01Facts
SIPCOT allotted the appellant a two-acre plot in 2007 on a 99-year lease for a hotel project.
pp. 2–6, 14–15The allotment and lease required construction to be completed within 24 months and commercial production to commence within 30 months; they also placed responsibility for obtaining statutory approvals, including building-plan approval, on the allottee.
pp. 2–6, 14–15After the appellant failed to complete the project despite extensions and notices, SIPCOT cancelled the allotment in February 2020 and directed the appellant to execute a surrender deed.
pp. 7–10The appellant challenged the cancellation by writ petition, which was dismissed by a Single Judge; it then filed this writ appeal.
pp. 1–2, 12–1302Issues
i.1. Whether SIPCOT’s failure to obtain or provide layout approval justified the appellant’s failure to secure building-plan approval and comply with the project timelines.
pp. 13–17ii.2. Whether the cancellation was arbitrary or disproportionate, warranting interference under Article 226 of the Constitution.
pp. 13–14, 18–2003Law Applied
The Allotment Order and Lease Deed, read together, governed the parties’ rights and obligations.
pp. 3–6, 14–15Their relevant terms required timely construction and commencement of commercial production, placed responsibility for statutory approvals on the allottee, restricted use of the plot to the allotted purpose, and authorised cancellation and resumption for non-compliance.
pp. 3–6, 14–15The Lease Deed also provided for action under the Tamil Nadu Public Premises (Eviction of Unauthorised Occupants) Act, 1975.
pp. 4–6The Court applied the principle that a party cannot accept the benefits of a commercial bargain while disowning its burdens, and held that legitimate expectation cannot arise contrary to express contractual terms.
p. 16, 18It further stated that discretionary jurisdiction under Article 226 cannot be invoked to excuse a prolonged, clear breach of a commercial lease of public industrial land.
p. 1904Reasoning
The Court found that the plot was a stand-alone site and that neither the Allotment Order nor the Lease Deed required SIPCOT to procure layout or building-plan approval; the appellant had accepted the obligation to obtain approvals itself.
pp. 14–16The appellant applied to the DTCP only in 2012, did not furnish the particulars it requested, and did not challenge the return of the application or seek directions against either respondent.
pp. 8–11, 16–17Its earlier explanations for delay did not refer to the approval issue, which arose only after the contractual deadlines had passed.
pp. 7–9, 16–17Despite extensions and prolonged forbearance, the project remained incomplete and commercial operations never began; the appellant’s later request to change the land use did not confer a right to retain the plot.
pp. 17–1905Holding
The Court answered the issues against the appellant, holding that SIPCOT was not responsible for securing the approvals and that the cancellation did not warrant interference under Article 226.
pp. 14–19It found no illegality, infirmity, or perversity in the Single Judge’s order, dismissed the writ appeal, confirmed that order, made no order as to costs, and closed the connected miscellaneous petition.
p. 20Original Court PDF
Shyam Trading CorporationvsState industries Promotion Corporation of Tamil Na
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in