Supreme CourtProperty and Real Estate LawAdministrative and Public Law

Supreme Court appoints ex-judge Sanjay Karol to head verification of Okhla plot claims, as 866 verified buyers compete for about 150 vacant plots

Okhla Enclave Plot Holders Wel. Ason.v.Union Of India

Supreme Court appoints ex-judge Sanjay Karol to head verification of Okhla plot claims, as 866 verified buyers compete for about 150 vacant plots. Okhla Enclave Plot Holders Wel. Ason. vs Union Of India. Supreme Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether a new Chairperson should be appointed to reconstitute the Special Committee, which had become functus officio following the resignation of its Chairperson.

The court held

The Court appointed Justice (Retd.) Sanjay Karol as Chairperson of the reconstituted Special Committee and set its terms of reference: title scrutiny of Phase II claims under the 2019 cut-offs, audit of Phase I possession, allocation options including rezoning, investigation of the pre-verification building sanctions, and recovery of developer liabilities.

It also directed

The Court directed verification of General Category claims without the one-plot restriction.

The defaulting claimants were granted a final window to submit dossiers through the Nodal Officer by 20 November 2026, subject to final orders.

The Court held that OEPHFA members must submit dossiers and have no automatic exemption.

The Chairperson's honorarium was fixed at ₹60 lakh, with ₹20 lakh paid upfront by the State and recoverable from the Developer, and a ₹10,000 demand draft was required from late applicants.

Records are to be handed over within two weeks, and the Committee is to submit a sealed report within four months.

The Court disposed of MA Nos. 17124/2026, 812/2026 and 813/2026 and listed the matter for 2 March 2027.

The substantive questions in para. 53(iv)–(v), (vi), (x) and (xi)–(xii) remain open and were not finally decided.

01Facts

Between 1985 and 1991, M/s Durga Builders Pvt. Ltd. (the "Developer") acquired about 235 acres in Sector 91, Faridabad, for a colony styled "Okhla Enclave" (later "Edenburg City"). Seven colonisation licences were granted under the 1975 Act, and a Bilateral Agreement dated 2 December 1991 divided plots into EWS (20%), NPNL (25%) and General (55%) categories.

¶ 4–5

The Developer defaulted on development works, licence renewal fees and EDC, made excess and duplicate allotments, and its licences expired in 1999 without renewal.

¶ 7

Writ petitions were filed under Article 32 in 1996.

¶ 9

The High Court's 2002 judgment, affirmed by this Court on 4 January 2008, extended parity to 567 further allottees.

¶ 10

A Court Commissioner, then a Special Committee and a Scrutiny Committee were appointed. This Court's judgment of 3 October 2019 approved the eligibility criteria (land cost paid by 7 April 1997; development charges by 31 December 1999; one plot per family).

¶ 15–17

Phase I verified 1,011 allottees by order of 11 July 2023.

¶ 19

The 25 April 2025 order directed Phase II scrutiny of 480 unverified petitioners, modified the 2019 judgment to let General Category multi-plot holders participate, and directed the State to take further steps.

¶ 20

Despite the 2025 restraint, DTCP sanctioned building plans for unverified claimants up to 25 March 2025.

¶ 21

Justice (Retd.) Vikramajit Sen resigned as Chairperson, and the 18 May 2026 order imposed a restraint on transfers and building permissions.

¶ 22–24

The State's compliance affidavit and Nodal Officer process followed.

¶ 26–28

Phase I allottees face a physical deficit: 866 NPNL allottees compete for about 150 vacant plots, and 49 General allottees for one.

¶ 51, 53(iii)

02Issues

i.1. Whether a new Chairperson should be appointed to reconstitute the Special Committee, which had become functus officio following the resignation of its Chairperson.

¶ 53(i), 54

ii.2. Whether a comprehensive framework should be evolved to resolve the supply–demand mismatch in plot allocation, including rezoning or conversion of EWS land bank into NPNL plots or group housing.

¶ 53(iv)–(v)

iii.3. Whether the 25 April 2025 modification exempting General Category holders from the one-plot-per-family rule requires revisiting.

¶ 53(vi)

iv.4. Whether the 74 defaulting original petitioners deserve a final opportunity to submit title documents.

