In brief

The question

1. Whether the interest component of the arbitral award survives the Court's partial setting aside under Section 34, such that it is enforceable against NTPC.

The court held

The Court held that NTPC's contention that no interest is payable is untenable. Interest at 10% survives, because the Section 34 judgment set aside only the additional expenditure component.

It also directed

The Court accepted the Decree Holder's calculation sheet and directed NTPC to pay the due amount shown in it within four weeks from uploading of the judgment, with 10% interest until actual payment.

The execution petition was disposed of along with pending applications.

01Facts

The Decree Holder (L&T MHI Power Boilers, the claimant) and the Judgment Debtor (NTPC, the respondent) were parties to an arbitration. By a majority award dated 25.06.2020, the Tribunal directed NTPC to pay ₹7.104 crores with 10% interest per annum from the date of filing the claim until payment, and ₹50,00,000 as costs.

¶ 2 · pp. 1–2

The Tribunal also permitted L&T to prove expenditure exceeding the awarded amount, to be examined by both parties and certified by a Chartered Accountant, with 10% interest on any sum so determined.

¶ 2 · pp. 1–2

Both parties challenged the award under Section 34 (OMP (COMM) 535/2020 and 567/2020). By judgment dated 29.11.2021, the Court partly upheld the award and set aside the portion granting the additional expenditure amount, subject to examination and Chartered Accountant certification.

¶ 3 · p. 2

NTPC's appeal under Section 37 (FAO (OS) (COMM) 45/2022) was dismissed by a Division Bench on 18.07.2023, and the award was therefore treated as final.

¶ 4 · p. 3

L&T now seeks enforcement under Section 36 for the amount due as on 05.09.2026, computed in a chart that is not reproduced in the text.

¶ 5 · p. 3

NTPC contended that no interest was payable because the interest component had been set aside.

¶ 6 · p. 3

02Issues

i.1. Whether the interest component of the arbitral award survives the Court's partial setting aside under Section 34, such that it is enforceable against NTPC.

¶ 6–8 · pp. 3–4

ii.2. Whether the Decree Holder's calculation sheet for the amount due is to be accepted for execution.

¶ 9 · p. 4

03Law Applied

The Court proceeded under Section 36 of the Arbitration and Conciliation Act, 1996, which governs enforcement of an arbitral award as a decree.

¶ 1 · p. 1

Only the portion of an award expressly set aside under Section 34 ceases to be enforceable, and the remainder continues to bind the judgment debtor.

¶ 7–8 · pp. 3–4

The Court read the operative part of its earlier Section 34 judgment, which set aside the award "to the extent it directs NTPC to examine L&T's claim once again and pay the same along with interest at the rate of 10% per annum or pay the amount as certified by the Chartered Accountant along with interest".

¶ 7 · pp. 3–4

The finality of the 29.11.2021 judgment, as affirmed on appeal under Section 37, was relied upon by the Court.

¶ 4 · p. 3

No precedents are cited in the judgment.

Provisions in the judgment · 3 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 36Section 34Section 37

04Reasoning

NTPC's argument that all interest was set aside depends on reading the Section 34 judgment as wholesale. The Court rejected that reading.

¶ 8 · p. 4

The Court held that the 29.11.2021 judgment set aside only the portion granting expenditure in addition to ₹7.104 crores, which was subject to examination and Chartered Accountant certification. The principal award amount of ₹7.104 crores and its 10% interest therefore survived and remained enforceable.

¶ 8 · p. 4

Because the Section 37 appeal was dismissed, the award's surviving components had become final.

¶ 4 · p. 3

The Court accepted the Decree Holder's calculation sheet, subject to the statutory basis of that computation being confirmed by the operative order.

¶ 9 · p. 4

05Holding

The Court held that NTPC's contention that no interest is payable is untenable. Interest at 10% survives, because the Section 34 judgment set aside only the additional expenditure component.

¶ 7–8 · pp. 3–4

The Court accepted the Decree Holder's calculation sheet and directed NTPC to pay the due amount shown in it within four weeks from uploading of the judgment, with 10% interest until actual payment.

¶ 9 · p. 4

The execution petition was disposed of along with pending applications.

¶ 10 · p. 4
Delhi High Court

Original Court PDF

L And T Mhps Boilers Pvt. Ltd.vsNtpc Ltd.

Delhi High Court · November 20, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment