01Facts
The Applicants (Avenue Hotels Pvt. Ltd. and Vinayak Hospitality Pvt. Ltd., jointly trading as "Hotel Avenue") have received PNG supply from the Respondent, Mahanagar Gas Ltd. (MGL), since July 2002.
¶ 4The original contract is an Offer Letter dated 21 January 2002, accepted by Applicant No.1 on 5 March 2002, which contains no arbitration clause.
¶ 5, 12, 14The Applicants say that detailed Terms and Conditions printed on MGL's bills from April 2021 onwards contain an arbitration clause.
¶ 13, 15MGL disconnected supply, alleging meter tampering, and raised a demand of Rs. 37,84,196.
¶ 4, 19The Applicants paid Rs. 17,00,000 and gave two post-dated cheques for the balance.
¶ 4MGL contends that a settlement was reached at a meeting on 24 April 2026, recorded in Minutes circulated by email the same day, and that supply was restored on 29 April 2026.
¶ 30–31, 40The Applicants' letters dated 25 and 28 April 2026 state that payments were made under protest, without prejudice, and under economic compulsion.
¶ 34–38The Applicants issued an Invocation Notice dated 20 May 2026 citing Clause 16.1 (appointment by the seller), while the Application relies on Clause 13 (appointment by mutual agreement, failing which under the Act).
¶ 20–2402Issues
i.1. Whether an arbitration agreement exists between the parties, given that the original Offer Letter contract contains no arbitration clause and the arbitration clause appears only in later bills.
¶ 11–19ii.2. Whether the difference between the clause invoked in the Invocation Notice (Clause 16.1) and the clause relied upon in the Application (Clause 13) is fatal to the Application.
¶ 20–26iii.3. Whether Applicant No.2, not a party to the original contract, can participate in the arbitration.
¶ 27–29, 71iv.4. Whether the alleged settlement dated 24 April 2026 has brought the disputes to an end, such that no arbitrable dispute remains.
¶ 30–57, 64–68v.5. Whether the allegations of meter tampering and theft must be examined in the Section 11 proceedings.
¶ 58–6303Law Applied
The Court relied on Section 11(6-A) of the Arbitration and Conciliation Act, 1996, under which the referral court's enquiry is confined to the existence of an arbitration agreement.
¶ 7, 11The Court followed SBI General Insurance Co. Ltd. v. Krish Spg., (2024) 12 SCC 1, which, relying on Duro Felguera (2017), Mayavati Trading (2019) and Vidya Drolia (2021), holds that accord and satisfaction and similar defences are ordinarily for the arbitral tribunal, and that refusal of reference is permissible only as a demurrer where claims are ex facie frivolous or non-arbitrable, applying the "eye of the needle" test (NTPC Ltd. v. SPML Infra Ltd., (2023) 9 SCC 385).
¶ 7–10, 47, 96 of Krish Spg. quoted at para. 10An arbitration clause may be introduced into a continuing contract by later agreement, which is to be determined from documents and conduct, and an invoice's printed conditions are not automatically binding.
¶ 14–15, 17Section 21 of the Act requires only notice that a party seeks arbitration of the dispute.
¶ 26The Court distinguished Ranjit Kantilal Shah v. Kruti Infrastructure, Arbitration Petition No. 55 of 2021 (Bom. HC, 15 June 2023), where a settlement was recorded in signed minutes, acted upon, and the arbitration notice abandoned after about two years.
¶ 50–56Provisions in the judgment · 4 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 11Section 12Section 21
Indian Partnership Act, 1932 Section 11
04Reasoning
On Issue 1, the Court held that the original Offer Letter does not exclude a later arbitration agreement; the Applicants rely on bills issued over several years, accepted and paid, containing the arbitration clause, and MGL's unilateral right to amend its terms does not by itself make every change binding. The question is therefore one for examination of documents and conduct, and prima facie an agreement exists.
¶ 14–19, 69On Issue 2, the Court acknowledged that the clause numbers and appointment mechanisms differ, but found that the Invocation Notice reproduced an arbitration clause, identified the PNG supply arrangement and the same disputes, and that MGL had responded substantively. The notice therefore served its purpose under Section 21, and the choice between Clauses 13 and 16.1 is left to the Tribunal.
¶ 21–26On Issue 3, separate legal identity and the mere fact that Applicant No.2 was named in the bills or paid money were held insufficient to establish that it is bound, so the question is reserved for the Tribunal. This does not prevent reference of Applicant No.1's disputes.
¶ 29, 71On Issue 4, the Court found that the settlement and the Applicants' protest letters present a genuine factual conflict regarding whether a final, voluntary settlement was reached. The Applicants' protest letters were sent before payment, and their claim of economic duress has some basis, so it cannot be dismissed as ex facie frivolous under the Krish Spg. test. MGL cannot simultaneously assert breach and liability while denying any dispute.
¶ 39–49, 56, 64–68The Invocation Notice, issued within about three weeks of restoration, also undercuts the claim of abandonment.
¶ 49, 55On Issue 5, the Court held that meter tampering and inspection evidence involve disputed facts requiring evidence. Such questions are for the Tribunal, though criminal liability remains outside its scope and MGL may pursue criminal remedies.
¶ 58–6305Holding
The Court held that an arbitration agreement exists, at least prima facie, for the PNG supply arrangement between Applicant No.1 and MGL, and that the disputes raised by Applicant No.1 arise out of or are connected with it. The alleged 24 April 2026 settlement is not shown to be a clear and undisputed full and final settlement, and the discrepancy between Clauses 13 and 16.1 is not fatal.
¶ 25–26, 69The Application is allowed. Mr. Harsh Moorjani, Advocate, is appointed Sole Arbitrator to adjudicate disputes between Applicant No.1 and MGL, including claims and counterclaims, under Consumer Reference No. 220000000876 / BP No. 1300000824. The Court directed communication of the Order to the Arbitrator, disclosure under Sections 11(8) and 12(1), an initial appearance for directions, and arbitral costs to be shared equally in the first instance. The questions of Applicant No.2's status, the validity and effect of the settlement, the existence and scope of the arbitration agreement, and all merits issues are left open for the Tribunal. No order as to costs.
¶ 70(A)–(F), 57, 72, 74Original Court PDF
Avenue Hotels Private LtdvsMahanagar Gas Limited
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in