BEST Not Liable for Clean Energy Cess Hike Under Power Supply Deal Lacking Change-in-Law Payment Clause

Municipal Corporation of Greater Mumbaiv.Central Electricity Regulatory Commission {i.e. CERC} & Ors

BEST Not Liable for Clean Energy Cess Hike Under Power Supply Deal Lacking Change-in-Law Payment Clause. Municipal Corporation of Greater Mumbai vs Central Electricity Regulatory Commission {i.e. CERC} & Ors. APTEL. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the increase in Clean Energy Cess constitutes a "Change in Law" event under Clause 17(E) of the LoI, and whether the LoI, read as a whole, provides for economic restitution for such an event.

The court held

The Clean Energy Cess increase is a change-in-law event under Clause 17(E), but Clause 17 is confined to FM relief from delay or non-performance and provides no economic restitution.

It also directed

The MoP direction dated 27.08.2018 cannot create a recovery right over the LoI rates.

The cost increase is not an FM hindrance, and Section 70 of the Contract Act does not apply.

The privity issue was not decided.

The Appeal is allowed and CERC's Order dated 05.11.2018 is set aside insofar as it grants compensation for the Clean Energy Cess increase. TPTCL shall refund the deposited amounts with simple interest at SBI's one-year MCLR, as applicable from time to time, from the respective dates of deposit until actual refund.

01Facts

BEST, a statutory distribution licensee in Mumbai, invited bids in December 2015 for short-term round-the-clock power for 01.02.2016 to 31.12.2016.

¶ 3, 4

BEST issued a Letter of Intent (LoI) dated 14.01.2016 to TPTCL, a trader, for monthly firm supply at fixed rates, with the source identified as JITPL's Angul station and the delivery point in Maharashtra.

¶ 5

Clause 17 of the LoI, the force majeure (FM) clause, listed "Change in law" as item E among non-exhaustive FM events. The LoI contained no separate change-in-law compensation provision.

¶ 42, 43

By Notification dated 29.02.2016, the Clean Energy Cess rose from ₹200 to ₹400 per tonne with effect from 01.03.2016.

¶ 7, 39

TPTCL and JITPL sought a tariff increase of ₹0.151/kWh, which BEST declined on the ground that the LoI provided no compensatory tariff for tax or cess revisions and that the bid price was fixed.

¶ 8, 39, 40

TPTCL issued debit notes for ₹1,34,97,683 and ₹46,90,253.

¶ 10, 11

CERC, in Petition No. 159/MP/2017, held by order dated 05.11.2018 that TPTCL and JITPL could recover the differential cess from BEST.

¶ 12

BEST appealed and, pending appeal, deposited ₹1,81,00,000, ₹18,02,018 and ₹1,80,80,019 with TPTCL.

¶ 21, 62

Parties continued performance under the original LoI during the dispute.

¶ 40

02Issues

i.1. Whether the increase in Clean Energy Cess constitutes a "Change in Law" event under Clause 17(E) of the LoI, and whether the LoI, read as a whole, provides for economic restitution for such an event.

¶ 41, 43, 45, 47, 48

ii.2. Whether the MoP direction dated 27.08.2018 under Section 107 of the Electricity Act, 2003 entitles TPTCL/JITPL to pass the increased cess through to BEST.

¶ 49–54

iii.3. Whether the increased cost of performance amounts to a hindrance or FM event entitling the supplier to compensation, and whether the decision in GMR Warora assists TPTCL.

¶ 55–57

iv.4. Whether Section 70 of the Indian Contract Act, 1872 permits compensation for the increased cost of performing a subsisting contract.

¶ 58–60

v.5. Whether BEST had privity of contract with JITPL, and whether BEST is entitled to a refund with interest.

¶ 61, 62

03Law Applied

The Tribunal applied Clause 17 of the LoI, which treats change in law as an FM event that relieves a party from breach where performance is prevented, hindered or delayed.

