Gauhati High CourtCivil Procedure and EvidenceProperty and Real Estate Law

Gauhati HC Upholds Refusal To Let Tenant Add Possession Claim After Alleged 2019 Lockout, Citing Section 6’s Six-Month Limit

Mrs Juliana Saikia Dekav.Rishiraj Saikia And Anr

Gauhati HC Upholds Refusal To Let Tenant Add Possession Claim After Alleged 2019 Lockout, Citing Section 6’s Six-Month Limit. Mrs Juliana Saikia Deka vs Rishiraj Saikia And Anr. Gauhati High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the Trial Court erred in rejecting the amendment seeking restoration of possession on the grounds of limitation, delay, and change in the nature of the suit

The court held

The High Court dismissed the revision petition, declining to interfere with the order rejecting the plaint amendment.

It also directed

The parties were left to bear their own costs; the stay on further proceedings in Title Suit No. 14/2019 was vacated, and the Trial Court was directed to proceed with and conclude the suit expeditiously.

01Facts

The petitioner, claiming to be a tenant of the respondent, had filed Title Suit No. 14/2019 seeking an injunction against eviction, locking of the premises, and disconnection of electricity.

pp. 2–3 · ¶ 2–4

She later alleged that the suit premises had been locked on 12 February 2019 and sought, by an application filed on 23 July 2024 under Order VI Rule 17 CPC, to amend the plaint to add a relief for restoration of possession.

pp. 2–3 · ¶ 2–4

The Trial Court rejected the amendment application, finding it belated and the proposed relief time-barred.

pp. 2–3 · ¶ 2–4

The petitioner challenged that order under Article 227 of the Constitution.

pp. 7–8 · ¶ 15–16

02Issues

i.1. Whether the Trial Court erred in rejecting the amendment seeking restoration of possession on the grounds of limitation, delay, and change in the nature of the suit

pp. 3–6 · ¶ 5–12

ii.2. Whether the Trial Court’s order warranted interference under the High Court’s supervisory jurisdiction under Article 227

p. 8 · ¶ 16–17

03Law Applied

Order VI Rule 17 CPC governs amendment of pleadings; the Court considered the Trial Court’s finding that the petitioner had not shown due diligence and that the amendment was sought after substantial delay.

p. 8 · ¶ 16

The Court held that where a tenant alleges dispossession otherwise than in due course of law, the remedy is under Section 6 of the Specific Relief Act, 1963, which requires proceedings to be brought within six months of dispossession; Article 64 of the Limitation Act, 1963 did not govern the petitioner’s proposed claim in these circumstances.

p. 7 · ¶ 14

Article 227 jurisdiction is supervisory and is to be exercised sparingly; it is not a basis for interference merely because another view is possible.

pp. 8–9 · ¶ 16–17

The parties cited Nair Service Society Ltd. v. K.C. Alexander, Usha Devi v. Rijwan Ahamad, Usha Balasaheb Swami v. Kiran Appaso Swami, and Revajeetu Builders and Developers v. Narayanaswamy and Sons; the judgment does not set out a separate analysis of those authorities.

pp. 4–7 · ¶ 6–7, 12–13

Provisions in the judgment · 2 · Linked ones open on LawLens

Specific Relief Act, 1963 Section 6

Limitation Act, 1963 Section 64

04Reasoning

The petitioner’s own case was that she was dispossessed on 12 February 2019, whereas she sought amendment on 23 July 2024—more than five years later.

pp. 7–8 · ¶ 14–15

Because the proposed possession relief arose from alleged dispossession of a tenant, the Court applied Section 6 of the Specific Relief Act and found the six-month period had expired; Article 64 did not assist the petitioner.

pp. 7–8 · ¶ 14–15

The asserted period during which the suit was kept in abeyance did not alter the fact that the amendment application was filed more than ten months after proceedings resumed.

p. 8 · ¶ 15–17

The Court therefore found no basis to disturb the Trial Court’s decision, including its conclusion concerning delay and lack of due diligence, under Article 227.

p. 8 · ¶ 15–17

05Holding

The High Court dismissed the revision petition, declining to interfere with the order rejecting the plaint amendment.

p. 9 · ¶ 18

The parties were left to bear their own costs; the stay on further proceedings in Title Suit No. 14/2019 was vacated, and the Trial Court was directed to proceed with and conclude the suit expeditiously.

p. 9 · ¶ 19–21
Gauhati High Court

Original Court PDF

Mrs Juliana Saikia DekavsRishiraj Saikia And Anr

Gauhati High Court · November 10, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment