Delhi High CourtContract LawAdministrative and Public Law

Security deposit retention under a contractual lien clause is invalid absent prior identification and communication of the claim.

M/S K.B. Enterprisesv.Hindustan Prefab Limited

Security deposit retention under a contractual lien clause is invalid absent prior identification and communication of the claim.. M/S K.B. Enterprises vs Hindustan Prefab Limited. Delhi High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the writ petition under Article 226 is maintainable, despite the Respondent's objections that the dispute is contractual, involves disputed questions of fact, and that an alternate remedy exists.

The court held

The writ petition is maintainable despite the contractual character of the dispute and the alternate-remedy objection, given the Respondent's conduct and the absence of any need for evidentiary inquiry.

It also directed

Clause 29A permits retention only where a claim is identified and duly communicated to the contractor. HPL failed to meet that requirement, and its retention of the Security Deposit was unjust.

The Court directed HPL to release the Security Deposit of ₹6,55,545 and the PBG of ₹7,42,500 (if not already released) within four weeks. The Court clarified that HPL may pursue any independently enforceable claim, including the GST liability or the alleged excess payment, in accordance with law and the contractual mechanism. The petition was disposed of accordingly.

01Facts

Hindustan Prefab Limited (HPL) issued a tender dated 03.01.2019 for construction of six single-officer accommodation units for Assam Rifles at Minuthong, Manipur. A Letter of Intent dated 19.02.2019 was issued to M/s K.B. Enterprises (the Petitioner) for ₹1,48,40,682.

¶ 2

The Petitioner furnished a Performance Bank Guarantee (PBG) of ₹7,42,500 and executed an agreement dated 20.04.2019.

¶ 3

The work was completed on 28.04.2021, inspected on 28.06.2021, and handed over to Assam Rifles on 30.06.2021.

¶ 4

The one-year defect liability period expired on 30.06.2022.

¶ 10, 20

A No Defect Certificate dated 20.07.2022 was issued by the client.

¶ 6

The Petitioner sought release of the PBG from October 2021 and of the Security Deposit (₹6,55,545) from July 2022, followed by reminders.

¶ 5, 7, 21

HPL's internal notings dated 13.09.2022 and 11.10.2022 recommended release of both amounts, and the Regional Office confirmed that the final bill had been released.

¶ 24–27

A GST notice (ASMT-10) dated 05.05.2022 concerning ineligible ITC for 2017–18 had been served on HPL, which replied on 03.06.2022.

¶ 23

A handwritten noting dated 10.02.2023 first referred to "pending GST action".

¶ 30

The Order in Original dated 22.12.2023 recorded no individual liability of the Petitioner, and the appeal was rejected on 08.01.2025.

¶ 32

Notice in the writ was issued on 05.02.2024.

¶ 9

Only on 29.02.2024 did HPL communicate a demand for an alleged excess payment of ₹14,82,054 and GST dues of ₹2,06,624, relying on Clause 29A.

¶ 14, 34

HPL stated that the PBG had been released and that the Security Deposit was retained under a lien.

¶ 15

02Issues

i.1. Whether the writ petition under Article 226 is maintainable, despite the Respondent's objections that the dispute is contractual, involves disputed questions of fact, and that an alternate remedy exists.

¶ 13, 18–19

ii.2. Whether HPL could withhold the Petitioner's Security Deposit and PBG by way of lien under Clause 29A, where no claim was identified or communicated to the Petitioner before the writ was filed.

¶ 35–37, 39–40

iii.3. Whether the continued retention of the Security Deposit and PBG, after completion of the work and expiry of the defect liability period, was unjust and arbitrary.

¶ 41–43

03Law Applied

ABL International Ltd. v. Export Credit Guarantee Corporation of India, (2004) 3 SCC 553, holds that a contractual dispute, disputed facts, or an alternate remedy do not bar Article 226 review where a State instrumentality's action is alleged to be arbitrary, unfair, or unreasonable.

¶ 18

Clause 29A of the contract permits the Engineer-in-Charge to withhold or retain any sum due to the contractor, including the Security Deposit, as a lien against claims arising under other contracts, until the claim is mutually settled, decided by arbitration, or determined by a competent court. The contractor is not entitled to interest on the withheld amount "duly notified" to it.

¶ 35

Clause 29A requires that the claim be identified and communicated, specifying the amount, the other contract, and the nature of the claim.

¶ 36–38

Clause 29A confers a right of retention, not an automatic right of appropriation.

¶ 41

Unitech Limited v. Telangana State Industrial Infrastructure Corporation, (2021) 16 SCC 35, requires that a State instrumentality must act fairly and reasonably.

¶ 41

Provisions in the judgment · 2

the Contract (alias, unresolved) Section 29ASection 25

04Reasoning

The Court declined to dismiss the petition on maintainability grounds. The petition had been pending since 2024, and the dispute turned on the Respondent's own records rather than on evidence requiring cross-examination.

¶ 19

The Court found that completion, handover, expiry of the defect liability period, and the No Defect Certificate were undisputed.

¶ 20

HPL's internal notings from 2022 recommended release and identified no GST liability or excess payment, although HPL had been aware of the GST proceedings since May 2022.

¶ 23–29

The first reference to any withholding appeared in the February 2023 noting, which fastened no liability on the Petitioner.

¶ 30–31

The GST Order in Original attributed no individual liability to the Petitioner.

¶ 32

The Court found that no claim was identified or communicated to the Petitioner before the writ was filed. The first communication asserting the excess payment and GST dues was dated 29.02.2024, after notice in the writ.

¶ 34, 39

Applying Clause 29A, the Court held that the retention was "mechanical" and made in anticipation of an uncrystallised claim, without notice.

¶ 40

HPL had also taken no step to have any claim adjudicated in the three years since completion.

¶ 41

The Court held that the Petitioner had already become entitled to release of both amounts when the belated claim was raised, and that continued retention was unjust in the circumstances.

¶ 42–43

05Holding

The writ petition is maintainable despite the contractual character of the dispute and the alternate-remedy objection, given the Respondent's conduct and the absence of any need for evidentiary inquiry.

¶ 18–19

Clause 29A permits retention only where a claim is identified and duly communicated to the contractor. HPL failed to meet that requirement, and its retention of the Security Deposit was unjust.

¶ 37–39, 43

The Court directed HPL to release the Security Deposit of ₹6,55,545 and the PBG of ₹7,42,500 (if not already released) within four weeks. The Court clarified that HPL may pursue any independently enforceable claim, including the GST liability or the alleged excess payment, in accordance with law and the contractual mechanism. The petition was disposed of accordingly.

¶ 44–46
Delhi High Court

Original Court PDF

M/S K.B. EnterprisesvsHindustan Prefab Limited

Delhi High Court · November 20, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment