Kerala High CourtProperty and Real Estate LawAdministrative and Public Law

Kerala HC Bars RERA Authorities From Probing Hoysala EVM's Occupancy Certificate; Allottee Claims Proceed

M/S HOYSALA PROJECTS PRIVATE LIMITED,v.SANTHOSH KUMAR

Kerala HC Bars RERA Authorities From Probing Hoysala EVM's Occupancy Certificate; Allottee Claims Proceed. M/S HOYSALA PROJECTS PRIVATE LIMITED, vs SANTHOSH KUMAR. Kerala High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether non-compliance with Regulation 21(4), arising solely from failure to afford an opportunity to file objections on an inspection report, has any legal consequence in finding that the project building is complete on the basis of an OC.

The court held

Question (A) is answered by holding that the breach of Regulation 21(4) has no consequence for the completion finding, which rests on the OC.

It also directed

Questions (B) and (C) are answered in the appellants' favour: the Authority and the Tribunal cannot disregard the OC, and the Tribunal could not depart from Nidhish P.V. and Siji Jacob.

Question (D) is answered by holding that a procedural defect alone does not justify reopening the completion finding, though other RERA adjudication may proceed.

The Tribunal's order is modified. It is declared that RERA authorities shall not enquire into the legality of the OC dated 10.05.2023 or whether the building is complete as per permit and fit for occupation. Subject to that, K-RERA shall adjudicate all other questions under the RERA Act and endeavour to dispose of the complaints within the timeline fixed in MSA No. 40 of 2026 (judgment dated 11.09.2026).

The appeals are disposed of and all pending interlocutory applications are closed.

01Facts

The appellants, promoters of the "Hoysala EVM" project, challenged a common order of the Kerala Real Estate Appellate Tribunal, which had set aside the Kerala Real Estate Regulatory Authority's (K-RERA) order. The respondents are allottees who filed complaints seeking sale deeds, delay interest and other reliefs.

¶ 1

The promoters contended that the project was complete, that an Occupancy Certificate (OC) dated 10.05.2023 had been issued and intimated to allottees, and that the complaints were filed about one and a half years later, when cancellation under Section 11(5) of the RERA Act was being initiated.

¶ 2

The allottees alleged that the project was not complete, that common areas were not registered to the Association, and that parking slots were not allotted.

¶ 3

K-RERA held the completion-related relief not maintainable, but held the other reliefs maintainable and treated the project as complete in all respects, based on the OC and Form 6 on its portal.

¶ 4

The Tribunal found a breach of Regulation 21(4) of the Kerala RERA (General) Regulations, 2020 and Rule 36 of the Kerala RERA Rules, 2018, because no notice was given before two Deputy Directors inspected the project. It also held that the completion relief was maintainable, relied on Nidhish P.V. v. Sivaprakash to the extent distinguished on allegations of fraud, and directed K-RERA to consider the complaints in toto.

¶ 5

Show-cause notices regarding cancellation of the OC were noted.

¶ 5

The promoters appealed.

¶ 6

02Issues

i.1. Whether non-compliance with Regulation 21(4), arising solely from failure to afford an opportunity to file objections on an inspection report, has any legal consequence in finding that the project building is complete on the basis of an OC.

¶ 7(A)

ii.2. Whether the Tribunal and the Authority can disregard an OC issued by the competent authority and rely on other materials to determine completion of a project building under the RERA Act.

¶ 7(B)

iii.3. Whether the Tribunal can ignore the dictum in Nidhish P.V. and Siji Jacob v. Ultima Builders that an OC is conclusive proof of completion, and direct K-RERA to rely on other materials.

¶ 7(C)

iv.4. Whether an Appellate Authority, on finding a procedural defect, can permit or direct reopening of a completion finding made on the strength of an OC, without recording that such an exercise was illegal, without jurisdiction or otherwise invalid.

¶ 7(D)

03Law Applied

The Kerala Municipality Building Rules, 2019 provide that an OC is issued by the municipal Secretary on completion of construction as per permit (Rules 19C, 20(1), 20(3)), with deemed-OC and partial-occupancy provisions (Rules 20(4)–(5)).

¶ 12–13

Under the RERA Act, "occupancy certificate" and "completion certificate" are defined (Section 2(zf), 2(q)), and the promoter must obtain the certificate and make it available to allottees (Section 11(4)(b)).

¶ 15–16

The promoter must execute conveyances, hand over possession and common areas (Section 17), pay interest for delay (Section 18), answer for defects (Section 14(3)), and face cancellation regulation (Section 11(5)), with complaints under Section 31.

¶ 15–16

The court relied on Nidhish P.V. v. Sivaprakash (2024 KHC 7050) and Siji Jacob v. Ultima Builders and Developers Pvt. Ltd. (2023 KHC 9214) for the principle that the legality of an OC under the Building Rules cannot be questioned before RERA authorities, and that the OC certifies construction per permit and fitness for occupation.

¶ 9, 19

Regulation 21(4) of the 2020 Regulations and Rule 36 of the 2018 Rules, on notice before inspection, were considered in relation to the inspection.

¶ 5, 21

Provisions in the judgment · 7 · Linked ones open on LawLens

Real Estate (Regulation and Development) Act, 2016. Section 11Section 3Section 17Section 2Section 18Section 14Section 31

04Reasoning

The Building Rules and the RERA Act operate in different fields. The Building Rules ask whether the building was built as permitted and is safe to occupy, and the OC is the end product of that process. The RERA Act asks whether the promoter performed his statutory obligations to allottees, and the OC is only an input and trigger for those duties.

¶ 17

"Completion" carries two meanings: completion per permit, which the OC settles, and completion in the RERA sense, which includes the promoter's obligations and is not settled by the OC.

¶ 18

Because the legality of the OC, and whether the building is complete per permit and fit for occupation, cannot be examined by RERA forums, and because an allegation of fraud does not enlarge their jurisdiction, the authorities cannot re-examine these matters.

¶ 19

The respondents' grievances about common areas, parking slots, sale deeds and interest for delay fall within the RERA Act and remain open to the allottees.

¶ 20

The Deputy Directors' inspection was aimed at determining completion, an enquiry outside the Authority's purview. Hence, the want of notice before that inspection could not justify reopening a finding resting on the OC.

¶ 21

The respondents' argument that Nidhish concerned registration rather than reliefs was noted, but the court's answer to Question (C) proceeded on the OC-conclusiveness principle.

¶ 11, 22

05Holding

Question (A) is answered by holding that the breach of Regulation 21(4) has no consequence for the completion finding, which rests on the OC.

¶ 22

Questions (B) and (C) are answered in the appellants' favour: the Authority and the Tribunal cannot disregard the OC, and the Tribunal could not depart from Nidhish P.V. and Siji Jacob.

¶ 22

Question (D) is answered by holding that a procedural defect alone does not justify reopening the completion finding, though other RERA adjudication may proceed.

¶ 22

The Tribunal's order is modified. It is declared that RERA authorities shall not enquire into the legality of the OC dated 10.05.2023 or whether the building is complete as per permit and fit for occupation. Subject to that, K-RERA shall adjudicate all other questions under the RERA Act and endeavour to dispose of the complaints within the timeline fixed in MSA No. 40 of 2026 (judgment dated 11.09.2026).

¶ 22

The appeals are disposed of and all pending interlocutory applications are closed.

¶ 22
Kerala High Court

Original Court PDF

M/S HOYSALA PROJECTS PRIVATE LIMITED,vsSANTHOSH KUMAR

Kerala High Court · November 18, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment