01Facts
Hindustan Prefab Limited (HPL) issued a tender dated 03.01.2019 for construction of six single-officer accommodation units for Assam Rifles at Minuthong, Manipur. A Letter of Intent dated 19.02.2019 was issued to M/s K.B. Enterprises (the Petitioner) for ₹1,48,40,682.
¶ 2The Petitioner furnished a Performance Bank Guarantee (PBG) of ₹7,42,500 and executed an agreement dated 20.04.2019.
¶ 3The work was completed on 28.04.2021, inspected on 28.06.2021, and handed over to Assam Rifles on 30.06.2021.
¶ 4The one-year defect liability period expired on 30.06.2022.
¶ 10, 20A No Defect Certificate dated 20.07.2022 was issued by the client.
¶ 6The Petitioner sought release of the PBG from October 2021 and of the Security Deposit (₹6,55,545) from July 2022, followed by reminders.
¶ 5, 7, 21HPL's internal notings dated 13.09.2022 and 11.10.2022 recommended release of both amounts, and the Regional Office confirmed that the final bill had been released.
¶ 24–27A GST notice (ASMT-10) dated 05.05.2022 concerning ineligible ITC for 2017–18 had been served on HPL, which replied on 03.06.2022.
¶ 23A handwritten noting dated 10.02.2023 first referred to "pending GST action".
¶ 30The Order in Original dated 22.12.2023 recorded no individual liability of the Petitioner, and the appeal was rejected on 08.01.2025.
¶ 32Notice in the writ was issued on 05.02.2024.
¶ 9Only on 29.02.2024 did HPL communicate a demand for an alleged excess payment of ₹14,82,054 and GST dues of ₹2,06,624, relying on Clause 29A.
¶ 14, 34HPL stated that the PBG had been released and that the Security Deposit was retained under a lien.
¶ 1502Issues
i.1. Whether the writ petition under Article 226 is maintainable, despite the Respondent's objections that the dispute is contractual, involves disputed questions of fact, and that an alternate remedy exists.
¶ 13, 18–19ii.2. Whether HPL could withhold the Petitioner's Security Deposit and PBG by way of lien under Clause 29A, where no claim was identified or communicated to the Petitioner before the writ was filed.
¶ 35–37, 39–40iii.3. Whether the continued retention of the Security Deposit and PBG, after completion of the work and expiry of the defect liability period, was unjust and arbitrary.
¶ 41–4303Law Applied
ABL International Ltd. v. Export Credit Guarantee Corporation of India, (2004) 3 SCC 553, holds that a contractual dispute, disputed facts, or an alternate remedy do not bar Article 226 review where a State instrumentality's action is alleged to be arbitrary, unfair, or unreasonable.
¶ 18Clause 29A of the contract permits the Engineer-in-Charge to withhold or retain any sum due to the contractor, including the Security Deposit, as a lien against claims arising under other contracts, until the claim is mutually settled, decided by arbitration, or determined by a competent court. The contractor is not entitled to interest on the withheld amount "duly notified" to it.
¶ 35Clause 29A requires that the claim be identified and communicated, specifying the amount, the other contract, and the nature of the claim.
¶ 36–38Clause 29A confers a right of retention, not an automatic right of appropriation.
¶ 41Unitech Limited v. Telangana State Industrial Infrastructure Corporation, (2021) 16 SCC 35, requires that a State instrumentality must act fairly and reasonably.
¶ 41Provisions in the judgment · 2
the Contract (alias, unresolved) Section 29ASection 25
04Reasoning
The Court declined to dismiss the petition on maintainability grounds. The petition had been pending since 2024, and the dispute turned on the Respondent's own records rather than on evidence requiring cross-examination.
¶ 19The Court found that completion, handover, expiry of the defect liability period, and the No Defect Certificate were undisputed.
¶ 20HPL's internal notings from 2022 recommended release and identified no GST liability or excess payment, although HPL had been aware of the GST proceedings since May 2022.
¶ 23–29The first reference to any withholding appeared in the February 2023 noting, which fastened no liability on the Petitioner.
¶ 30–31The GST Order in Original attributed no individual liability to the Petitioner.
¶ 32The Court found that no claim was identified or communicated to the Petitioner before the writ was filed. The first communication asserting the excess payment and GST dues was dated 29.02.2024, after notice in the writ.
¶ 34, 39Applying Clause 29A, the Court held that the retention was "mechanical" and made in anticipation of an uncrystallised claim, without notice.
¶ 40HPL had also taken no step to have any claim adjudicated in the three years since completion.
¶ 41The Court held that the Petitioner had already become entitled to release of both amounts when the belated claim was raised, and that continued retention was unjust in the circumstances.
¶ 42–4305Holding
The writ petition is maintainable despite the contractual character of the dispute and the alternate-remedy objection, given the Respondent's conduct and the absence of any need for evidentiary inquiry.
¶ 18–19Clause 29A permits retention only where a claim is identified and duly communicated to the contractor. HPL failed to meet that requirement, and its retention of the Security Deposit was unjust.
¶ 37–39, 43The Court directed HPL to release the Security Deposit of ₹6,55,545 and the PBG of ₹7,42,500 (if not already released) within four weeks. The Court clarified that HPL may pursue any independently enforceable claim, including the GST liability or the alleged excess payment, in accordance with law and the contractual mechanism. The petition was disposed of accordingly.
¶ 44–46Original Court PDF