¶ 53(vii)

v.5. Whether the 567 OEPHFA members are exempt from Phase II re-scrutiny on the strength of the High Court's 2002 judgment.

¶ 53(viii)

vi.6. Whether building plans sanctioned by DTCP before 25 March 2025 are void ab initio, and what remedial measures follow.

¶ 53(x)

vii.7. Whether the Developer's dues and the allottees' development-charge deposits require recovery and audit.

¶ 53(xi)–(xii)

03Law Applied

The Court's jurisdiction rests on Article 32 of the Constitution and its continuing supervision of its own judgments of 3 October 2019 and 25 April 2025.

¶ 2, 17, 20

Under the 1975 Act, Section 3 governs colonisation licences and Section 8(4) governs conveyance on payment of development charges.

¶ 5, 18

The Bilateral Agreement of 2 December 1991 fixes the 20:25:55 category ratio and cross-subsidy objective.

¶ 5–6

The eligibility parameters (cut-off dates and one-plot-per-family rule) affirmed in the 2019 judgment, as modified in 2025, are final and not open to re-agitation.

¶ 52(i)

The crystallised rights of 1,011 Phase I allottees, confirmed by the 11 July 2023 order, are final.

¶ 52(ii)

Interim protective orders or paper conveyances cannot dispense with a rigorous title audit.

¶ 52(iii)

A Committee whose mandate is complete becomes functus officio and must be reconstituted to continue.

¶ 53(i)

The judgment cites no external precedent.

Provisions in the judgment · 2

Haryana Development and Regulation of Urban Areas Act, 1975 Section 3Section 8

04Reasoning

The Court treated the eligibility criteria and the Phase I list as settled, so it confined its inquiry to continuity and process.

¶ 52–53

It found that the Special Committee had become functus officio after the resignation of its Chairperson. It therefore appointed Justice (Retd.) Sanjay Karol and vested in him all administrative, supervisory and adjudicatory powers, with autonomy to frame procedure.

¶ 54, 58(g), 59

To address the 2025 irregularities, the Court directed the Committee to investigate the pre-verification building sanctions and recommend remedies, without itself declaring them void.

¶ 58(e)

Against the OEPHFA claim of automatic parity, the Court held that because all original petitioners were directed to undergo verification, the Forum members could not claim exemption from scrutiny.

¶ 57

The 74 defaulting claimants were given a three-week window, with any allotment subject to final orders.

¶ 56

On the one-plot rule, the Court directed that General Category claims be verified "unfettered" by that restriction, which gives effect to the 2025 modification without expressly revisiting it.

¶ 55

The rezoning, plot-distribution scheme, void-ab-initio question and recovery of dues were referred to the Committee for examination and report, so the Court did not decide them on the merits.

¶ 58(c), (f)

05Holding

The Court appointed Justice (Retd.) Sanjay Karol as Chairperson of the reconstituted Special Committee and set its terms of reference: title scrutiny of Phase II claims under the 2019 cut-offs, audit of Phase I possession, allocation options including rezoning, investigation of the pre-verification building sanctions, and recovery of developer liabilities.

¶ 54, 58(a)–(f)

The Court directed verification of General Category claims without the one-plot restriction.

¶ 55

The defaulting claimants were granted a final window to submit dossiers through the Nodal Officer by 20 November 2026, subject to final orders.

¶ 56

The Court held that OEPHFA members must submit dossiers and have no automatic exemption.

¶ 57

The Chairperson's honorarium was fixed at ₹60 lakh, with ₹20 lakh paid upfront by the State and recoverable from the Developer, and a ₹10,000 demand draft was required from late applicants.

¶ 64

Records are to be handed over within two weeks, and the Committee is to submit a sealed report within four months.

¶ 61, 65

The Court disposed of MA Nos. 17124/2026, 812/2026 and 813/2026 and listed the matter for 2 March 2027.

¶ 66, 68

The substantive questions in para. 53(iv)–(v), (vi), (x) and (xi)–(xii) remain open and were not finally decided.

¶ 53(iv)–(v), (vi), (x), (xi)–(xii)
Supreme Court

Original Court PDF

Okhla Enclave Plot Holders Wel. Ason.vsUnion Of India

Supreme Court · November 20, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment