01Facts
The petitioner owned two parcels of land at Kotur Village, Dharwad, notified for acquisition for an industrial area under Sections 28(1), 28(4) and 28(6) of the Karnataka Industrial Areas Development Act, 1966.
pp. 2–4Although possession had been taken, no award had been passed and no compensation paid.
pp. 2–4The petitioner made representations seeking either exclusion of her land from acquisition or payment of compensation, including a general award.
pp. 2–4KIADB stated that it had sought valuation of trees and that it would make an award after receiving the valuation; it also referred to a consent-compensation offer under Section 29(2).
pp. 2–4The petitioner sought a direction to consider her representations
pp. 2–402Issues
i.Whether the respondents’ failure to pass an award and pay compensation after acquisition and taking possession warranted a direction to make a general award within a fixed period
pp. 4–8ii.Whether, in making the award, the market value should be fixed as of the date of the award, having regard to the delay in determining compensation
pp. 5–803Law Applied
Sections 28(1), 28(4) and 28(6) of the Karnataka Industrial Areas Development Act, 1966 govern the relevant acquisition process; the respondents are obliged to determine and pay compensation through an award within a reasonable time.
pp. 2–5Section 29(2) provides for compensation by agreement, which the petitioner was not bound to accept in place of seeking a general award.
p. 4Relying on Bernard Francis Joseph Vaz v. Government of Karnataka, (2025) 7 SCC 580, the Court applied the principle that, where delay in determining compensation is attributable to the acquiring authorities, compensation may be determined by reference to the market value prevailing on the date of the award, to avoid injustice to landowners and protect the right to property under Article 300-A.
pp. 5–7Provisions in the judgment · 2 · Linked ones open on LawLens
KARNATAKA INDUSTRIAL AREAS DEVELOPMENT ACT, 1966 Section 28Section 29
04Reasoning
The Court found that the acquisition notification had issued in February 2024 and that, despite the petitioner’s representations, no award had been passed.
pp. 4–8KIADB’s pending requests for valuation of trees did not discharge its legal duty to make an award.
pp. 4–8Nor did the Section 29(2) offer resolve the matter, because the petitioner sought a general award rather than agreeing to the proposed consent compensation.
pp. 4–8Applying Bernard Francis Joseph Vaz, the Court concluded that the authorities’ prolonged inaction could not justify postponing compensation on an outdated valuation basis; the general award should reflect market value as of the date the award is passed.
pp. 4–805Holding
The petition was allowed in part.
p. 8The respondents were directed to pass a general award for the acquired lands and pay compensation based on market value as of the date of the award, together with all statutory benefits, within three months.
p. 8They were also directed to file a compliance report immediately after that period.