and conditions cancellation on clearance of those cheques.

¶ 10–13

On 23 July 2022 a Deed of Retirement was also signed, under which the petitioner retired "with effect from the date of execution," without any condition tied to payment.

¶ 14–16

The respondent states that the Rs. 50 lakh was paid, the cheques were issued, the firm was reconstituted on 27 July 2022 with Rathi Lifespaces Realtors Pvt. Ltd. as a new partner, and over Rs. 3.96 crore has been invested with 16 tenants and third-party purchasers involved.

¶ 3, 27

The petitioner alleges non-payment of the balance but has produced no bank records.

¶ 17

Neither side has proved whether the cheques were honoured.

¶ 18

An ad-interim injunction under prayer clause A was granted ex parte on 15 October 2026.

¶ 35

The respondent later appeared, contested the petition, and raised objections regarding limitation, the arbitration notice of 20 June 2025, the firm's name, the death/retirement of named partners, and the joinder of Rathi Lifespaces.

¶ 20–25

02Issues

i.1. Whether the petitioner has shown a prima facie right in the partnership property, including whether she continued as a partner after the Retirement Deed dated 23 July 2022.

¶ 4, 9, 16, 29

ii.2. Whether there is a real possibility that the respondent will take steps that defeat or affect her right, such that interim protection is needed to safeguard the arbitral proceedings.

¶ 4, 28, 30

iii.3. Whether an arbitration agreement exists between the parties despite the wrong clause references and the respondent's objections.

¶ 21–22

iv.4. Whether the balance of convenience and the need to protect the redevelopment project and third parties justify continuing the injunction and the status quo order.

¶ 34, 38

v.5. Whether appointment of a Court Receiver is necessary.

¶ 33

03Law Applied

Section 9 of the Arbitration and Conciliation Act, 1996 governs interim protection in aid of arbitration.

¶ 1

Section 9 is intended to protect the subject matter of arbitration so that a future award is not rendered ineffective, and it is not meant to halt an ongoing business merely because a money dispute exists.

¶ 30

Interim relief requires a prima facie right, a real risk that the right will be defeated, and a favourable balance of convenience.

¶ 4, 34, 38

A Court Receiver is appointed only where property requires protection from misuse, waste, or damage and ordinary protection is insufficient.

¶ 33

An ad-interim order may be re-examined once the other side appears.

¶ 35

Contract interpretation applies: clauses of the partnership deed are read together, with Clause 13 (restrictions on partners) read alongside Clause 9 (right to sell saleable area) and Clause 18.

¶ 5–8

A cheque given is not the same as the amount received until it is presented and paid.

¶ 17

Arbitration agreements in the earlier MoU (2018) and Deed of Reconstitution (Clause 17) may extend to later disputes connected with the same arrangement.

¶ 21

The judgment cites no case law.

Provisions in the judgment · 1 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 9

04Reasoning

Clause 13 cannot be read to bar all ordinary sales in the redevelopment, since Clause 9 permits partners to sell their saleable areas without consent.

¶ 8

The petitioner's reliance on Clause 13 fails because the Retirement Deed, which has no payment condition, ended her partnership from 23 July 2022.

¶ 16, 26, 29

The Cancellation Deed ties the cancellation of the MoU to clearance of the cheques, so the petitioner retains a contractual claim for any unpaid balance, which is distinct from her partnership status.

¶ 13, 16, 29

Neither party proved payment of the Rs. 1.50 crore: the respondent produced no evidence of honouring the cheques, and the petitioner produced no bank records. The court therefore left this factual question to the tribunal.

¶ 17–19

The petitioner showed no specific transaction, third party, or document that threatened to defeat an award.

¶ 28, 31

The prayer was overbroad: it would freeze the entire project, affect 16 tenants and purchasers who are not parties, and go beyond protecting a money claim.

¶ 30, 37–38

Given the absence of a specific threat, the balance of convenience did not favour continuing the injunction.

¶ 34, 38

The Court Receiver was refused because there was no evidence of waste or diversion, and appointment would interfere with an advanced project.

¶ 33

An arbitration agreement exists in the 2018 MoU and the 2019 Deed of Reconstitution, and wrong clause numbers do not defeat it.

¶ 21–22

Limitation, the adequacy of service of the notice, and the firm's name were not decided and were left to the tribunal.

¶ 20, 23–24

The ex parte order was granted without the complete facts, including the firm's present constitution.

¶ 36

05Holding

The petitioner did not establish a continuing partnership right after 23 July 2022 or a real risk of dissipation that justified interim protection.

¶ 39

The Arbitration Petition is dismissed insofar as it seeks interim reliefs under prayer clauses A, B, D, E, and F. The ad-interim injunction of 15 October 2026 stands vacated, the respondent's application for vacation is allowed to that extent, and the prayer for a Court Receiver is rejected.

¶ 41(i)–(iv)

The claim for the unpaid Rs. 1.50 crore under the Cancellation/Surrender Deed, along with the limitation and service issues, is left open for the arbitral tribunal, and the findings are confined to the interim application.

¶ 40, 41(v)–(vi)

No order as to costs.

¶ 41(vii)
Bombay High Court

Original Court PDF

Mrs Snehlata Anurag Singh Through Poa Holder Mr Niraj Shivkumar VermavsM S Ghori Enterprises Running Its Business Through Its Partners Mr Abdul Hafeez Aziz Ghori

Bombay High Court · November 26, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment