01Facts
ISRO awarded RVR Projects an EPC contract for an Integrated Titanium Alloy Tank Production Facility at Tumakuru.
¶ 3–8, 11–14RVR claimed payment for additional works, including an enlarged cable trench, mezzanine-floor work exceeding the tender quantity, and related BOQ items.
¶ 3–8, 11–14ISRO disputed liability, relying on Clause 12 of the General Conditions of Contract (GCC), which governed variations and additional costs.
¶ 3–8, 11–14The Commercial Court decreed RVR’s claim for Rs.6,92,87,650, but did not award the interest sought.
¶ 3–8, 11–14ISRO appealed; RVR filed a cross-objection seeking interest at 18% per annum, which was delayed by 316 days.
¶ 15–18, 27–2902Issues
i.1. Whether the Commercial Court’s decree for the claimed additional works was sustainable in light of Clause 12 of the GCC and the evidence of departmental approval and payment.
¶ 18 · ¶ 19–25ii.2. Whether RVR was entitled to interest at 18% per annum on its claim.
¶ 27–2903Law Applied
The Court applied Clause 12 of the GCC, which required the contractor to follow the Department-approved drawings and designs and required variations to be specifically approved; absent such approval, variations were to be carried out at no extra cost where the cost was deemed included in the contract price.
¶ 19A party claiming payment for additional work must establish not merely that the work was physically executed, but that it fell outside the contractual scope, was undertaken pursuant to a duly authorised departmental variation, and was properly measured and valued.
¶ 20–24The judgment cited no judicial precedents.
Section 13(1-A) of the Commercial Courts Act provided the basis for the appeal, and Order XLI Rule 22 CPC was invoked for the cross-objection.
pp. 1–2Provisions in the judgment · 1 · Linked ones open on LawLens
Commercial Courts Act, 2015 Section 13
04Reasoning
The Court held that the tender documents and Clause 12 required prior departmental approval for the disputed variations.
¶ 20–24RVR produced no contemporaneous written instruction or approval for the principal cable-trench and mezzanine claims; the later preparation of extra-item statements and evidence that some other extra works had been accepted did not establish entitlement to all disputed amounts.
¶ 20–24The Commercial Court had not adequately distinguished approved extra work from work already within the EPC scope, nor established the contractual basis and valuation of each claimed item.
¶ 21–24Because the consequential claims depended on the alleged additional mezzanine and cable-trench work, they also could not independently sustain the decree.
¶ 21–24With the suit dismissed, the interest claim did not survive; the cross-objection was also barred by the unexplained 316-day delay.
¶ 28–2905Holding
The High Court allowed ISRO’s appeal, set aside the Commercial Court’s judgment and decree dated 15 October 2024, and dismissed RVR’s suit for Rs.6,92,87,650.
¶ 26 · order · ¶ (ii)RVR’s cross-objection for interest was dismissed on the merits and for delay.
¶ 28–29 · order · ¶ (iii)The final order directed that the parties bear their respective costs.