¶ 42, 43, 48

The contract governs compensation, so absent a contractual provision, no restitution arises.

¶ 33, 52

Section 107(1) of the Electricity Act, 2003 provides that the Central Commission is only "guided by" Central Government directions.

¶ 53

Kerala State Electricity Board v. Jhabua Power (2024 INSC 768) and Gujarat Urja Vikas Nigam v. Solar Semiconductor ((2017) 16 SCC 498) hold that policy directions cannot displace or vary agreed contractual terms.

¶ 53, 54

Energy Watchdog v. CERC ((2017) 14 SCC 80) and Alopi Parshad (1960 SCC OnLine SC 13) establish that increased cost or onerousness does not constitute FM or frustrate a contract.

¶ 57

Section 70 of the Indian Contract Act, 1872 operates as a restitutionary remedy, as explained in Food Corporation of India v. Vikas Majdoor ((2007) 13 SCC 544), State of West Bengal v. B.K. Mondal (AIR 1962 SC 779) and V.R. Subramanyam v. B. Thayappa (AIR 1966 SC 1034), and it cannot enhance agreed consideration.

¶ 59

The contra proferentem rule applies only where ambiguity exists.

¶ 48

GMR Warora (Appeal Nos. 111 and 290 of 2017) is distinguished on the basis that compensation there rested on express economic-restitution provisions in the PPAs.

¶ 55

The principle of restitution determines refund and interest.

¶ 62

Provisions in the judgment · 7 · Linked ones open on LawLens

Electricity Act, 2003 Section 3Section 63Section 76Section 107Section 108

Indian Contract Act, 1872 Section 70

Interest Act, 1978 Section 10

04Reasoning

The Tribunal accepted CERC's finding that the cess increase is a change-in-law event, since the standard PPA definition supports that classification.

¶ 45

The LoI refers to change in law only within the FM clause, which addresses delay and non-performance, and does not provide for tariff adjustment. CERC erred in moving from FM relief to economic compensation without a contractual basis.

¶ 43, 45, 46

Clause 17 confers protection against breach, not adjustment of the agreed consideration, and the absence of an express bar on reimbursement does not create an entitlement. Because the LoI contained no ambiguity on this point, contra proferentem did not apply.

¶ 47, 48

The MoP direction was rejected as a source of entitlement: it is directed at expediting pass-through, is expressly subject to "unless provided otherwise in the PPA", and cannot create a right absent a contractual mechanism.

¶ 51, 52, 53, 54

GMR Warora was distinguished because its PPAs expressly provided restitution.

¶ 55

Supplying power at higher cost did not hinder performance, since the supply continued, and increased cost does not constitute FM.

¶ 56, 57

Section 70 did not apply because the supply was made under the existing contract, for which consideration was stipulated; no extra work or benefit outside the contract was involved.

¶ 59, 60

Since no basis for recovery existed, the Tribunal found it unnecessary to decide privity.

¶ 61

05Holding

The Clean Energy Cess increase is a change-in-law event under Clause 17(E), but Clause 17 is confined to FM relief from delay or non-performance and provides no economic restitution.

¶ 43, 48

The MoP direction dated 27.08.2018 cannot create a recovery right over the LoI rates.

¶ 53, 54

The cost increase is not an FM hindrance, and Section 70 of the Contract Act does not apply.

¶ 56–60

The privity issue was not decided.

¶ 61

The Appeal is allowed and CERC's Order dated 05.11.2018 is set aside insofar as it grants compensation for the Clean Energy Cess increase. TPTCL shall refund the deposited amounts with simple interest at SBI's one-year MCLR, as applicable from time to time, from the respective dates of deposit until actual refund.

¶ 61, 62 · Order · pp. 24–25
APTEL

Original Court PDF

Municipal Corporation of Greater MumbaivsCentral Electricity Regulatory Commission {i.e. CERC} & Ors

APTEL · November 28, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment