01Facts
An expert committee constituted by KPCL determined the base excavation charge at ₹1,169.16 per tonne in 2017.
pp. 3–5Following related proceedings, Petitioner No. 1 and KPCL entered into an agreement on 19 March 2021. Clause 28.1.1(ii) provided for quarterly revision of the base excavation charge, commencing from the first quarter after the agreement was signed.
pp. 8–10The petitioners sought to replace that commencement date with the first quarter after ECL accepted the committee report in May 2017, and sought recalculation of charges with 18% annual interest. They alleged that the agreement had been signed under economic duress.
pp. 5–6, 11–1202Issues
i.Whether the Court could direct KPCL to modify Clause 28.1.1(ii) of the signed agreement so that quarterly escalation commenced from May 2017 rather than after the agreement was signed in March 2021.
pp. 11–12ii.Whether the petitioners could avoid the agreed terms on the ground that the agreement was signed under economic duress.
pp. 12–1303Law Applied
The Court applied the terms of the parties’ agreement, particularly Clause 28.1.1(i)–(ii), which fixed the base excavation charge at ₹1,169.16 per tonne and provided for quarterly revision from the first quarter after the agreement’s signing date.
pp. 3–5It held that a party could not resile from a signed agreement and compel the other party to accept terms at variance with it; an unsubstantiated allegation of economic duress was insufficient to justify that result.
pp. 12–13Although the dispute arose against the background of proceedings under the Coal Mines (Special Provisions) Act, 2015, and earlier litigation, the Court cited no statute or precedent as the basis for its decision on the requested contractual modification.
pp. 7–10Provisions in the judgment · 1
Companies Act, 2013 Section 11
04Reasoning
The agreement expressly tied quarterly revision to the period following its signing, while separately specifying the base excavation charge determined by the expert committee. The petitioners’ requested implementation of the committee report would therefore require the agreement to be modified, rather than merely enforced according to its terms.
pp. 3–6, 11–12The Court rejected the duress allegation because the parties were then before the Supreme Court, where the petitioners could have raised any coercion, and because the petitioners produced no material substantiating economic duress.
p. 13It also held that the petitioners could not challenge the base rate expressly agreed in the contract.
p. 1305Holding
The Court answered the issues against the petitioners. It found no merit in the request to modify the agreement, recalculate excavation charges from May 2017, or award interest.
p. 13The writ petition was dismissed, and the pending interlocutory application was disposed of.