01Facts
The petitioner No. 1, a co-operative society, bid for a tender floated on 12 October 2012 by the District Project Officer (DPO), Sarva Shiksha Mission, Murshidabad, for wall writing work across the district. The work order was issued on 18 March 2013.
¶ 1By memo dated 8 May 2013, the petitioners were informed that the rate per wall was Rs. 631.27 and the total bill for 26 blocks was Rs. 38,49,484, to be billed block-wise.
¶ 2A Block Development Officer certified completion of work at the CPC, Bhagwangola-II block.
¶ 3The petitioners submitted bills, requested payment on 11 November 2013, and sent a reminder on 22 September 2013.
¶ 4Further representations dated 30 October 2013, 22 January 2014 and 26 May 2014 went unanswered. The petitioners then filed W.P. 23673(W) of 2014, and on 16 June 2015 a coordinate Bench directed the DPO to consider payment after hearing the petitioners.
¶ 5By order dated 13 August 2015, the DPO rejected the claim. He recorded that only 1,274 of 6,098 walls were completed, that the remaining 4,824 walls were not executed per specification, and that the writing was poor, done by stencil rather than by hand, and not in Asian Paints colour. He directed the petitioners to redo all 6,098 walls.
¶ 6The petitioners challenged that order in this writ petition.
¶ 7The State contended that only 4,824 walls were completed, and those in violation of the tender specifications.
¶ 902Issues
i.1. Whether the DPO's order dated 13 August 2015, a quasi-judicial order, is liable to be interfered with under the limited scope of writ review (arbitrariness, perversity, excess of jurisdiction, violation of natural justice, or unreasonableness).
¶ 11–12ii.2. Whether the DPO could, after an unexplained delay of about one and a half years, rely on alleged deficiencies in the quality of work to deny payment for work completed before November 2013.
¶ 14–16iii.3. Whether the petitioners are entitled to payment for the 4,824 walls executed, and whether disputed questions concerning the remaining walls can be decided in writ proceedings.
¶ 13, 17–1903Law Applied
The court applied the established principles of judicial review of administrative and quasi-judicial orders, under which a writ court may interfere if the order is arbitrary or perverse, the authority has exceeded its jurisdiction, natural justice has been violated, or no reasonable authority could have reached the decision.
¶ 11The principle that a public authority must decide claims within a reasonable time, and that a failure to do so amounts to arbitrariness.
¶ 15The maxim that an authority cannot take advantage of its own inaction, so a belated plea of defective execution cannot defeat a claim when the authority neither inspected the work nor held an enquiry at the relevant time.
¶ 15–16The principle that writ proceedings are not suited to disputed questions of fact, which must be left to a civil suit.
¶ 19No specific statutory provisions or precedents are cited in the judgment.
04Reasoning
The court held that the petitioners had not shown any procedural impropriety in the DPO's order, but found that the order could not stand on the merits.
¶ 12The DPO admitted that 4,824 walls had been completed, but the deficiencies he relied on were recorded in August 2015, more than one and a half years after the work was finished and after the petitioners' November 2013 payment request.
¶ 13–14No inventory or enquiry was conducted during the relevant period, and the DPO did not decide the bills within a reasonable time despite repeated representations and the earlier writ direction. The court characterised this inaction as an arbitrary approach that deprived the petitioners of a legitimate claim.
¶ 15Applying the maxim that the authority cannot take advantage of its own inaction, the court refused to accept the belated quality objection.
¶ 16For the 4,824 walls, the court found no genuine dispute requiring evidence and ordered payment. For the remaining walls, the court found that the questions involved disputed facts and left the petitioners to a civil suit.
¶ 17, 1905Holding
The DPO's order dated 13 August 2015 was arbitrary and is set aside, because the authority's unexplained delay of about one and a half years, with no inventory or enquiry, precluded a belated plea of poor quality.
¶ 15–17The court directed the DPO to release the proportionate amount for the 4,824 walls within two weeks of communication of the order, with 10% per annum interest from 11 November 2013 until actual disbursement.
¶ 18As to the remaining walls, the petitioners may file a civil suit, as those issues involve disputed questions of fact. The writ petition is disposed of with no order as to costs.
¶ 19–21Original Court PDF
BHAGIRATH ENGINEERS COOP. SERVICE CONSTR. SOCIETY LTD & ANRvsSTATE OF WEST BENGAL & ORS
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in