01Facts
Land belonging to respondents 1–3 was acquired for a KPTCL electricity receiving station and residential quarters.
p. 2The petitioner deposited ₹7,35,750 with the Assistant Commissioner on 30 January 1997, before the preliminary notification dated 8 July 1997, and deposited a further ₹7,44,348 after the award dated 12 November 1999.
pp. 2–3On reference, compensation was enhanced to ₹3,00,000 per acre.
p. 3In execution, the parties disputed the amount payable, and the Executing Court’s Registry prepared a calculation dated 5 August 2017.
pp. 3–5The petitioner challenged that calculation, contending that the pre-notification deposit should first have been deducted before calculating interest.
pp. 3–502Issues
i.1. Whether the Executing Court’s calculation was incorrect because it failed to deduct the ₹7,35,750 deposited before the preliminary notification before calculating interest
pp. 5–6ii.2. Whether the Registry should recalculate the amount payable in accordance with the Reference Court’s order after making that deduction
pp. 6–703Law Applied
The Court applied the principle that, where an amount has already been deposited toward compensation, interest is payable only on the amount exceeding that deposit.
p. 6Accordingly, the ₹7,35,750 deposited before the preliminary notification had to be deducted from the aggregate of ₹26,99,247—comprising market value, 12% additional market value, and 30% solatium—before calculating interest from the date of the preliminary notification to the date of the award; interest thereafter was to be calculated in accordance with the Reference Court’s order.
p. 6The judgment identifies the acquisition as proceeding under the Land Acquisition Act, 1894, but cites no additional statutory provision or precedent as the basis for this calculation.
pp. 2–3, 6Provisions in the judgment · 1
Land Acquisition Act, 1894 Section 18
04Reasoning
The respondents accepted that ₹7,35,750 had been deposited before the preliminary notification.
p. 5Because that sum had already been paid toward compensation, the Court held that interest could not be calculated on it.
pp. 5–6The Registry’s calculation was therefore incorrect to the extent it failed to deduct the deposit from the aggregate compensation before calculating interest for the period from the preliminary notification to the award.
pp. 5–605Holding
The petition was allowed.
p. 7The Registry of the Executing Court was directed to deduct ₹7,35,750 from ₹26,99,247, calculate interest on the balance from the date of the preliminary notification to the date of the award, and then proceed in accordance with the interest rates awarded by the Reference Court.
p. 7Any amount deposited by the petitioner before the High Court was ordered transferred to the Executing Court for appropriate orders.
p. 7Original Court PDF