Patna High CourtContract LawAdministrative and Public Law

Pre-contract financial estimate cannot override executed agreement's terms; unexplained delay bars writ relief for contractual dues.

Aman Enterprisesv.The State of Bihar

Pre-contract financial estimate cannot override executed agreement's terms; unexplained delay bars writ relief for contractual dues.. Aman Enterprises vs The State of Bihar. Patna High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the petitioner can claim 10% contractor's margin/profit where the executed agreement contains no such stipulation, and the financial estimate and tender acceptance are relied upon as the basis of the claim.

The court held

The 10% contractor's margin/profit is not payable because the executed agreement contains no such stipulation, and the petitioner cannot rely on the financial estimate or tender acceptance to override it.

It also directed

The rejection order was not found to be arbitrary or interfered with on the grounds raised.

The unexplained delay and the monetary, contractual nature of the claim were held to disentitle the petitioner from discretionary relief under Article 226.

The writ petition was dismissed, and the challenge to Letter No. 3632 dated 04.12.2023 failed.

01Facts

The Samastipur Municipal Corporation (formerly referred to as the Nagar Parishad) floated an Expression of Interest-cum-Tender Notice dated 19.02.2018 for outsourcing sanitation work.

¶ 3

The petitioner's financial estimate dated 16.03.2018 included 10% of the total bill as contractor's margin/profit.

¶ 3

The Empowered Standing Committee accepted the proposal on 31.03.2018, and an agreement was executed on 11.05.2018.

¶ 3 · ¶ 22

The executed agreement contains no provision for the 10% margin/profit.

¶ 23

The agreement was rescinded with effect from 01.10.2019.

¶ 15

The petitioner's first writ petition, C.W.J.C. No. 9327 of 2023, was disposed of on 02.11.2023 with a direction to the Municipal Commissioner to examine the claim and pass a speaking order.

¶ 5 · ¶ 19

The Commissioner rejected the claim by Letter No. 3632 dated 04.12.2023.

¶ 5 · ¶ 15

The present writ petition was filed on 28.01.2026, after an interval the petitioner acknowledged.

¶ 8 · ¶ 15

The respondents contended that EPF dues were already paid, that the claim of Rs. 54,10,445/- with 18% interest was inflated, and that the petitioner produced no valid documentary evidence.

¶ 12 · ¶ 13

02Issues

i.1. Whether the petitioner can claim 10% contractor's margin/profit where the executed agreement contains no such stipulation, and the financial estimate and tender acceptance are relied upon as the basis of the claim.

¶ 4 · ¶ 6–7 · ¶ 22–25

ii.2. Whether the impugned rejection order (Letter No. 3632 dated 04.12.2023) is arbitrary, non-speaking, or vitiated by non-application of mind, warranting interference under Article 226.

¶ 6–7 · ¶ 20–21 · ¶ 24–25

iii.3. Whether the writ petition is liable to be refused on account of unexplained delay and laches, given the nature of the claim as a monetary contractual dispute.

¶ 8 · ¶ 16–18 · ¶ 26–27

03Law Applied

Although limitation does not strictly apply under Article 226, stale claims cannot be revived after an unreasonable lapse of time.

¶ 16

Delay as a bar to discretionary writ relief, as held in S.S. Balu v. State of Kerala, (2009) 2 SCC 479.

¶ 17

Writ petitions in contractual matters are not absolutely barred but are discretionary, and purely money claims arising from contract ordinarily fall outside writ jurisdiction save in exceptional cases, as held in Joshi Technologies International Inc. v. Union of India, (2015) 7 SCC 728.

¶ 18

Judicial review of contractual decisions is confined to legality, fairness, and rationality under Article 14, with interpretation of contractual terms generally left to ordinary civil law, per Banshidhar Construction Pvt. Ltd. v. Bharat Coking Coal Ltd., (2024) 10 SCC 273.

¶ 20

The tendering authority is the best judge of its documents, and courts intervene only for arbitrariness, irrationality, bias, mala fides, or perversity, as applied in Silppi Construction Contractors v. Union of India, (2020) 16 SCC 489.

¶ 21

The respondent's reliance on Section 94 of the Bharatiya Sakshya Adhiniyam, 2023, barring extrinsic evidence to vary a written contract, was recorded as an argument.

¶ 11

Provisions in the judgment · 1 · Linked ones open on LawLens

Bharatiya Sakshya Adhiniyam, 2023 Section 94

04Reasoning

On the agreement's terms, the executed contract contains no provision for the 10% margin/profit.

¶ 23

The Empowered Standing Committee's acceptance of the financial estimate was at most a circumstance leading to the contract and could not override the express terms of the executed agreement.

¶ 24

The petitioner neither sought clarification nor objected to the omission during execution or the contract's subsistence, and therefore could not introduce the component at a belated stage.

¶ 23 · ¶ 25

Because the foundation of the claim failed on the agreement's terms, the Commissioner's rejection was not arbitrary, and the Court did not undertake a merits review of the contractual claim.

¶ 20–21 · ¶ 24–25

The petitioner approached the Court in 2023 after termination in 2019, and again in January 2026 after the 2023 rejection, and the explanation for this delay was insufficient for a monetary contractual claim.

¶ 26

Taken together, the nature of the claim, the absence of any stipulation, and the unexplained delay led the Court to decline the discretionary relief sought.

¶ 27

The Court did not separately decide the respondents' Section 94 argument or the quantum and interest disputes.

¶ 11 · ¶ 13

05Holding

The 10% contractor's margin/profit is not payable because the executed agreement contains no such stipulation, and the petitioner cannot rely on the financial estimate or tender acceptance to override it.

¶ 23–25

The rejection order was not found to be arbitrary or interfered with on the grounds raised.

¶ 24–25

The unexplained delay and the monetary, contractual nature of the claim were held to disentitle the petitioner from discretionary relief under Article 226.

¶ 26–27

The writ petition was dismissed, and the challenge to Letter No. 3632 dated 04.12.2023 failed.

¶ 28
Patna High Court

Original Court PDF

Aman EnterprisesvsThe State of Bihar