01Facts
The petitioner was awarded the renovation and upgradation of the Surkhi Podi Reservoir, owned by the Department of Water Resources, Government of Madhya Pradesh.
¶ 3Respondents 3 to 6 issued proforma No. 105 (Annexure P-8), recommending termination of the contract under clause 27.2(g).
¶ 2, 3The petitioner contends that this was done without a hearing, in violation of natural justice; that clause 27.2(g) does not apply because he did not engage in corrupt or fraudulent practices in executing the agreement; and that the work was completed.
¶ 3The allegation against the petitioner is that he encashed and closed the FDRs furnished as performance security and additional performance security.
¶ 6The petitioner admitted the encashment in his reply dated 18.08.2026 to the notice dated 14.08.2026, and later sought, by representation dated 25.09.2026 (Annexure P-5), foreclosure of the contract without punitive action.
¶ 6The State contended that the petition is premature, that the dispute is purely contractual, that proforma No. 105 is only a recommendation with no final order, and that clause 12 of the tender document provides the remedy.
¶ 402Issues
i.1. Whether a writ petition challenging a mere recommendation for termination of contract, with no final order passed, discloses a valid cause of action.
¶ 5ii.2. Whether the petitioner should be relegated to the dispute resolution mechanism under clause 12 of the tender document, rather than obtaining relief under writ jurisdiction.
¶ 7, 8, 9, 1003Law Applied
A writ petition filed in anticipation of an order cannot be entertained, and no indulgence can be granted on such a petition.
¶ 5Clause 12 of the tender document provides a sequential dispute resolution mechanism: a dispute must be raised before the Competent Authority within 45 days of first occurrence (cl. 12.1, 12.2); the Competent Authority decides within 45 days (cl. 12.3); appeal lies to the Appellate Authority within 30 days (cl. 12.4); a further appeal lies to the Madhya Pradesh Arbitration Tribunal under the MP Madhyastham Adhikaran Adhiniyam, 1983 (cl. 12.5); and the contractor must continue execution pending the dispute (cl. 12.6).
¶ 7, 8The judgment cites no judicial precedent for the propositions relating to the availability of alternative contractual remedies.
04Reasoning
The Court first noted that only a recommendation for termination had been made and that no termination order existed.
¶ 5The Court concluded that the petitioner had no present cause of action and that the petition appeared to have been filed in anticipation of a termination order.
¶ 5The Court did not examine the merits of the natural justice challenge or the applicability of clause 27.2(g).
¶ 3, 5Even if an adverse order were later passed, the petitioner would have an adequate remedy under clause 12, which provides a complete, staged mechanism for adjudication of contractual disputes.
¶ 7, 8, 9The Court treated the dispute as contractual and capable of resolution within the contractual framework, and found no ground for interference at that stage.
¶ 9, 1005Holding
Because only a recommendation for termination exists and no final order has been passed, the petitioner has no valid cause of action, and alternative contractual remedies under clause 12 bar interference at this stage.
¶ 5, 9, 10The petition is dismissed, with liberty to the petitioner to pursue remedies under clause 12 of the tender document upon arising of a valid cause of action. No finding is recorded on the merits of the termination recommendation, the natural justice claim, or the applicability of clause 27.2(g).